Forensic Quantity Surveying (FQS) is the specialized practice of investigating, analyzing, and resolving financial and contractual disputes in construction projects. It combines traditional quantity surveying skills—cost estimation, contract management, and project valuation—with forensic techniques to uncover the truth behind delays, cost overruns, defects, and breaches of contract. Think of it as "construction detective work," where you dissect project records, schedules, and financial data to determine what went wrong, who’s responsible, and what it costs.
Delay Analysis: Unraveling project delays to assign blame (e.g., weather vs. contractor negligence).
Cost Overrun Investigations: Tracing budget explosions to design flaws, material waste, or scope changes.
Defect Liability Assessment: Quantifying repair costs for faulty work and assigning responsibility.
Disruption Quantification: Measuring productivity loss due to chaos like design changes or resource shortages.
Claims Validation: Verifying if contractor claims for extras or delays are legitimate.
Reality: 1 in 3 projects faces disputes exceeding $10M (e.g., delayed skyscrapers, defective bridges).
Consequence: Without FQS skills, you risk:
Profit Erosion: A single dispute can wipe out 20–30% of project margins.
Career Vulnerability: Senior roles demand dispute-resolution expertise.
Example: A hospital project in Dubai faced 120+ design changes. The contractor’s team, untrained in FQS, couldn’t prove 70% were client-caused → lost $8M in claims.
FQS teaches you to spot red flags before they explode:
Documentation Gaps: Missing change orders or site diaries.
Schedule Weaknesses: Float mismanagement or unrealistic critical paths.
Real Scenario: A highway contractor in Australia used FQS protocols to flag poor soil reports before foundation work. This prevented $3M in rework.
Modern projects face:
Cross-Border Risks: Currency crashes, geopolitical chaos.
Cultural Pitfalls: Hierarchical decision-making in the Middle East vs. consensus-driven cultures in Scandinavia.
Example: A U.S. engineer in Saudi Arabia misinterpreted "approval delays" as inefficiency. FQS training revealed it was cultural protocol → saved the relationship and $500K in claims.
FQS expertise lets you:
Lead Dispute Resolution Teams: Direct mediators, arbitrators, or legal teams.
Defend Your Decisions: Use data to justify cost/time positions to clients.
Case Study: A QS in Singapore became CEO after uncovering $12M fraud in a rail project using forensic cost auditing.
Project: $200M Power Plant in Texas.
Crisis: 90-day delay blamed on contractor.
FQS Intervention:
Analyzed schedules, emails, weather logs.
Proved 60 days were due to client’s late equipment deliveries.
Outcome: Contractor recovered $4.5M in delay costs.
Project: Luxury Condos in Sydney.
Issue: Cracks in balconies post-handover.
FQS Process:
Traced defects to design flaws (not construction).
Quantified repair costs: $1.2M + $400K for tenant relocation.
Result: Design firm’s insurance covered 100%.
Project: Oil Refinery in Saudi Arabia.
Claim: Contractor sought $15M for "cumulative disruptions."
FQS Tactic:
Used Measured Mile Analysis to prove only 40% loss was valid.
Exaggerated costs were rejected.
Savings: Client paid $6M instead of $15M.
Bhadanis Quantity Surveying Online Course isn’t just theory—it’s a battle-tested toolkit for senior professionals. Here’s why it stands out:
Real Case Studies: Work on 50+ real disputes (e.g., airport delays, hospital defects).
Templates You Use Tomorrow:
Delay culpability scorecards.
Defect classification matrices.
Quantum calculation models.
BIM Clash Detection: Find design conflicts in 3D models.
Drone Data Analysis: Measure delays from aerial progress photos.
AI Document Review: Uncover critical evidence in 10,000+ emails.
FIDIC/NEC/JCT Contracts: Decode clauses like a lawyer.
Cross-Border Enforcement: Recover debts from Dubai to Australia.
Currency Risk Shields: Hedge against inflation or currency crashes.
Draft bulletproof reports judges understand.
Survive cross-examination with confidence.
Navigate conflicts of interest.
Reject pressure to manipulate data.
Industry-Led Training: Courses designed by dispute resolution experts who’ve handled $1B+ claims.
Immediate ROI: Apply skills to recover losses or prevent disputes in your current projects.
Flexibility: 100% online, with 24/7 mentor support.
Senior professionals: In an era where 65% of mega-projects face disputes, FQS isn’t a "nice-to-have"—it’s your shield and sword.