MODE OF MEASUREMENT TERMINOLOGIES TRAINING FOR BILLING ENGINEERS IN CIVIL ENGINEERING IN INDIA

1. Unit of Measurement (UOM)

The unit of measurement specifies the way work quantities are calculated. Common units in construction include:

  • Cubic meter (m³): For volume-based items like concrete or excavation.
  • Square meter (m²): For area-based items like plastering or flooring.
  • Linear meter (lm): For linear items such as pipes or electrical conduits.
  • Kilogram (kg): For weight-based items like steel reinforcement.
  • Lump sum: For work or tasks that are billed as a fixed price regardless of the quantity.

Example:

  • Concrete for slab: Measured in cubic meters (m³).
  • Wall plastering: Measured in square meters (m²).

2. Measurement Method

The way the quantity is measured based on the scope of work:

  • As executed: Measurement is taken after the work has been completed.
  • Bill of Quantities (BOQ): Measurement is based on the agreed-upon quantities at the start of the project.
  • Provisional Sums: Estimated quantities where final measurement is determined later.

Example:
For road excavation, if the original estimate was based on a bill of quantities, but due to site conditions, the excavation quantity increases, the measurement might change to "as executed."

3. Quantity Calculation

The actual process of calculating the quantities to be billed based on the unit of measurement and the measurement method.

Item Description

Quantity (UOM)

Rate

Amount

Concrete for slab

10 m³

₹5000/m³

₹50,000

Wall plastering

200 m²

₹50/m²

₹10,000

Example: Concrete for slab is measured in cubic meters (m³), with a rate of ₹5000 per cubic meter. The total quantity is 10 m³, leading to a billing amount of ₹50,000.

4. Measurement for Different Work Types

  • Earthwork: Measured in cubic meters (m³) for excavation or filling.
  • Steel Reinforcement: Measured in kilograms (kg) or tons (T).
  • Formwork: Measured in square meters (m²).
  • Painting: Measured in square meters (m²).

5. Additions and Omissions

  • Additions: Work quantities added to the contract post-award.
  • Omissions: Work quantities reduced or removed from the contract.

Example:
If the original plan for electrical work involved 100 meters of wiring and, due to changes, it increases to 120 meters, the additional 20 meters would be measured separately.

6. Pro-rata Measurement

This refers to an adjustment made based on the portion of work completed. It is often used when the work is done in stages, and billing is done accordingly.

Item Description

Total Quantity (UOM)

Completed Quantity (UOM)

Rate

Amount

Earthwork (Excavation)

500 m³

300 m³

₹300/m³

₹90,000

Road Asphalt

1000 m²

600 m²

₹200/m²

₹120,000

Example:
If the excavation work is 500 m³ but only 300 m³ is completed, billing will be done for the 300 m³ at ₹300 per cubic meter.

7. Rate Analysis

A detailed breakdown of the cost of each item, including materials, labor, and overheads, based on the quantity being measured.

Item Description

Material Cost (₹)

Labor Cost (₹)

Overheads (₹)

Total Cost (₹)

Concrete for slab

₹30,000

₹10,000

₹10,000

₹50,000

Electrical wiring

₹15,000

₹5,000

₹5,000

₹25,000

Example:
For concrete, the total cost is calculated by adding the material cost, labor cost, and overheads. For 10 m³, this gives a total cost of ₹50,000.

8. Lump Sum Measurement

This refers to a fixed price for a defined scope of work, regardless of the actual quantity.

Example:
The construction of a boundary wall for a project may be priced as a lump sum amount, regardless of the final measurement.

Conclusion

Understanding and using the correct mode of measurement in billing engineering and contract management ensures accuracy in cost estimation, payment processing, and contract management.

9. Breakdown of Items (Sub-Items)

Sometimes, an item is broken down into sub-items for easier measurement and payment. Each sub-item represents a detailed portion of the overall task.

Item Description

Sub-Item Description

Quantity (UOM)

Rate

Amount

Concrete for slab

Concrete base (for slab)

5 m³

₹5000/m³

₹25,000

Concrete top (for slab)

5 m³

₹5000/m³

₹25,000

Example:
The total concrete for the slab is 10 m³, broken down into base and top portions, each with 5 m³.

10. Measurement for Temporary Works

Temporary works are items that are not part of the permanent construction but are essential for construction activities. These are also measured and billed separately.

Item Description

Quantity (UOM)

Rate

Amount

Temporary scaffolding

100 m²

₹150/m²

₹15,000

Temporary access roads

200 m

₹200/m

₹40,000

Example:
Temporary scaffolding is measured in square meters (m²) based on the area it covers. Access roads are measured in linear meters (m) based on their length.

11. Recurring Items (Monthly Billing)

Some items of work, like maintenance, cleaning, or temporary works, are billed on a monthly basis, where the rate is multiplied by the number of months of use.

Item Description

Quantity (Months)

Rate

Amount

Maintenance of construction site

12 months

₹10,000

₹1,20,000

Temporary lighting

6 months

₹5,000

₹30,000

Example:
Maintenance is calculated on a per-month basis for 12 months. The total billing is ₹1,20,000.

12. Re-measurement Contracts

Under re-measurement contracts, the actual quantities are measured at the end of the work, and the final payment is based on the re-measured quantities. This is common in projects where the scope of work is uncertain.

Item Description

Initial Estimated Quantity

Final Quantity (as executed)

Rate

Amount

Earthwork (Excavation)

1000 m³

1200 m³

₹300/m³

₹360,000

Concrete for foundation

150 m³

140 m³

₹5000/m³

₹700,000

Example:
Earthwork excavation was estimated at 1000 m³, but the actual executed work was 1200 m³, leading to an additional 200 m³ measured and billed.

13. Measurement of Structural Elements

Structural elements like beams, columns, slabs, and walls are measured according to their dimensions, with particular attention to depth, width, and length for accurate billing.

Item Description

Length (m)

Width (m)

Height/Thickness (m)

Quantity (m³)

Rate

Amount

Concrete beam

10

0.3

0.5

1.5

₹6000/m³

₹9,000

Concrete column

2

0.3

3

1.8

₹6000/m³

₹10,800

Example:
For a concrete beam, the volume is calculated by multiplying the length, width, and height. The total volume of concrete for the beam is 1.5 m³.

14. Overhead and Profit

These are added as a percentage of the total cost of work to cover the contractor’s overhead costs and profits. This percentage is usually specified in the contract and can vary.

Item Description

Total Cost (₹)

Overhead (%)

Profit (%)

Overhead Cost (₹)

Profit (₹)

Total Amount (₹)

Earthwork (Excavation)

₹90,000

10%

5%

₹9,000

₹4,500

₹1,03,500

Concrete foundation

₹700,000

12%

8%

₹84,000

₹56,000

₹8,40,000

Example:
For earthwork excavation, the overhead cost is 10% of ₹90,000 (₹9,000), and the profit is 5% of ₹90,000 (₹4,500). The total amount to be billed is ₹1,03,500.

15. Retentions and Deductions

Retentions are a percentage of the total contract value withheld to ensure the contractor completes the work satisfactorily. These amounts are typically returned upon successful completion or rectification of defects.

Item Description

Contract Value (₹)

Retention (%)

Retention Amount (₹)

Structural work

₹500,000

5%

₹25,000

Electrical work

₹200,000

5%

₹10,000

Example:
If the total contract value for structural work is ₹500,000, the retention amount will be 5% of ₹500,000, i.e., ₹25,000.

16. Time-Related Billing

Some works are billed on the basis of time, especially for manpower and machinery usage. These are often calculated hourly, daily, or monthly.

Item Description

Unit of Time

Rate

Total Time

Amount

Crane Hire

Hour

₹1000/hr

50 hrs

₹50,000

Manpower (Labor)

Day

₹500/day

30 days

₹15,000

Example:
The crane is hired for 50 hours at ₹1000 per hour, resulting in a total cost of ₹50,000.

Conclusion

The mode of measurement in billing engineering and contract management ensures accuracy in cost estimation and payment processes. These measurements help establish clarity between contractors, clients, and stakeholders, making the contract administration smoother. By understanding the terminology and utilizing appropriate measurement methods, professionals can manage projects more efficiently and fairly.

17. Measurement for Specialized Works

Specialized works like mechanical, electrical, and plumbing (MEP) are measured separately from general construction works. These items often require detailed breakdowns.

Item Description

Quantity (UOM)

Rate

Amount

HVAC system installation

500 m

₹1000/m

₹500,000

Electrical wiring

2000 m

₹50/m

₹100,000

Plumbing works (piping)

300 m

₹200/m

₹60,000

Example:
For HVAC system installation, the work is measured by the linear meter (m) of ducting or pipe used. Here, 500 meters are measured at ₹1000 per meter.

18. Measurement for Finishing Works

Finishing works like plastering, flooring, painting, and tiling are usually measured by area (square meters).

Item Description

Quantity (m²)

Rate

Amount

Floor tiling

200 m²

₹500/m²

₹100,000

Wall painting

300 m²

₹150/m²

₹45,000

Example:
Floor tiling is measured in square meters (m²), and the total area is 200 m². The total cost would be ₹100,000.

19. Bulk Materials Measurement

Bulk materials like sand, gravel, and cement are usually measured in tons (T) or cubic meters (m³), depending on the material's density.

Item Description

Quantity (Tons)

Rate

Amount

Sand

100 tons

₹1500/ton

₹150,000

Cement

50 tons

₹4000/ton

₹200,000

Example:
Sand is measured in tons, and the rate is ₹1500 per ton. If 100 tons of sand is required, the total cost will be ₹150,000.

20. Measurement of Roadworks

Road construction, including pavements, curbs, and drains, often requires specialized measurement methods.

Item Description

Quantity (m)

Rate

Amount

Road paving

1000 m

₹800/m

₹800,000

Concrete curb installation

500 m

₹400/m

₹200,000

Example:
For road paving, the length is measured in meters (m), and the rate is ₹800 per meter. If 1000 meters of paving are required, the total cost will be ₹800,000.

21. Measurement of Demolition Works

Demolition works, such as the dismantling of old structures, are usually measured in cubic meters (m³) or tons (T), depending on the material being removed.

Item Description

Quantity (m³)

Rate

Amount

Demolition of brick wall

200 m³

₹500/m³

₹100,000

Demolition of concrete slab

100 m³

₹800/m³

₹80,000

Example:
Demolition work for a brick wall is measured in cubic meters (m³), and the rate is ₹500 per cubic meter. For 200 m³, the total cost will be ₹100,000.

22. Measurement of Complex Systems (MEP)

For specialized mechanical, electrical, and plumbing (MEP) systems, detailed breakdowns and exact measurements are crucial.

Item Description

Quantity (UOM)

Rate

Amount

Chilled water piping system

300 m

₹800/m

₹240,000

Electrical panel installation

10 units

₹20,000/unit

₹200,000

Firefighting piping

150 m

₹900/m

₹135,000

Example:
For a chilled water piping system, the work is measured in meters (m). Here, 300 meters of piping at ₹800 per meter would total ₹240,000.

23. Measurement for Temporary Site Facilities

Temporary facilities like site offices, security fences, and worker accommodation are typically measured as lump sum items, but they can also be calculated by area or quantity.

Item Description

Quantity (UOM)

Rate

Amount

Site office construction

Lump sum

₹50,000

₹50,000

Temporary security fencing

500 m

₹200/m

₹100,000

Example:
The construction of a site office is usually billed as a lump sum amount, while temporary security fencing is measured in linear meters (m).

24. Measurement for Underground Services

For underground services like pipelines, cables, and drainage systems, measurements are taken based on depth, length, and sometimes the type of material used.

Item Description

Quantity (m)

Rate

Amount

Underground drainage pipes

500 m

₹500/m

₹250,000

Electrical cable (underground)

300 m

₹200/m

₹60,000

Example:
For underground drainage pipes, the total length is measured in meters (m), and the rate is ₹500 per meter.

25. Measurement of Reinforcement Works

Reinforcement works (steel bars for concrete) are measured in weight (kilograms or tons). The total weight is calculated based on the length, diameter, and type of steel used.

Item Description

Weight (kg)

Rate

Amount

Reinforcement steel (bars)

1000 kg

₹80/kg

₹80,000

Reinforcement (for slab)

500 kg

₹90/kg

₹45,000

Example:
Reinforcement steel is measured in kilograms (kg). For 1000 kg of steel at ₹80 per kilogram, the total cost will be ₹80,000.

26. Measurement for Landscaping

Landscaping works are measured based on area for soft landscaping (e.g., grass, plants) and linear measurements for hard landscaping (e.g., fences, pathways).

Item Description

Quantity (m²)

Rate

Amount

Lawn area preparation

500 m²

₹30/m²

₹15,000

Garden bed construction

100 m²

₹150/m²

₹15,000

Example:
Lawn area preparation is measured in square meters (m²), and the total area is 500 m². At ₹30 per square meter, the total amount is ₹15,000.

27. Overruns and Underruns

Overruns refer to quantities that exceed the estimated quantity, while underruns refer to quantities that are less than expected. These can be addressed through adjustment clauses in the contract.

Item Description

Estimated Quantity

Actual Quantity

Difference

Adjustment

Concrete for slab

100 m³

110 m³

+10 m³

Extra cost of ₹50,000

Road paving

1000 m

950 m

-50 m

Deduction of ₹40,000

Example:
For concrete, the estimated quantity was 100 m³, but 110 m³ was required. The additional 10 m³ will incur an extra cost, which will be adjusted in the final bill.

Conclusion

These additional measurement practices and terminologies enhance the accuracy and transparency of billing in the construction industry. By incorporating them, construction professionals ensure that billing reflects the true scope of work, while minimizing disputes and maintaining fairness in contract execution. Understanding these measurements is critical for managing construction contracts and budgets effectively.

28. Measurement of Temporary Works for Site Preparation

Site preparation involves various temporary works like access roads, fencing, and site drainage. These are usually billed based on their area, volume, or duration of use.

Item Description

Quantity (UOM)

Rate

Amount

Temporary site fencing

200 m

₹50/m

₹10,000

Site access road construction

500 m²

₹200/m²

₹100,000

Example:
Temporary site fencing is measured by the linear meter (m), while the construction of access roads is measured by square meters (m²). The total cost for the site access road is calculated based on the area constructed.

29. Measurement for Excavation and Backfilling

Excavation and backfilling for foundations or trenches are usually measured in cubic meters (m³) or sometimes in linear meters (lm), depending on the project type.

Item Description

Quantity (m³)

Rate

Amount

Excavation for foundation

150 m³

₹500/m³

₹75,000

Backfilling for foundation

120 m³

₹400/m³

₹48,000

Example:
For excavation of 150 m³ at ₹500 per cubic meter, the total cost will be ₹75,000. Similarly, backfilling is charged based on the volume (m³) and rate.

30. Measurement of Demolition Works (Cont’d)

Demolition works can be complex, especially when removing old structures or parts of buildings. This process is often measured based on the volume of materials removed or the total area affected.

Item Description

Quantity (m³)

Rate

Amount

Demolition of existing structure

500 m³

₹600/m³

₹300,000

Example:
Demolition is often billed by volume (m³), like the removal of 500 m³ of concrete at ₹600 per cubic meter.

31. Measurement for Paving Works

For paving works, especially for roads or driveways, the measurements are based on area (m²) or sometimes linear measurement (m).

Item Description

Quantity (m²)

Rate

Amount

Asphalt road paving

1000 m²

₹600/m²

₹600,000

Concrete road paving

500 m²

₹800/m²

₹400,000

Example:
Road paving is measured in square meters (m²), and for asphalt paving, the total area of 1000 m² will result in a cost of ₹600,000.

32. Measurement of Structural Reinforcement (BBS)

Bar Bending Schedule (BBS) details the measurements and the type of steel used for reinforcing concrete structures. The weight of steel reinforcement is measured in kilograms (kg) or tons (T).

Item Description

Quantity (kg)

Rate

Amount

Reinforcement for slab

1000 kg

₹80/kg

₹80,000

Reinforcement for column

500 kg

₹90/kg

₹45,000

Example:
Reinforcement for a slab is measured in kilograms (kg). For 1000 kg of steel at ₹80 per kilogram, the total cost will be ₹80,000.

33. Measurement for Road Marking and Signage

Road marking and signage are commonly measured in linear meters (lm) for markings and square meters (m²) for signs.

Item Description

Quantity (lm)

Rate

Amount

Road line marking

500 m

₹50/m

₹25,000

Road signage installation

10 signs

₹2000/sign

₹20,000

Example:
Road line marking is measured by linear meter (lm), and the total length marked is 500 m at ₹50 per meter. Road signage is measured as a lump sum or by the number of signs.

34. Measurement for Drainage Works

Drainage works, especially for underground systems, are typically measured in linear meters (lm) for pipes and cubic meters (m³) for excavation.

Item Description

Quantity (m)

Rate

Amount

Drainage pipe installation

300 m

₹500/m

₹150,000

Excavation for drainage system

150 m³

₹400/m³

₹60,000

Example:
Drainage pipes are measured in linear meters (lm), and for 300 meters of installation at ₹500 per meter, the total cost would be ₹150,000. Excavation for the drainage system is measured in cubic meters (m³).

35. Measurement for Electrical and Mechanical Systems

Electrical and mechanical works such as cable laying, conduit installation, or HVAC ducting are usually measured by length, area, or volume, depending on the system type.

Item Description

Quantity (m)

Rate

Amount

Cable laying (underground)

500 m

₹100/m

₹50,000

HVAC ducting installation

200 m

₹1200/m

₹240,000

Example:
Cable laying is measured by length (m), and 500 meters of underground cable at ₹100 per meter results in a cost of ₹50,000. HVAC ducting is measured in linear meters (m).

36. Measurement for Foundation Works

Foundation works for buildings, including the digging of pits or trenches and the pouring of concrete, are typically measured by volume (m³) or by the number of foundations.

Item Description

Quantity (m³)

Rate

Amount

Excavation for foundation

300 m³

₹500/m³

₹150,000

Concrete for foundation

100 m³

₹6000/m³

₹600,000

Example:
Excavation for foundation is measured in cubic meters (m³). For 300 m³ at ₹500 per cubic meter, the total cost would be ₹150,000. Concrete is also measured in cubic meters (m³) for foundation works.

37. Measurement for Site Drainage

For drainage systems on-site, including trenches and pipes, the measurement method often includes both the excavation and installation of pipes.

Item Description

Quantity (m)

Rate

Amount

Site drainage pipe laying

200 m

₹400/m

₹80,000

Excavation for drainage trench

100 m³

₹350/m³

₹35,000

Example:
Site drainage pipe laying is measured in linear meters (m), while the excavation for drainage trenches is measured in cubic meters (m³).

38. Measurement of Commissioning and Testing

For systems like HVAC, plumbing, and electrical, commissioning and testing are essential phases measured as part of the contract.

Item Description

Quantity (UOM)

Rate

Amount

HVAC commissioning

Lump sum

₹50,000

₹50,000

Electrical system testing

Lump sum

₹30,000

₹30,000

Example:
HVAC commissioning is usually measured as a lump sum, while electrical system testing may be similarly priced.

39. Measurement for Earthworks

Earthworks, which include excavation, filling, grading, and leveling, are common tasks measured by volume (cubic meters) or area (square meters), depending on the type of work. It is essential to measure these works correctly, as they often make up a large portion of the project costs.

Item Description

Quantity (m³)

Rate

Amount

Excavation for foundation

500 m³

₹400/m³

₹200,000

Embankment filling

300 m³

₹350/m³

₹105,000

Grading for roadworks

200 m²

₹150/m²

₹30,000

Example:
For excavation of 500 m³ of soil at ₹400 per cubic meter, the total cost will be ₹200,000. Similarly, embankment filling and grading are measured in cubic meters and square meters, respectively.

40. Measurement for Waterproofing

Waterproofing is a specialized construction activity for preventing water ingress. The measurement is generally based on the surface area to be treated, often in square meters (m²).

Item Description

Quantity (m²)

Rate

Amount

Waterproofing of basement walls

200 m²

₹150/m²

₹30,000

Waterproofing of roof terrace

300 m²

₹180/m²

₹54,000

Example:
Waterproofing works are typically measured in square meters (m²). For the waterproofing of 200 m² of basement walls at ₹150 per square meter, the total cost is ₹30,000.

41. Measurement for Structural Steelwork

For structural steelwork, the measurement is done based on weight, as the steel components are generally measured by tons (T) or kilograms (kg).

Item Description

Quantity (kg)

Rate

Amount

Structural steel beams

5000 kg

₹80/kg

₹400,000

Steel columns

3000 kg

₹90/kg

₹270,000

Example:
Structural steel components like beams and columns are measured by weight. For 5000 kg of steel beams at ₹80 per kilogram, the total cost will be ₹400,000.

42. Measurement for Formwork

Formwork is used for shaping and supporting the concrete during the setting process. The quantity is measured in square meters (m²) for walls, slabs, and beams, and is based on the surface area to be formed.

Item Description

Quantity (m²)

Rate

Amount

Formwork for concrete slab

100 m²

₹200/m²

₹20,000

Formwork for concrete column

50 m²

₹250/m²

₹12,500

Example:
For slab formwork, 100 m² at ₹200 per square meter would cost ₹20,000. Similarly, for column formwork, 50 m² would cost ₹12,500.

43. Measurement for Insulation Works

Insulation works, such as thermal or acoustic insulation, are measured based on the surface area (square meters), and the rates can vary depending on the material used.

Item Description

Quantity (m²)

Rate

Amount

Thermal insulation for roof

500 m²

₹120/m²

₹60,000

Acoustic insulation for walls

300 m²

₹150/m²

₹45,000

Example:
Thermal insulation for a roof is measured in square meters (m²), with a total area of 500 m² at ₹120 per square meter, resulting in ₹60,000.

44. Measurement for Finishing Materials (Tiles, Paint, etc.)

Finishing materials like tiles, paint, and other coatings are typically measured in square meters (m²). The quantity is determined by the area of walls, floors, or ceilings to be covered.

Item Description

Quantity (m²)

Rate

Amount

Ceramic floor tiles

200 m²

₹500/m²

₹100,000

Painting of walls

300 m²

₹150/m²

₹45,000

Example:
For ceramic floor tiles, 200 m² at ₹500 per square meter results in a total cost of ₹100,000. Similarly, wall painting costs ₹45,000 for 300 m².

45. Measurement for Concrete Works

Concrete works, such as slabs, beams, foundations, and columns, are typically measured by volume (m³). The concrete is priced based on its cubic volume, and the rate varies by the type of concrete.

Item Description

Quantity (m³)

Rate

Amount

Concrete for foundation

100 m³

₹5000/m³

₹500,000

Concrete for slab

200 m³

₹5500/m³

₹1,100,000

Example:
For concrete work in the foundation (100 m³ at ₹5000 per cubic meter), the total cost will be ₹500,000. For a slab (200 m³ at ₹5500 per cubic meter), the total cost will be ₹1,100,000.

46. Measurement for Roofing and Cladding Works

Roofing and cladding works are generally measured in square meters (m²) or linear meters (lm) depending on the type of roof or cladding system being used.

Item Description

Quantity (m²)

Rate

Amount

Roof sheet installation

500 m²

₹250/m²

₹125,000

Cladding of external walls

800 m²

₹300/m²

₹240,000

Example:
Roof sheet installation is measured in square meters (m²). For 500 m² of roofing at ₹250 per square meter, the cost will be ₹125,000.

47. Measurement for Demolition of Existing Structures

When demolishing existing structures, the measurement is often based on the volume of materials removed or the area of structures demolished.

Item Description

Quantity (m²)

Rate

Amount

Demolition of brick wall

100 m²

₹250/m²

₹25,000

Demolition of concrete slab

50 m²

₹350/m²

₹17,500

Example:
Demolition of a brick wall is measured by area (m²), and for 100 m² at ₹250 per square meter, the total cost would be ₹25,000.

48. Measurement for Structural Shoring and Forming

Shoring and forming are temporary structures used to support buildings during construction. These works are usually measured in square meters (m²) or linear meters (lm).

Item Description

Quantity (m²)

Rate

Amount

Shoring for foundation

200 m²

₹100/m²

₹20,000

Shoring for retaining wall

100 m²

₹150/m²

₹15,000

Example:
Shoring for foundation is measured in square meters (m²), and for 200 m² at ₹100 per square meter, the cost will be ₹20,000.

49. Measurement for Site Preparation (Clearing and Grubbing)

Clearing and grubbing involve removing debris, trees, or vegetation from the construction site. This work is typically measured in square meters (m²) or acres.

Item Description

Quantity (m²)

Rate

Amount

Clearing of site

1000 m²

₹20/m²

₹20,000

Grubbing of trees

100 m²

₹50/m²

₹5000

Example:
Clearing of the site is measured in square meters (m²). For 1000 m² at ₹20 per square meter, the total cost will be ₹20,000.

50. Measurement for Mechanical Works (HVAC, Fire Fighting, Plumbing)

Mechanical systems like HVAC, firefighting, and plumbing are typically measured by volume (m³), area (m²), or length (m), depending on the work type. These works require precise measurements to ensure proper billing.

Item Description

Quantity (m)

Rate

Amount

HVAC ductwork installation

200 m

₹1000/m

₹200,000

Firefighting pipe installation

150 m

₹1500/m

₹225,000

Plumbing pipework installation

300 m

₹500/m

₹150,000

Example:
For HVAC ductwork, it is measured in linear meters (m). For 200 meters of duct installation at ₹1000 per meter, the total amount will be ₹200,000.

51. Measurement for Site Restoration and Cleanup

At the end of the project, site restoration and cleanup work are measured based on area or volume. This may include removing debris, cleaning surfaces, and restoring the landscape.

Item Description

Quantity (m²)

Rate

Amount

Site cleaning and debris removal

2000 m²

₹10/m²

₹20,000

Landscape restoration

500 m²

₹50/m²

₹25,000

Example:
Site cleaning is measured in square meters (m²). For 2000 m² of cleanup at ₹10 per square meter, the total cost is ₹20,000.

52. Measurement for Surface Treatment (Polishing, Painting, etc.)

Surface treatment such as polishing, painting, and other coatings are typically measured in square meters (m²), reflecting the area covered by the treatment.

Item Description

Quantity (m²)

Rate

Amount

Floor polishing

500 m²

₹100/m²

₹50,000

Wall painting

300 m²

₹150/m²

₹45,000

Example:
Floor polishing is measured in square meters (m²). For 500 m² at ₹100 per square meter, the total cost would be ₹50,000.

53. Measurement for Brickwork

Brickwork is usually measured in cubic meters (m³) for volume-based works like walls and columns, or square meters (m²) for areas like cladding.

Item Description

Quantity (m³)

Rate

Amount

Brick masonry for wall

100 m³

₹4000/m³

₹400,000

Brickwork for cladding

200 m²

₹200/m²

₹40,000

Example:
Brick masonry for walls is measured in cubic meters (m³). For 100 m³ of brickwork at ₹4000 per cubic meter, the total cost will be ₹400,000.

54. Measurement for Concrete Paving Blocks

Paving blocks, commonly used for roads, walkways, and other exterior surfaces, are measured by area (m²) or quantity (per block), depending on the type of work.

Item Description

Quantity (m²)

Rate

Amount

Concrete paving blocks (laid)

500 m²

₹200/m²

₹100,000

Example:
For laying 500 m² of paving blocks at ₹200 per square meter, the total cost will be ₹100,000.

55. Measurement for Surveying and Testing

Surveying and testing are necessary for confirming the quality and alignment of works. These are typically billed on a lump sum basis or by the unit of measurement for specific activities.

Item Description

Quantity (Lump Sum)

Rate

Amount

Land surveying

Lump sum

₹50,000

₹50,000

Concrete testing (compression)

Lump sum

₹30,000

₹30,000

Example:
Surveying is usually measured as a lump sum amount, and concrete testing can be billed on a lump sum basis for the testing of samples.

56. Measurement for Pile Foundation Works

Pile foundation work is generally measured by the number of piles or by the total length of piles driven into the ground, depending on the project type.

Item Description

Quantity (m)

Rate

Amount

Pile driving (bored piles)

100 m

₹3000/m

₹300,000

Pile cap construction

Lump sum

₹150,000

₹150,000

Example:
Pile driving is measured in linear meters (m). For 100 meters of pile driving at ₹3000 per meter, the total cost will be ₹300,000.

57. Measurement for Temporary Utilities (Water, Electricity)

Temporary utilities like water and electricity for site operations are measured by usage, usually in terms of quantity (liters or kilowatt hours) or duration.

Item Description

Quantity (UOM)

Rate

Amount

Temporary water supply

1000 m³

₹50/m³

₹50,000

Temporary electricity supply

5000 kWh

₹10/kWh

₹50,000

Example:
Temporary water supply is measured in cubic meters (m³), and for 1000 m³ of water at ₹50 per cubic meter, the total cost will be ₹50,000.

58. Measurement for Excavation for Underground Tanks

Excavation for underground tanks is often measured by volume (m³), and the rate depends on the depth and soil type.

Item Description

Quantity (m³)

Rate

Amount

Excavation for underground tank

50 m³

₹700/m³

₹35,000

Example:
Excavation for underground tanks is measured in cubic meters (m³), and for 50 m³ at ₹700 per cubic meter, the total cost will be ₹35,000.

59. Measurement for Electrical Wiring

Electrical wiring for both internal and external systems is typically measured by the length of wiring installed.

Item Description

Quantity (m)

Rate

Amount

Electrical wiring for lighting

500 m

₹30/m

₹15,000

Electrical wiring for power

1000 m

₹50/m

₹50,000

Example:
Electrical wiring is measured by linear meters (m). For 500 meters of lighting wiring at ₹30 per meter, the total cost will be ₹15,000.

60. Measurement for Structural Precast Elements

Precast elements like beams, columns, and panels are typically measured by weight or volume, depending on the item.

Item Description

Quantity (Tons)

Rate

Amount

Precast concrete beams

10 T

₹7000/T

₹70,000

Precast concrete panels

5 T

₹6000/T

₹30,000

Example:
Precast concrete beams are measured by tons (T). For 10 tons of beams at ₹7000 per ton, the total cost will be ₹70,000.

61. Measurement for Landscaping Works (Tree Planting, Turfing, etc.)

Landscaping works, including tree planting, turfing, and grass seeding, are measured by area or by quantity (trees, plants, etc.).

Item Description

Quantity (m²)

Rate

Amount

Tree planting

50 trees

₹1000/tree

₹50,000

Turfing of garden

200 m²

₹50/m²

₹10,000

Example:
Tree planting is measured by the number of trees, and for 50 trees at ₹1000 per tree, the total cost will be ₹50,000.

62. Measurement for Drainage and Sewerage Works

For drainage and sewerage systems, the measurements are typically based on the length of pipe laid, the type of material used, or excavation for trenches.

Item Description

Quantity (m)

Rate

Amount

Sewer pipe installation

500 m

₹600/m

₹300,000

Excavation for sewer trench

100 m³

₹400/m³

₹40,000

Manhole construction

10 units

₹15,000/unit

₹150,000

Example:
Sewer pipe installation is measured in linear meters (m), and the excavation for the trench is measured by volume (m³).

63. Measurement for Underground Utilities

Utility installation (like water, gas, or electric cables) often involves measuring the length of cables laid, the volume of trenching, or the area of installation.

Item Description

Quantity (m)

Rate

Amount

Underground water pipe laying

200 m

₹700/m

₹140,000

Cable trench excavation

50 m³

₹500/m³

₹25,000

Gas pipeline installation

300 m

₹1000/m

₹300,000

Example:
Utility installation is often measured by length for pipelines (m) and volume for excavation (m³), with each work item having its own rate.

64. Measurement for Structural Elements (Slabs, Beams, and Columns)

Structural elements like slabs, beams, and columns are typically measured in terms of volume (m³) or surface area (m²), depending on the part being measured.

Item Description

Quantity (m³)

Rate

Amount

Concrete slab

50 m³

₹5000/m³

₹250,000

Concrete beams

20 m³

₹5500/m³

₹110,000

Concrete columns

10 m³

₹6000/m³

₹60,000

Example:
For concrete slabs, the volume is measured in cubic meters (m³), and the total quantity of 50 m³ would cost ₹250,000 at ₹5000 per cubic meter.

65. Measurement for Asphalt Works (Roads and Pavements)

Asphalt works, especially road paving, are typically measured by area (m²), as this determines the amount of asphalt used.

Item Description

Quantity (m²)

Rate

Amount

Road paving with asphalt

5000 m²

₹800/m²

₹4,000,000

Asphalt patching

200 m²

₹600/m²

₹120,000

Example:
Asphalt works for road paving are generally measured in square meters (m²). For 5000 m² at ₹800 per square meter, the total cost would be ₹4,000,000.

66. Measurement for Geotechnical Works (Soil Testing, Pile Testing)

Geotechnical works are related to the testing of soil and materials for construction purposes. These works are typically measured as lump sums or by specific test unit.

Item Description

Quantity (Lump Sum)

Rate

Amount

Soil testing for foundation

Lump sum

₹30,000

₹30,000

Pile testing (per pile)

20 piles

₹5,000/pile

₹100,000

Example:
Soil testing and pile testing are usually charged on a lump sum basis or per unit, like per pile for pile testing.

67. Measurement for Formwork in Precast Concrete

Precast concrete works like beams, slabs, and walls are often measured by the area or volume of formwork needed, as these structures require temporary forms to shape the concrete.

Item Description

Quantity (m²)

Rate

Amount

Precast concrete slab formwork

200 m²

₹300/m²

₹60,000

Precast concrete wall formwork

150 m²

₹350/m²

₹52,500

Example:
Precast formwork is measured in square meters (m²), where the total area of 200 m² at ₹300 per square meter will cost ₹60,000.

68. Measurement for Scaffoldings and Shoring Systems

Scaffolding and shoring systems are temporary installations required for construction. These are usually measured by area (m²) or volume (m³), depending on the complexity of the structure.

Item Description

Quantity (m²)

Rate

Amount

Scaffold installation

300 m²

₹100/m²

₹30,000

Shoring system for excavation

200 m²

₹150/m²

₹30,000

Example:
Scaffolding is usually measured by the surface area covered (m²), and for 300 m² at ₹100 per square meter, the total cost would be ₹30,000.

69. Measurement for Temporary Traffic Management

For construction projects that impact roads, temporary traffic management is needed to divert and manage traffic flow. These are typically measured by the length of roads affected or for specific traffic control measures.

Item Description

Quantity (Lump Sum)

Rate

Amount

Temporary traffic diversion

Lump sum

₹200,000

₹200,000

Road signs and barriers

Lump sum

₹50,000

₹50,000

Example:
Traffic management is often billed as a lump sum, with specific rates for items like barriers and signs.

70. Measurement for Roofing and Cladding Systems

Roofing and cladding are critical components for both functional and aesthetic purposes. These systems are generally measured by area or linear length, depending on the material type.

Item Description

Quantity (m²)

Rate

Amount

Metal roof installation

1000 m²

₹400/m²

₹400,000

Wall cladding

500 m²

₹500/m²

₹250,000

Example:
Roof installation is measured in square meters (m²), and for 1000 m² of metal roofing at ₹400 per square meter, the total cost will be ₹400,000.

71. Measurement for Concrete Repairs and Restoration

Concrete repairs and restoration works are essential for maintaining structural integrity, and these are often measured by area or volume depending on the type of repair.

Item Description

Quantity (m²)

Rate

Amount

Concrete surface repair

200 m²

₹200/m²

₹40,000

Concrete crack injection

50 m²

₹250/m²

₹12,500

Example:
Concrete surface repair is typically measured by area (m²). For 200 m² of repair at ₹200 per square meter, the total cost will be ₹40,000.

72. Measurement for Stormwater Drainage

Stormwater drainage works are measured by the length of the system installed, which may include pipes, culverts, and other elements.

Item Description

Quantity (m)

Rate

Amount

Stormwater pipe laying

300 m

₹700/m

₹210,000

Catch basin installation

5 units

₹10,000/unit

₹50,000

Example:
Stormwater pipes are measured by length (m), and the total quantity of 300 meters at ₹700 per meter results in a cost of ₹210,000.

73. Measurement for Thermal Insulation and Acoustic Works

Thermal and acoustic insulation works are necessary for controlling the environment inside buildings. They are measured by the area (m²) or length (m), depending on the application.

Item Description

Quantity (m²)

Rate

Amount

Acoustic insulation for walls

500 m²

₹150/m²

₹75,000

Thermal insulation for ceiling

400 m²

₹200/m²

₹80,000

Example:
Acoustic insulation is measured in square meters (m²), and for 500 m² at ₹150 per square meter, the total cost will be ₹75,000.

74. Measurement for Landscaping Hardscape and Softscape Works

Landscaping works are divided into hardscaping (non-plant elements like pavements, walls, etc.) and softscaping (plant-related works like lawns, trees, and shrubs). Both are measured in square meters (m²) or number of items (trees, plants, etc.).

Item Description

Quantity (m² or Units)

Rate

Amount

Turfing for lawn area

1000 m²

₹50/m²

₹50,000

Tree planting (per tree)

50 trees

₹1000/tree

₹50,000

Paving for walkways

500 m²

₹200/m²

₹100,000

Example:
Turfing of 1000 m² of lawn area at ₹50 per square meter costs ₹50,000. Tree planting is measured by the number of trees, costing ₹1000 per tree.

75. Measurement for Demolition and Dismantling

Demolition works, especially for large structures or portions of buildings, are measured by the area or volume of materials to be removed. Some demolition activities are paid based on the number of units or portions of structures dismantled.

Item Description

Quantity (m² or Units)

Rate

Amount

Demolition of concrete wall

200 m²

₹500/m²

₹100,000

Dismantling of roof structure

100 m²

₹600/m²

₹60,000

Removal of debris

50 m³

₹400/m³

₹20,000

Example:
For the demolition of a concrete wall, 200 m² at ₹500 per square meter results in ₹100,000. Dismantling of a roof structure is measured in square meters, and removal of debris in cubic meters (m³).

76. Measurement for Reinforced Concrete Work (BBS)

Reinforcement works (such as steel bars used for reinforcing concrete) are often measured in terms of weight (kilograms or tons). These measurements are based on the Bar Bending Schedule (BBS), which details the length and weight of the steel.

Item Description

Quantity (kg or Tons)

Rate

Amount

Reinforced concrete slab (BBS)

1000 kg

₹80/kg

₹80,000

Reinforced steel for beams

500 kg

₹100/kg

₹50,000

Example:
Reinforcement steel for a concrete slab (1000 kg at ₹80 per kg) will cost ₹80,000. Similarly, reinforcement for beams is measured by weight.

77. Measurement for Temporary Site Facilities (Offices, Toilets, etc.)

Temporary facilities required during construction, such as site offices or temporary toilets, are measured either as lump sums for specific items or by area (m²).

Item Description

Quantity (Lump Sum or m²)

Rate

Amount

Site office construction

Lump sum

₹100,000

₹100,000

Temporary toilet block

Lump sum

₹30,000

₹30,000

Site fencing

200 m²

₹50/m²

₹10,000

Example:
Site office construction and temporary toilets are typically measured as lump sums, while site fencing is measured by area (m²).

78. Measurement for Electrical Works (Wiring, Lighting, etc.)

Electrical works like wiring, conduit installation, and lighting are often measured by length or the number of items, such as light fixtures or outlets.

Item Description

Quantity (m or Units)

Rate

Amount

Wiring installation for lighting

500 m

₹50/m

₹25,000

Lighting fixtures installation

30 units

₹2000/unit

₹60,000

Example:
Wiring installation is typically measured by length (m), and lighting fixtures by units. For 500 meters of wiring at ₹50 per meter, the cost is ₹25,000.

79. Measurement for Water and Sewerage Systems

Water and sewerage system installations, including pipes, drains, and manholes, are measured by length (for pipes), area (for drainage), or by unit (for manholes).

Item Description

Quantity (m or Units)

Rate

Amount

Water pipe laying

200 m

₹600/m

₹120,000

Sewerage trench excavation

100 m³

₹350/m³

₹35,000

Manhole construction

10 units

₹10,000/unit

₹100,000

Example:
Water pipe laying is measured by length (m), sewerage trench excavation by volume (m³), and manhole construction by units.

80. Measurement for Insulation (Thermal, Acoustic)

Insulation works, which include thermal insulation for temperature control and acoustic insulation for soundproofing, are typically measured by area (m²) or the number of units (such as acoustic panels).

Item Description

Quantity (m² or Units)

Rate

Amount

Thermal insulation for walls

500 m²

₹120/m²

₹60,000

Acoustic panels installation

200 units

₹500/unit

₹100,000

Example:
Thermal insulation for walls is measured in square meters (m²), and for 500 m² at ₹120 per square meter, the cost will be ₹60,000.

81. Measurement for Brick and Block Work

Brick and block work, which includes laying bricks or blocks for walls, is measured by volume (m³) or by area (m²) depending on the thickness of the walls.

Item Description

Quantity (m³ or m²)

Rate

Amount

Brick wall construction (1st floor)

50 m³

₹4000/m³

₹200,000

Block wall cladding

100 m²

₹250/m²

₹25,000

Example:
Brick wall construction is measured by volume (m³), while block wall cladding is measured by area (m²).

82. Measurement for Concrete Pavement Works

Concrete pavement works for roads, walkways, or driveways are measured by area (m²) for surface coverage.

Item Description

Quantity (m²)

Rate

Amount

Concrete pavement installation

500 m²

₹800/m²

₹400,000

Example:
Concrete pavement is measured in square meters (m²). For 500 m² of pavement at ₹800 per square meter, the total cost will be ₹400,000.

83. Measurement for Road Excavation and Earthworks

Excavation works for roads, such as trenching for utilities or earth moving, are measured by volume (m³) or by the area of the road worked on.

Item Description

Quantity (m³ or m²)

Rate

Amount

Excavation for road foundation

200 m³

₹400/m³

₹80,000

Subgrade compaction for road

1000 m²

₹150/m²

₹150,000

Example:
Road excavation is measured in cubic meters (m³), and subgrade compaction is measured in square meters (m²).

84. Measurement for Road Signage and Marking

For roads, traffic signage and road markings are measured based on units or area, depending on the type of sign or marking.

Item Description

Quantity (Units or m²)

Rate

Amount

Road line marking

1000 m

₹50/m

₹50,000

Road sign installation (per unit)

30 units

₹5000/unit

₹150,000

Example:
Road line markings are measured by linear meters (m), while road signs are measured by units.

85. Measurement for Concrete Casting and Curing Works

Concrete casting and curing are integral to construction, especially in structural works like foundations, slabs, and beams. The work is measured based on volume (m³) for casting, and sometimes by area (m²) for curing treatments.

Item Description

Quantity (m³ or m²)

Rate

Amount

Concrete slab casting

100 m³

₹5000/m³

₹500,000

Concrete curing (for slab)

1000 m²

₹10/m²

₹10,000

Example:
Concrete slab casting is measured by volume (m³), and the total quantity of 100 m³ at ₹5000 per cubic meter results in ₹500,000. Curing is usually measured by area (m²).

86. Measurement for Masonry (Stonework, Brickwork, etc.)

Masonry work, whether using stone or bricks, is typically measured in volume (m³) or area (m²), depending on the scope of work and the wall thickness.

Item Description

Quantity (m³ or m²)

Rate

Amount

Stone wall construction

50 m³

₹4500/m³

₹225,000

Brickwork for partition walls

200 m²

₹300/m²

₹60,000

Example:
Stone wall construction is measured by volume (m³), while brickwork for partition walls is measured by area (m²). For stonework, 50 m³ at ₹4500 per cubic meter results in ₹225,000.

87. Measurement for Paint and Coating Works

Painting and coating works are generally measured in square meters (m²) based on the area to be covered. This could include interior and exterior surfaces, or specific items such as doors or windows.

Item Description

Quantity (m²)

Rate

Amount

Interior wall painting

500 m²

₹150/m²

₹75,000

External surface coating

1000 m²

₹200/m²

₹200,000

Example:
For interior wall painting (500 m² at ₹150 per square meter), the total cost would be ₹75,000. External surface coating is measured similarly.

88. Measurement for Road Construction and Surfacing

For road construction, the work typically includes excavation, base preparation, asphalt or concrete surfacing, and finishing. These tasks are measured in terms of area (m²) for surfacing and length (m) for the overall road.

Item Description

Quantity (m or m²)

Rate

Amount

Asphalt road surfacing

5000 m²

₹800/m²

₹4,000,000

Sub-base preparation for road

1000 m³

₹500/m³

₹500,000

Example:
Asphalt surfacing for a 5000 m² area at ₹800 per square meter results in ₹4,000,000. Sub-base preparation is measured in cubic meters (m³).

89. Measurement for Foundation Excavation

Excavation for foundations typically includes trenching or pit excavation and is measured in cubic meters (m³). This also includes the volume of soil removed, compacted, or replaced during the work.

Item Description

Quantity (m³)

Rate

Amount

Excavation for foundation pits

100 m³

₹500/m³

₹50,000

Excavation for trenching

200 m³

₹450/m³

₹90,000

Example:
Foundation excavation is measured in cubic meters (m³). For a total of 100 m³ at ₹500 per cubic meter, the cost will be ₹50,000.

90. Measurement for Forming, Shuttering, and Scaffolding

Shuttering and formwork are temporary structures used to support concrete until it hardens. These works are generally measured in square meters (m²) for area-based activities or linear meters (m) for beams, columns, etc.

Item Description

Quantity (m² or m)

Rate

Amount

Formwork for concrete slab

200 m²

₹150/m²

₹30,000

Formwork for beams

100 m

₹200/m

₹20,000

Example:
Formwork for slabs is usually measured by area (m²), while beams are measured by linear length (m). For 200 m² of formwork at ₹150 per square meter, the total cost will be ₹30,000.

91. Measurement for Asphalt Paving

Asphalt paving for roads, driveways, or parking lots is typically measured by area (m²) based on the thickness and surface coverage.

Item Description

Quantity (m²)

Rate

Amount

Asphalt paving for roads

3000 m²

₹900/m²

₹2,700,000

Asphalt driveway paving

500 m²

₹1000/m²

₹500,000

Example:
Asphalt paving is usually measured in square meters (m²). For a 3000 m² road paving at ₹900 per square meter, the total cost will be ₹2,700,000.

92. Measurement for Site Grading and Compaction

Site grading and compaction are crucial for preparing a solid base for roads, buildings, and other structures. These are typically measured by volume (m³) or area (m²).

Item Description

Quantity (m³ or m²)

Rate

Amount

Site grading and leveling

1000 m²

₹20/m²

₹20,000

Soil compaction for foundation

500 m³

₹300/m³

₹150,000

Example:
Site grading is measured in square meters (m²), while soil compaction is measured in cubic meters (m³). For grading of 1000 m² at ₹20 per square meter, the total cost will be ₹20,000.

93. Measurement for Prefabricated Building Components

Prefabricated components such as walls, roofs, and panels are often measured by area (m²) or volume (m³), depending on the nature of the component.

Item Description

Quantity (m² or m³)

Rate

Amount

Prefabricated wall panels

200 m²

₹300/m²

₹60,000

Prefabricated roof panels

150 m²

₹500/m²

₹75,000

Example:
Prefabricated wall panels are typically measured by area (m²). For 200 m² of panels at ₹300 per square meter, the total cost will be ₹60,000.

94. Measurement for Bulk Earthworks (Excavation, Filling, etc.)

Earthworks, including excavation, filling, and grading, are critical to most construction projects. These are typically measured by volume (m³).

Item Description

Quantity (m³)

Rate

Amount

Excavation for site preparation

500 m³

₹450/m³

₹225,000

Filling for embankment

600 m³

₹500/m³

₹300,000

Example:
Excavation is measured by volume (m³). For a total excavation of 500 m³ at ₹450 per cubic meter, the total cost will be ₹225,000.

95. Measurement for Concrete Repairs

Concrete repairs, such as resurfacing or crack filling, are often measured by area (m²) or volume (m³) depending on the type of repair.

Item Description

Quantity (m² or m³)

Rate

Amount

Concrete resurfacing

200 m²

₹150/m²

₹30,000

Concrete crack filling

50 m³

₹1000/m³

₹50,000

Example:
Concrete resurfacing is measured by area (m²), while crack filling is measured by volume (m³). For resurfacing of 200 m² at ₹150 per square meter, the total cost will be ₹30,000.

96. Measurement for Drainage and Stormwater Management

Stormwater and drainage works often involve the installation of pipes, catch basins, and culverts. Measurement is typically by length (m), volume (m³), or by the number of manholes and other features.

Item Description

Quantity (m or Units)

Rate

Amount

Stormwater pipe installation

500 m

₹700/m

₹350,000

Catch basin installation

10 units

₹12,000/unit

₹120,000

Excavation for drainage system

200 m³

₹350/m³

₹70,000

Example:
Stormwater pipe installation is measured by length (m). Catch basins are measured by units, and drainage system excavation is based on volume (m³).

97. Measurement for Structural Steel Works

Structural steel works, including beams, columns, and trusses, are typically measured by weight (kg or tons). The steel weight is based on the quantity of material used in the structure.

Item Description

Quantity (kg or Tons)

Rate

Amount

Structural steel for beams

5000 kg

₹80/kg

₹400,000

Steel columns

3000 kg

₹100/kg

₹300,000

Example:
Steel reinforcement for beams and columns is measured by weight (kg or tons). For 5000 kg of steel for beams at ₹80 per kg, the total cost will be ₹400,000.

98. Measurement for Road Marking and Signage

For road construction and maintenance projects, road marking and signage are typically measured by the length (m) of markings or the number of signs installed.

Item Description

Quantity (m or Units)

Rate

Amount

Road line marking

1000 m

₹50/m

₹50,000

Road sign installation

20 units

₹2000/unit

₹40,000

Example:
Road markings are measured by the length (m), and road signage is typically measured by the number of signs installed (units).

99. Measurement for Electrical and Mechanical Systems (HVAC, Plumbing, etc.)

For HVAC (Heating, Ventilation, and Air Conditioning), plumbing, and other mechanical systems, measurements are usually based on the length of ducts or pipes, the number of units (fixtures), or the area of installation.

Item Description

Quantity (m or Units)

Rate

Amount

HVAC duct installation

200 m

₹1200/m

₹240,000

Plumbing pipe installation

100 m

₹500/m

₹50,000

Firefighting system installation

50 units

₹5000/unit

₹250,000

Example:
HVAC ducts are measured by length (m), plumbing pipes by length (m), and firefighting system components by units installed.

100. Measurement for Excavation and Backfilling in Foundations

Excavation and backfilling are crucial in foundation works. The excavation is typically measured by volume (m³), while backfilling can be measured similarly or by weight in some cases.

Item Description

Quantity (m³)

Rate

Amount

Excavation for foundation pits

150 m³

₹400/m³

₹60,000

Backfilling for foundation

100 m³

₹350/m³

₹35,000

Example:
Excavation for foundations is measured by volume (m³), and backfilling is also measured by volume (m³). The total cost of excavation will be ₹60,000 for 150 m³ at ₹400 per m³.

101. Measurement for Brickwork and Blockwork

Brick and blockwork are essential components in masonry. They are typically measured by volume (m³) or area (m²), depending on whether it's a wall, column, or cladding.

Item Description

Quantity (m³ or m²)

Rate

Amount

Brickwork for walls

100 m³

₹4500/m³

₹450,000

Concrete block cladding

200 m²

₹250/m²

₹50,000

Example:
Brickwork for walls is typically measured in cubic meters (m³), while block cladding is measured in square meters (m²). For 100 m³ of brickwork at ₹4500 per m³, the total cost will be ₹450,000.

102. Measurement for Site Clearance and Demolition

Site clearance and demolition work are required for preparing the site or removing old structures. These works are generally measured by volume (m³) or area (m²).

Item Description

Quantity (m² or m³)

Rate

Amount

Site clearing and debris removal

1000 m²

₹20/m²

₹20,000

Demolition of existing structure

500 m³

₹500/m³

₹250,000

Example:
Site clearing is typically measured by area (m²), while demolition is measured by volume (m³). The total cost for clearing a 1000 m² site at ₹20 per m² will be ₹20,000.

103. Measurement for Structural Concrete

Structural concrete work for various elements like slabs, beams, foundations, and columns is measured by volume (m³).

Item Description

Quantity (m³)

Rate

Amount

Concrete slab construction

200 m³

₹5000/m³

₹1,000,000

Concrete column construction

50 m³

₹6000/m³

₹300,000

Example:
For a concrete slab (200 m³ at ₹5000 per cubic meter), the total cost is ₹1,000,000. Concrete columns (50 m³ at ₹6000 per cubic meter) cost ₹300,000.

104. Measurement for Formwork and Shuttering

Formwork and shuttering are temporary structures to support concrete during setting. These works are usually measured by area (m²) for walls, slabs, and beams.

Item Description

Quantity (m² or m)

Rate

Amount

Formwork for concrete slab

200 m²

₹150/m²

₹30,000

Formwork for beams and columns

100 m²

₹200/m²

₹20,000

Example:
Formwork is measured in square meters (m²). For 200 m² of slab formwork at ₹150 per square meter, the total cost will be ₹30,000.

105. Measurement for Waterproofing

Waterproofing is a critical activity in both foundation and roofing works. It is typically measured by area (m²) of the surface to be treated.

Item Description

Quantity (m²)

Rate

Amount

Waterproofing for foundations

100 m²

₹200/m²

₹20,000

Waterproofing for roof terrace

200 m²

₹250/m²

₹50,000

Example:
Waterproofing for foundations is typically measured by area (m²). For 100 m² at ₹200 per square meter, the total cost is ₹20,000.

106. Measurement for Substructure Works

Substructure works, such as the excavation, construction, and finishing of basements, are measured by volume (m³) or area (m²), depending on the work type.

Item Description

Quantity (m³ or m²)

Rate

Amount

Excavation for basement

100 m³

₹450/m³

₹45,000

Basement slab concrete

200 m²

₹500/m²

₹100,000

Example:
Basement excavation is measured by volume (m³), while the basement slab is measured by area (m²). For 200 m² of basement slab at ₹500 per square meter, the total cost will be ₹100,000.

107. Measurement for Road Excavation and Backfilling

Excavation and backfilling for roads and highways are usually measured by volume (m³) or linear meters (m), depending on the type of work.

Item Description

Quantity (m³ or m)

Rate

Amount

Excavation for roadbed

200 m³

₹500/m³

₹100,000

Backfilling for roadbed

150 m³

₹400/m³

₹60,000

Example:
Roadbed excavation is measured by volume (m³), while backfilling is also measured in cubic meters (m³). For 200 m³ of excavation at ₹500 per m³, the total cost will be ₹100,000.

108. Measurement for Cement Concrete Works

Cement concrete works, such as foundation footings, slabs, and pavements, are typically measured by volume (m³).

Item Description

Quantity (m³)

Rate

Amount

Concrete footing for foundation

50 m³

₹5500/m³

₹275,000

Concrete pavement for road

100 m³

₹6000/m³

₹600,000

Example:
Cement concrete works are measured in cubic meters (m³). For concrete footing, 50 m³ at ₹5500 per cubic meter results in ₹275,000. Similarly, concrete pavement (100 m³ at ₹6000 per cubic meter) will total ₹600,000.

109. Measurement for Temporary Site Lighting and Power Supply

Temporary site lighting and power supply are essential for construction activities, especially for night work. These works are measured by duration or by units, depending on the setup.

Item Description

Quantity (Units or Hours)

Rate

Amount

Temporary lighting setup

10 units

₹5000/unit

₹50,000

Power supply for site activities

200 hours

₹100/hr

₹20,000

Example:
Temporary lighting is measured by units, and power supply is measured by hours. For 10 lighting units at ₹5000 per unit, the total cost will be ₹50,000. For 200 hours of power supply at ₹100 per hour, the total cost will be ₹20,000.

110. Measurement for Utility Ductwork and Piping

Utility ductwork and piping for services such as electrical, HVAC, and plumbing are measured based on length (m) or the number of installations (units).

Item Description

Quantity (m or Units)

Rate

Amount

HVAC ductwork installation

100 m

₹1500/m

₹150,000

Electrical conduit installation

200 m

₹500/m

₹100,000

Example:
HVAC ductwork is measured by length (m), and for 100 meters of ducting at ₹1500 per meter, the cost will be ₹150,000. Electrical conduit is measured in the same way, with a total cost of ₹100,000 for 200 meters at ₹500 per meter.

111. Measurement for Stone Masonry and Cladding

Stone masonry works, including walls, cladding, and paving, are typically measured by volume (m³) or area (m²), depending on the application.

Item Description

Quantity (m³ or m²)

Rate

Amount

Stone masonry for wall

50 m³

₹4500/m³

₹225,000

Stone cladding for facade

200 m²

₹400/m²

₹80,000

Example:
Stone masonry is usually measured by volume (m³), and cladding is measured by area (m²). For stone masonry (50 m³ at ₹4500 per m³), the cost will be ₹225,000. Stone cladding for 200 m² at ₹400 per square meter will cost ₹80,000.

112. Measurement for Road Sub-Base and Base Course

For road construction, the sub-base and base course layers are critical for structural support. These are usually measured by volume (m³) or area (m²), depending on the project.

Item Description

Quantity (m³ or m²)

Rate

Amount

Sub-base layer construction

500 m³

₹400/m³

₹200,000

Base course layer construction

600 m³

₹500/m³

₹300,000

Example:
The sub-base layer is typically measured by volume (m³), and base course layers are similarly measured in cubic meters (m³). For 500 m³ of sub-base at ₹400 per m³, the cost will be ₹200,000.

113. Measurement for Foundation Works (Pile Caps and Footings)

Foundation works for pile caps, footings, and other elements are measured based on volume (m³) or the number of units.

Item Description

Quantity (m³ or Units)

Rate

Amount

Pile cap construction

50 m³

₹6000/m³

₹300,000

Footing for foundation

100 m³

₹5500/m³

₹550,000

Example:
Pile caps are measured by volume (m³), and for 50 m³ at ₹6000 per cubic meter, the total cost is ₹300,000. Footings are similarly measured by volume (m³).

114. Measurement for Building Envelope (Walls, Windows, Doors)

Building envelope works, which include the construction of exterior walls, windows, and doors, are measured by area (m²) or number of units for items like windows and doors.

Item Description

Quantity (m² or Units)

Rate

Amount

External wall construction

500 m²

₹400/m²

₹200,000

Window installation

10 units

₹5000/unit

₹50,000

Door installation

10 units

₹3000/unit

₹30,000

Example:
External wall construction is measured by area (m²), while windows and doors are measured by units. For 500 m² of wall construction at ₹400 per square meter, the cost will be ₹200,000.

115. Measurement for Surface Finishing (Plastering, Rendering, etc.)

Surface finishing works, including plastering and rendering, are typically measured by area (m²) or volume (m³), depending on the finish type.

Item Description

Quantity (m² or m³)

Rate

Amount

Plastering for walls

1000 m²

₹40/m²

₹40,000

Rendering for exterior walls

500 m²

₹60/m²

₹30,000

Example:
Plastering is measured by area (m²), and for 1000 m² of plastering at ₹40 per square meter, the total cost will be ₹40,000.

116. Measurement for Flooring and Tiling

Flooring works, such as tile installation, are usually measured by area (m²), based on the surface area to be covered.

Item Description

Quantity (m²)

Rate

Amount

Ceramic tile flooring

500 m²

₹600/m²

₹300,000

Marble flooring

200 m²

₹1000/m²

₹200,000

Example:
Flooring works like tile and marble installation are measured by area (m²). For 500 m² of ceramic tile flooring at ₹600 per square meter, the total cost will be ₹300,000.

117. Measurement for Earthworks for Landscaping

Landscaping works often require excavation and grading, typically measured by area (m²) or volume (m³), depending on the task.

Item Description

Quantity (m² or m³)

Rate

Amount

Landscaping earthworks (excavation)

200 m³

₹400/m³

₹80,000

Grading for garden area

1000 m²

₹20/m²

₹20,000

Example:
Landscaping earthworks such as excavation are measured in cubic meters (m³), while grading is measured by area (m²). For 200 m³ of excavation at ₹400 per cubic meter, the cost will be ₹80,000.

118. Measurement for Asphalt Milling and Resurfacing

Asphalt milling and resurfacing are common tasks in road maintenance and rehabilitation. Milling involves removing a portion of the existing pavement, while resurfacing involves applying a new layer of asphalt. These works are typically measured by area (m²) for the resurfaced pavement and volume (m³) for milling.

Item Description

Quantity (m² or m³)

Rate

Amount

Asphalt milling (removal)

2000 m²

₹50/m²

₹100,000

Asphalt resurfacing

2000 m²

₹800/m²

₹1,600,000

Example:
Asphalt milling is measured by area (m²), and resurfacing is similarly measured in square meters (m²). For 2000 m² of milling at ₹50 per m², the cost is ₹100,000. Resurfacing 2000 m² at ₹800 per m² totals ₹1,600,000.

119. Measurement for Tunnel Excavation and Lining

Tunnel excavation and lining works are critical for underground infrastructure. These are measured by volume (m³) for excavation and area (m²) for lining.

Item Description

Quantity (m³ or m²)

Rate

Amount

Tunnel excavation

5000 m³

₹1200/m³

₹6,000,000

Tunnel lining

2000 m²

₹2000/m²

₹4,000,000

Example:
Tunnel excavation is measured in cubic meters (m³), and for 5000 m³ at ₹1200 per m³, the cost will be ₹6,000,000. Tunnel lining is measured by area (m²), and for 2000 m² at ₹2000 per m², the cost will be ₹4,000,000.

120. Measurement for Bridge Construction (Deck, Beams, Piers)

Bridge construction includes various components like decks, beams, and piers, which are typically measured by volume (m³) or length (m) depending on the element.

Item Description

Quantity (m³ or m)

Rate

Amount

Concrete deck for bridge

1000 m³

₹6000/m³

₹6,000,000

Bridge beams

200 m

₹2000/m

₹400,000

Bridge piers

50 m³

₹7000/m³

₹350,000

Example:
Concrete deck is measured by volume (m³), while beams and piers are typically measured by length (m) for beams and volume (m³) for piers. For 1000 m³ of deck at ₹6000 per m³, the total cost is ₹6,000,000.

121. Measurement for Drainage Systems (Manholes, Pipes, Culverts)

Drainage systems, including manholes, pipes, and culverts, are measured by the length (m) for pipes, units for manholes, and volume (m³) for excavation.

Item Description

Quantity (m, Units, or m³)

Rate

Amount

Pipe laying for drainage

500 m

₹800/m

₹400,000

Manhole construction

10 units

₹15,000/unit

₹150,000

Culvert excavation

50 m³

₹700/m³

₹35,000

Example:
Pipe laying is measured in meters (m), with 500 m at ₹800 per meter totaling ₹400,000. Manholes are measured by units, and culvert excavation is measured by volume (m³).

122. Measurement for Water Supply Systems (Pipes, Pump Stations)

Water supply systems typically involve piping and pump station installation. Piping is measured by length (m), while pump stations are often measured by the number of units.

Item Description

Quantity (m or Units)

Rate

Amount

Water supply pipe installation

300 m

₹600/m

₹180,000

Pump station installation

2 units

₹200,000/unit

₹400,000

Example:
Water supply pipes are measured by length (m), and pump stations by units. For 300 meters of piping at ₹600 per meter, the total cost is ₹180,000.

123. Measurement for Site Preparation and Earthworks

Site preparation and earthworks, such as clearing vegetation, leveling, and grading, are typically measured by area (m²) or volume (m³).

Item Description

Quantity (m² or m³)

Rate

Amount

Site clearing and leveling

1000 m²

₹25/m²

₹25,000

Earth excavation for grading

500 m³

₹400/m³

₹200,000

Example:
Site clearing is measured in square meters (m²), and excavation for grading is measured in cubic meters (m³). For 1000 m² of clearing at ₹25 per square meter, the cost is ₹25,000.

124. Measurement for Steel Reinforcement (BBS)

Steel reinforcement for concrete work is measured by weight (kg or tons), typically based on the Bar Bending Schedule (BBS), which provides detailed measurements for reinforcement bars used in slabs, beams, and columns.

Item Description

Quantity (kg or Tons)

Rate

Amount

Reinforcement for slab

2000 kg

₹80/kg

₹160,000

Reinforcement for beams

1000 kg

₹90/kg

₹90,000

Example:
Reinforcement is measured by weight. For 2000 kg of reinforcement at ₹80 per kg, the cost is ₹160,000.

125. Measurement for Finishing Works (Plastering, Painting, etc.)

Finishing works, such as plastering, painting, and rendering, are typically measured by area (m²), depending on the type of work and the surface to be covered.

Item Description

Quantity (m²)

Rate

Amount

Plastering for internal walls

500 m²

₹50/m²

₹25,000

Painting for exterior walls

600 m²

₹100/m²

₹60,000

Example:
Plastering is measured by area (m²), and for 500 m² at ₹50 per square meter, the total cost will be ₹25,000. Painting is similarly measured by area, with 600 m² costing ₹60,000.

126. Measurement for Site Drainage (Sewerage and Stormwater)

Site drainage, including sewerage and stormwater systems, is measured by the length of piping laid, volume of excavation, and units of manholes and chambers.

Item Description

Quantity (m, m³, or Units)

Rate

Amount

Stormwater pipe laying

400 m

₹700/m

₹280,000

Sewerage trench excavation

150 m³

₹350/m³

₹52,500

Manhole construction

8 units

₹12,000/unit

₹96,000

Example:
Stormwater pipe laying is measured in meters (m), with 400 meters at ₹700 per meter costing ₹280,000. Sewerage trench excavation is based on volume (m³).

127. Measurement for Substructure and Superstructure Works

Substructure works, like foundation excavation and concrete pouring, are measured by volume (m³), while superstructure works, like framing and roofing, are often measured by area (m²) or units.

Item Description

Quantity (m² or m³)

Rate

Amount

Excavation for foundation

300 m³

₹450/m³

₹135,000

Concrete column construction

50 m³

₹6000/m³

₹300,000

Example:
Substructure excavation is measured by volume (m³), and for 300 m³ at ₹450 per cubic meter, the total cost is ₹135,000.

128. Measurement for Tunnel Ventilation and Lighting Systems

For tunnels, both ventilation and lighting systems are critical for safety and functionality. These are measured based on the length of ductwork or the number of units installed.

Item Description

Quantity (m or Units)

Rate

Amount

Tunnel ventilation ducting

500 m

₹1000/m

₹500,000

Tunnel lighting installation

100 units

₹5000/unit

₹500,000

Example:
Ventilation ducting is measured by length (m). For 500 meters of ducting at ₹1000 per meter, the total cost will be ₹500,000. Tunnel lighting is measured by units, with 100 lights at ₹5000 each totaling ₹500,000.

129. Measurement for Precast Concrete Elements (Panels, Beams, Slabs)

Precast concrete elements are measured based on their volume (m³) or area (m²) depending on the component type. These elements are fabricated off-site and then transported to the construction site.

Item Description

Quantity (m³ or m²)

Rate

Amount

Precast concrete panels

200 m²

₹350/m²

₹70,000

Precast concrete beams

100 m³

₹5000/m³

₹500,000

Example:
Precast concrete panels are typically measured by area (m²), with 200 m² of panels at ₹350 per square meter totaling ₹70,000. Beams are measured by volume (m³), with 100 m³ at ₹5000 per cubic meter totaling ₹500,000.

130. Measurement for Road Construction Layers (Base, Sub-base, Asphalt)

For road construction, different layers like the base, sub-base, and asphalt surfacing are measured by volume (m³) or area (m²), depending on the layer.

Item Description

Quantity (m³ or m²)

Rate

Amount

Sub-base layer

300 m³

₹400/m³

₹120,000

Base layer

500 m³

₹450/m³

₹225,000

Asphalt surfacing

2000 m²

₹800/m²

₹1,600,000

Example:
Sub-base and base layers are measured by volume (m³), while asphalt surfacing is measured by area (m²). The total cost for asphalt surfacing for 2000 m² at ₹800 per square meter is ₹1,600,000.

131. Measurement for Steel Structural Work (Columns, Beams, Bracing)

Steel structural work, including the fabrication and erection of columns, beams, and bracing, is typically measured by weight (kg or tons).

Item Description

Quantity (kg or Tons)

Rate

Amount

Steel columns

2000 kg

₹80/kg

₹160,000

Steel beams

3000 kg

₹85/kg

₹255,000

Steel bracing

1500 kg

₹90/kg

₹135,000

Example:
Steel columns are measured by weight (kg), with 2000 kg at ₹80 per kg totaling ₹160,000. Similarly, beams and bracing are measured by weight, leading to the respective costs.

132. Measurement for MEP Systems (Mechanical, Electrical, Plumbing)

MEP systems (Mechanical, Electrical, Plumbing) are critical for a building’s functionality and safety. These are typically measured by length for piping and ducting, or by the number of units installed for fixtures.

Item Description

Quantity (m or Units)

Rate

Amount

HVAC duct installation

300 m

₹1000/m

₹300,000

Plumbing pipe installation

500 m

₹500/m

₹250,000

Electrical panel installation

10 units

₹20,000/unit

₹200,000

Example:
HVAC ducts are measured by length (m), with 300 m of ductwork at ₹1000 per meter totaling ₹300,000. Plumbing pipes are also measured by length, and electrical panels by units.

133. Measurement for Asphalt Pavement (Roads, Parking Lots)

Asphalt pavement for roads, parking lots, or other surfaces is typically measured by area (m²) to account for the surface coverage.

Item Description

Quantity (m²)

Rate

Amount

Asphalt paving for roads

1000 m²

₹900/m²

₹900,000

Asphalt parking lot paving

500 m²

₹1000/m²

₹500,000

Example:
Asphalt paving is measured by area (m²), and for 1000 m² at ₹900 per square meter, the total cost will be ₹900,000.

134. Measurement for Steel Reinforcement (Tying and Placing)

Steel reinforcement, including the tying and placing of steel bars for concrete elements like slabs, beams, and foundations, is measured by weight (kg or tons).

Item Description

Quantity (kg or Tons)

Rate

Amount

Reinforcement for slab

3000 kg

₹80/kg

₹240,000

Reinforcement for beam

2000 kg

₹90/kg

₹180,000

Example:
Steel reinforcement is measured by weight (kg), and for 3000 kg of steel for a slab at ₹80 per kg, the total cost will be ₹240,000.

135. Measurement for Roofing Works (Metal, Tile, Concrete)

Roofing works, such as the installation of metal sheets, tiles, or concrete roofs, are measured by area (m²) or sometimes by weight, depending on the roofing material used.

Item Description

Quantity (m²)

Rate

Amount

Metal roof installation

500 m²

₹600/m²

₹300,000

Tile roof installation

300 m²

₹700/m²

₹210,000

Example:
Metal roofing is measured by area (m²), and for 500 m² at ₹600 per square meter, the total cost will be ₹300,000.

136. Measurement for Concrete Road Works (Sub-base, Base, Asphalt Layer)

For road construction, concrete work is a key component. These are measured by volume (m³) for sub-base and base layers and by area (m²) for the asphalt surface.

Item Description

Quantity (m³ or m²)

Rate

Amount

Concrete sub-base layer

200 m³

₹400/m³

₹80,000

Concrete base layer

300 m³

₹450/m³

₹135,000

Asphalt surfacing for road

2000 m²

₹800/m²

₹1,600,000

Example:
Concrete sub-base and base layers are measured in cubic meters (m³), while the asphalt layer is measured by area (m²). The total cost for the asphalt layer for 2000 m² at ₹800 per square meter is ₹1,600,000.

137. Measurement for Interior Finishing (Drywall, Ceiling, Flooring)

Interior finishing works, including drywall, ceilings, and flooring, are measured by area (m²) or sometimes by unit for certain components.

Item Description

Quantity (m² or Units)

Rate

Amount

Drywall installation

500 m²

₹200/m²

₹100,000

Ceiling installation

300 m²

₹250/m²

₹75,000

Flooring installation

200 m²

₹300/m²

₹60,000

Example:
Drywall and ceiling installation are measured by area (m²), while flooring is similarly measured by area. For drywall installation of 500 m² at ₹200 per square meter, the total cost will be ₹100,000.

138. Measurement for Concrete Formwork

Formwork for concrete elements like beams, columns, and slabs is typically measured by area (m²), reflecting the surface area to be formed.

Item Description

Quantity (m²)

Rate

Amount

Formwork for concrete beams

200 m²

₹150/m²

₹30,000

Formwork for concrete columns

100 m²

₹200/m²

₹20,000

Example:
Formwork is measured by area (m²). For beam formwork (200 m² at ₹150 per square meter), the total cost will be ₹30,000.

139. Measurement for Earthworks for Landscaping (Excavation, Backfilling, Grading)

Landscaping requires various earthworks such as excavation, backfilling, and grading. These are typically measured by volume (m³) or area (m²), depending on the scope of work.

Item Description

Quantity (m³ or m²)

Rate

Amount

Excavation for landscaping

100 m³

₹500/m³

₹50,000

Backfilling for landscaping

50 m³

₹400/m³

₹20,000

Grading for lawn area

500 m²

₹30/m²

₹15,000

Example:
Excavation for landscaping is measured by volume (m³), with 100 m³ of earthwork at ₹500 per cubic meter totaling ₹50,000. Grading is measured by area (m²), with 500 m² of lawn area graded at ₹30 per square meter totaling ₹15,000.

140. Measurement for Roadworks (Pothole Repair, Crack Filling)

Road maintenance works like pothole repairs and crack filling are typically measured by area (m²) or linear meter (lm), depending on the type of repair.

Item Description

Quantity (m² or lm)

Rate

Amount

Pothole repair

100 m²

₹100/m²

₹10,000

Crack filling

200 lm

₹50/lm

₹10,000

Example:
Pothole repair is measured by area (m²), and for 100 m² at ₹100 per square meter, the total cost will be ₹10,000. Crack filling is measured by linear meter (lm), with 200 lm at ₹50 per meter costing ₹10,000.

141. Measurement for Precast Concrete Stairs

Precast concrete stairs are a common feature in multi-story buildings and are typically measured by the number of staircases or by the area of stair treads and risers.

Item Description

Quantity (Units or m²)

Rate

Amount

Precast concrete stairs

5 units

₹50,000/unit

₹250,000

Staircase treads (precast)

20 m²

₹800/m²

₹16,000

Example:
Precast concrete stairs are typically measured by units, and for 5 staircases at ₹50,000 per unit, the total cost will be ₹250,000. For precast stair treads, the measurement is by area (m²).

142. Measurement for Structural Columns and Foundations

Structural columns and foundation elements such as footings and pile caps are generally measured by volume (m³), and sometimes by the number of units for items like piers.

Item Description

Quantity (m³ or Units)

Rate

Amount

Concrete for foundation footings

150 m³

₹5000/m³

₹750,000

Concrete columns

100 m³

₹6000/m³

₹600,000

Pile cap construction

30 units

₹20,000/unit

₹600,000

Example:
Foundation footings and columns are measured by volume (m³), while pile caps are measured by units. For 150 m³ of concrete for footings at ₹5000 per cubic meter, the total cost will be ₹750,000.

143. Measurement for Floor Slab Reinforcement (BBS)

Floor slab reinforcement, based on the Bar Bending Schedule (BBS), is usually measured by weight (kg or tons), reflecting the quantity of steel reinforcement used in concrete slabs.

Item Description

Quantity (kg or Tons)

Rate

Amount

Reinforcement for floor slab

2000 kg

₹80/kg

₹160,000

Reinforcement for beams

1000 kg

₹90/kg

₹90,000

Example:
Reinforcement for floor slabs is measured by weight (kg). For 2000 kg of reinforcement at ₹80 per kg, the total cost will be ₹160,000.

144. Measurement for Asphalt Crack Sealing

Asphalt crack sealing is a maintenance procedure for roads, parking lots, or driveways. This work is typically measured by linear meter (lm) based on the length of cracks sealed.

Item Description

Quantity (lm)

Rate

Amount

Asphalt crack sealing

500 lm

₹50/lm

₹25,000

Example:
Asphalt crack sealing is measured by linear meters (lm). For 500 meters of crack sealing at ₹50 per meter, the total cost will be ₹25,000.

145. Measurement for Soundproofing and Acoustic Works

Acoustic treatments such as soundproofing walls, ceilings, and floors are measured by area (m²), depending on the surface treated.

Item Description

Quantity (m²)

Rate

Amount

Soundproofing for walls

300 m²

₹500/m²

₹150,000

Acoustic ceiling installation

400 m²

₹700/m²

₹280,000

Example:
Soundproofing is typically measured by area (m²). For 300 m² of soundproofing at ₹500 per square meter, the total cost will be ₹150,000.

146. Measurement for Site Drainage Systems (French Drains, Culverts)

Drainage systems such as French drains or culverts are measured by length (m) for pipes and trenches or by units for manholes and chambers.

Item Description

Quantity (m or Units)

Rate

Amount

French drain installation

100 m

₹500/m

₹50,000

Culvert installation

50 m

₹1000/m

₹50,000

Manhole construction

10 units

₹15,000/unit

₹150,000

Example:
French drains are measured by length (m), and for 100 meters at ₹500 per meter, the cost will be ₹50,000. Culverts and manholes are measured by units and linear meters (m).

147. Measurement for Interior and Exterior Painting (Walls, Ceilings, Doors)

Interior and exterior painting works are typically measured by area (m²), depending on the surface to be painted (walls, ceilings, doors, etc.).

Item Description

Quantity (m² or Units)

Rate

Amount

Interior wall painting

500 m²

₹100/m²

₹50,000

Exterior wall painting

600 m²

₹150/m²

₹90,000

Door painting

20 units

₹1000/unit

₹20,000

Example:
Interior wall painting is measured by area (m²), and for 500 m² at ₹100 per square meter, the total cost will be ₹50,000. Doors are measured by units, and for 20 doors at ₹1000 each, the total cost will be ₹20,000.

148. Measurement for Cable and Wiring Works

Electrical wiring for lighting, power supply, and other systems is measured by length (m) for cables and wires, or by units for fixtures.

Item Description

Quantity (m or Units)

Rate

Amount

Electrical wiring for lighting

1000 m

₹20/m

₹20,000

Electrical outlets installation

50 units

₹1000/unit

₹50,000

Example:
Electrical wiring is measured by length (m), and for 1000 meters at ₹20 per meter, the total cost will be ₹20,000. Electrical outlets are measured by units, and for 50 units at ₹1000 each, the total cost will be ₹50,000.

149. Measurement for External Works (Landscaping, Pavements, Paving Stones)

External works for public spaces, parking lots, or gardens typically involve paving, landscaping, and installation of features like benches or lighting, all measured by area (m²) or number of items.

Item Description

Quantity (m² or Units)

Rate

Amount

Landscaping (planting, turfing)

500 m²

₹100/m²

₹50,000

Paving stone installation

300 m²

₹500/m²

₹150,000

Benches installation

10 units

₹3000/unit

₹30,000

Example:
Landscaping is measured by area (m²), and for 500 m² at ₹100 per square meter, the cost is ₹50,000. Paving stones are similarly measured by area (m²), and for 300 m² at ₹500 per square meter, the cost is ₹150,000.

150. Measurement for Temporary Site Access Roads

Temporary site access roads, often required for construction activities, are measured by length (m) or area (m²) depending on the design.

Item Description

Quantity (m or m²)

Rate

Amount

Temporary access road installation

500 m

₹200/m

₹100,000

Gravel filling for access road

300 m²

₹150/m²

₹45,000

Example:
Temporary access roads are measured by length (m), and for 500 meters at ₹200 per meter, the total cost will be ₹100,000. Gravel filling is measured by area (m²), with 300 m² at ₹150 per square meter totaling ₹45,000.

Bhadanis Quantity Surveyors Training Institute: Your Gateway to Mastering Billing Engineering for Civil Engineers

Billing engineering is an essential aspect of construction project management. It ensures that work is accurately measured, documented, and billed in a transparent and efficient manner. Whether you're involved in road construction, building projects, or infrastructure development, a strong understanding of billing engineering will make you a valuable asset to any project team. If you're a civil engineer seeking to enhance your knowledge in this critical area, look no further than Bhadanis Quantity Surveyors Training Institute.

Why Choose Bhadanis Quantity Surveyors Training Institute?

At Bhadanis Quantity Surveyors Training Institute, we offer comprehensive online training designed to equip civil engineers with the necessary skills in billing engineering. Our courses are tailored to meet the demands of the modern construction industry, and our expert instructors provide practical insights based on years of hands-on experience.

Here are some reasons why Bhadanis is the right choice for your billing engineering training:

1. Expert-Led Training with Practical Insights

Our trainers at Bhadanis have years of experience in the construction industry, particularly in the field of quantity surveying and billing engineering. The course is designed to provide practical knowledge, which can be applied directly to construction projects. Whether you're dealing with residential, commercial, road, or bridge construction, our training will help you navigate the complexities of billing for each type of project.

2. Comprehensive Course Curriculum

Our online course on billing engineering for civil engineers covers a wide range of topics that are essential for mastering the discipline. Key areas include:

  • Methods of measurement for different construction activities (e.g., concrete, excavation, steel reinforcement).
  • Preparation of Bills of Quantities (BoQ): How to prepare accurate and detailed BoQs that align with the project scope.
  • Rate analysis: Learning how to calculate the rates for various construction activities based on market prices and project requirements.
  • Contractual obligations: Understanding the importance of contract terms and how they influence billing processes.
  • Progress billing and invoicing: How to generate progress bills and track payments accurately throughout the construction project.
  • Estimating variations: Learning how to handle changes in the scope of work and their impact on project costs.

3. Real-World Applications

Our courses focus on real-world applications, ensuring that what you learn is relevant and immediately applicable to your daily tasks. We cover both basic and advanced topics, making the course suitable for both freshers and experienced professionals. Our training is especially beneficial for those involved in large-scale projects such as highways, bridges, and high-rise buildings.

4. Interactive Online Learning

With Bhadanis Quantity Surveyors Training Institute’s online platform, you can access course materials at your own pace. Our interactive training modules include video tutorials, case studies, quizzes, and assignments, which allow you to engage deeply with the material and solidify your understanding. Whether you're a busy professional or a fresh graduate, our flexible learning approach ensures that you can balance your education with your other commitments.

5. Certifications that Enhance Your Career

Upon completion of our online training, you will receive a certification that adds immense value to your professional portfolio. This certification is a testament to your proficiency in billing engineering, showcasing your commitment to excellence in the construction industry. It also significantly enhances your career prospects, making you more competitive in the job market.

6. Specialized Courses for Civil Engineers

We understand that civil engineering is a diverse field, and that's why our training is tailored to meet the specific needs of civil engineers. The Bhadanis Quantity Surveyors Training Institute focuses on the aspects of billing engineering that directly affect your work, including cost control, budgeting, and contract management. Whether you're looking to enhance your existing skills or dive into new areas of quantity surveying, we offer specialized training designed for civil engineers.

7. Affordable and Accessible

We believe in making high-quality education accessible. Bhadanis offers affordable pricing for all our courses without compromising on the quality of content. Plus, being an online course, it is accessible from anywhere in the world. This means that you can gain world-class knowledge and certifications without the need to travel or take time off work.

Conclusion

At Bhadanis Quantity Surveyors Training Institute, we are committed to providing civil engineers with the skills they need to excel in billing engineering. Whether you're just starting out or looking to expand your expertise, our online training programs are designed to help you become proficient in this critical aspect of construction management. Join us today and take the next step in advancing your career in civil engineering.

For more details, visit Bhadanis Quantity Surveyors Training Institute and start your journey toward becoming a billing engineering expert.Tue Dec 24, 2024

Pop-Up Message
Call Us CALL US !