There are no items in your cart
Add More
Add More
Item Details | Price |
---|
Before anything, you have to get the site surveyed and perform soil testing. This will tell you the condition of the land, whether it’s suitable for a high-rise, and how deep the foundation should be.
Example: Let's say the soil test shows that you need a 20-meter-deep pile foundation. You’ll now know exactly what kind of machinery, labor, and time it will take to complete this foundation.
Next, you need a Master Schedule for the project. This is like your project’s roadmap, showing all the tasks from start to finish.
Example: For G+30, you may plan around 2-3 floors per month for the structure. So, if you’re aiming for 30 floors, it could take around 12-15 months for just the structure, assuming you have smooth progress.
Once you have the plan, now it’s time to think about resources:
Example: If you’re on the 15th floor, you need the crane to lift steel bars to that height. So, you’ll plan the timing and availability of the crane based on your floor construction schedule.
The foundation is critical, and it has to be done right, as it supports the entire building.
Example: If the soil test recommended a pile foundation 20 meters deep, you’ll need a rig to drill and place piles. Once done, you’ll pour concrete for the pile caps and raft foundation.
Once the foundation is complete, you can move to the superstructure, which is the actual construction of floors.
Example: For a G+30 building, each floor might take 7-10 days for casting and curing. By sticking to this cycle, you ensure smooth progress without too many interruptions.
As the structure goes up, you also need to plan for Mechanical, Electrical, and Plumbing (MEP) work. These services have to be installed in coordination with the construction.
Example: If you’re on the 10th floor and realize that the plumbing isn’t aligned, you’ll face delays because now you might need to break the concrete or make adjustments. Coordinating MEP from the start avoids such issues.
Once the structure is up, you move on to brickwork and plastering. This phase involves:
Example: Let’s say you finish the structure and begin plastering. You need to schedule different teams for different tasks (like a team for brickwork, another for plastering), ensuring smooth handover from one activity to the next.
The final stage is finishing. This includes laying tiles, painting the walls, fixing false ceilings, and installing electrical fittings. You also install elevators, a critical part of high-rise buildings.
Example: Once the painting is complete, the electrical team will come in to install switches and lighting fixtures. Then, you’ll run final quality checks before handing over the building.
Throughout the project, you need to focus on quality control and safety. This includes:
Example: You might have a safety officer who conducts daily checks to ensure there are no hazards like exposed wiring or unsecured scaffolding.
Once all the work is done, the final phase is the handover. This includes:
Example: After inspecting the building and ensuring it meets all safety and quality standards, you’ll hand over the keys and close out the project with any final paperwork.
https://www.bhadanisrecordedlectures.com/s/store
Sat Sep 7, 2024