Types of Measurement in Civil Engineering

In civil engineering, accurate measurement is essential for project planning, cost estimation, resource allocation, and quality control. There are various types of measurements used depending on the type of work and the specific requirements of the construction project. These measurements help ensure the consistency, quality, and efficiency of the construction process.

Common Types of Measurement in Civil Engineering

  1. Measurement by Area:

    • This measurement is used to quantify the surface work, and it is usually measured in square meters (m²). It is common for works such as:
      • Flooring (e.g., tiles, concrete)
      • Plastering
      • Paving works
      • Painting and wall treatments

    Example: For plastering a wall, the total area of the wall is calculated in square meters.

  2. Measurement by Volume:

    • The volume measurement is used for three-dimensional work where the quantity is measured in cubic meters (m³). It is typically used for:
      • Excavation works
      • Concrete works
      • Earthworks (e.g., trenching, filling)
      • Grading and landscaping

    Example: For concrete pouring, the volume of concrete is measured in cubic meters as length × width × thickness.

  3. Measurement by Length:

    • Length measurements are used for linear components, typically measured in meters (m). This is common in:
      • Masonry walls
      • Drainage systems
      • Pipes
      • Road constructions (e.g., laying curbs)

    Example: Measuring the length of a drain trench or the pipeline in construction.

  4. Measurement by Weight:

    • Weight-based measurements are typically used for materials like steel, bitumen, and cement, where the weight of the material directly impacts cost calculations. It is typically measured in kilograms (kg) or tons (T).
      • Steel reinforcement
      • Bitumen for roadworks

    Example: The weight of steel bars required for reinforcement is calculated in kilograms or tons.

  5. Measurement by Number:

    • Some works involve counting units. In this case, items are counted as units:
      • Doors
      • Windows
      • Pipes and fittings
      • Pre-fabricated units

    Example: Counting the number of windows or doors installed in a building.

  6. Measurement by Set or Unit:

    • For specific construction components, a set or unit measurement is used. This could include pre-fabricated elements or units that are installed:
      • Pre-fabricated panels
      • Fixtures
      • Streetlights

    Example: Measuring the installation of pre-fabricated concrete panels by the unit.

  7. Measurement by Percentage of Completion:

    • This method is often used in contracts for progress payments. It involves measuring the percentage of work completed, often for interim payments during construction.
      • Common in roadwork, drainage, or excavation projects.

    Example: Payment for excavation work can be based on the percentage of the total volume completed.

  8. Measurement by Time:

    • Time-based measurements are used when determining the duration for completion of tasks. This is important in scheduling and project planning.
      • Workforce mobilization times
      • Equipment rental time

    Example: The time spent on excavation or demolition work can be measured in hours or days.

Measurement for Payment and Contract Management

In construction contracts, especially in EPC (Engineering, Procurement, and Construction) or design-build contracts, measurements often follow specific methods for determining payment for completed work. Here are a few common methods used:

  1. Unit Rate Measurement:

    • This method involves measuring the quantities of work completed and multiplying them by the agreed rate per unit. Common for tasks like paving, earthworks, and concrete placement.

    Example: If the unit rate for paving is ₹500 per square meter, and 200 square meters are completed, the total cost would be ₹100,000.

  2. Lump Sum Measurement:

    • This is a fixed price for a specific portion of the work, regardless of the actual quantity. This is typically used for complete tasks such as foundation work, building structure, or roof installation.

    Example: The entire roofing installation might be priced as a lump sum.

  3. Cost Plus:

    • In this measurement, the contractor is reimbursed for the actual costs incurred during construction, plus an additional fee for profit. Common in situations where project scope is unclear.

    Example: A contractor might submit invoices for the actual cost of materials and labor used during construction, with a profit margin added.

IS Code for Measurement

IS 1200 is the primary standard for measurement of quantities in construction projects in India. This series includes multiple parts and covers various civil works such as:

  • Earthworks (Part 1)
  • Concrete Works (Part 2)
  • Masonry Works (Part 4)
  • Paving Works (Part 8)

It provides uniform measurement practices for various civil works and ensures that all contractors, consultants, and stakeholders follow the same standards for accurate reporting and invoicing.

Sun Jan 26, 2025

Pop-Up Message
Call Us Call Us Guidance