500 Important Terms of Construction Management For Civil Engineers and Managers

1. Scope

Definition: Scope refers to the overall work that needs to be done for a project. It includes the project's objectives, deliverables, and tasks. Example: When building a high-rise apartment, the scope would include designing, constructing, and ensuring all floors have necessary utilities like water and electricity.


2. Milestone

Definition: A milestone is a significant event or achievement in the project timeline, such as the completion of a key phase. Example: In road construction, completing the foundation layer might be a milestone.


3. Critical Path

Definition: This is the longest sequence of activities in a project that determines the shortest possible duration to complete it. Example: For building a bridge, the critical path could involve laying the foundation, followed by erecting the pillars, and finally placing the deck.


4. Gantt Chart

Definition: A visual tool for scheduling and tracking project timelines. It shows tasks along a horizontal timeline. Example: A Gantt chart might show that plumbing needs to start after the walls are erected in a residential building project.


5. Baseline

Definition: A baseline is the original plan or scope that the project’s progress is measured against. Example: If the estimated cost of a commercial building is $2 million, this becomes the baseline for tracking budget deviations.


6. Deliverable

Definition: A deliverable is a tangible or intangible output that is produced as a result of the project. Example: A fully constructed shopping mall is the final deliverable of a construction project.


7. Resource Allocation

Definition: This refers to assigning resources—such as labor, materials, and equipment—across different project activities. Example: Allocating 10 laborers to foundation work and 5 to brick-laying in a housing project.


8. Stakeholder

Definition: A stakeholder is anyone affected by or involved in the project, such as clients, contractors, or government officials. Example: In the construction of a hospital, stakeholders could include doctors, patients, and health department officials.


9. Risk Management

Definition: Risk management involves identifying, assessing, and mitigating potential risks that may affect the project. Example: In building a dam, risks like flooding during construction could be identified and managed by installing temporary drainage systems.


10. Change Order

Definition: A change order is a formal request to alter the original scope of work or budget. Example: A client might request additional floors to be added to an office building, requiring a change order.


11. Budget Overrun

Definition: This occurs when the actual project costs exceed the estimated budget. Example: If building a school was estimated to cost $1 million but ends up costing $1.2 million, that’s a budget overrun.


12. Work Breakdown Structure (WBS)

Definition: WBS is a method of breaking down a project into smaller, manageable tasks. Example: In constructing a hotel, the WBS might break down tasks into foundation work, electrical installations, plumbing, and finishing.


13. Procurement

Definition: Procurement is the process of obtaining goods and services needed for the project. Example: Sourcing concrete from a supplier for a bridge construction project.


14. Quality Assurance (QA)

Definition: QA is a set of activities designed to ensure that the project meets the quality standards set out in the plan. Example: Testing the strength of concrete to ensure it meets safety standards during a building project.


15. Kickoff Meeting

Definition: A kickoff meeting is the first official meeting where the project is initiated, and key details are discussed. Example: Before starting the construction of an airport, the project team meets with the client to clarify objectives.


16. Manpower Planning

Definition: This involves determining the labor force required to complete the project on time. Example: Estimating the need for 50 laborers for a 6-month road construction project.


17. Feasibility Study

Definition: A feasibility study evaluates whether a project is practical and likely to succeed. Example: Conducting a feasibility study to determine if the soil conditions are suitable for a high-rise building.


18. Sustainability

Definition: Sustainability involves ensuring that the project minimizes environmental impact and is eco-friendly. Example: Using solar panels in a housing project to reduce energy consumption.


19. Lead Time

Definition: Lead time is the time between placing an order for materials and when they are delivered to the site. Example: If it takes 2 weeks for steel beams to be delivered, that’s the lead time.


20. Float

Definition: Float is the amount of time that a task can be delayed without affecting the project’s completion date. Example: If painting can start 2 days later without delaying the overall project, it has a float of 2 days.


21. General Contractor

Definition: A general contractor is responsible for overseeing the entire construction project, including managing subcontractors and suppliers. Example: In a mall construction project, the general contractor coordinates with electricians, plumbers, and carpenters.


22. Punch List

Definition: A punch list is a document detailing items that need to be fixed or completed before the project is considered finished. Example: In a newly built apartment, the punch list might include items like fixing a faulty light fixture or repainting a wall.


23. Cost Estimate

Definition: A cost estimate is the approximation of the total expenses for completing a project. Example: Estimating $500,000 for building a small commercial complex based on labor, materials, and equipment costs.


24. Project Manager

Definition: A project manager is the person responsible for planning, executing, and completing a project within scope, budget, and time constraints. Example: A project manager overseeing the construction of a highway, ensuring tasks are completed as per schedule.


25. Subcontractor

Definition: A subcontractor is a specialist hired by the general contractor to complete specific tasks, like plumbing or electrical work. Example: Hiring a plumbing subcontractor to install water systems in a hotel.


26. BIM (Building Information Modeling)

Definition: BIM is a digital representation of a construction project, integrating data from all stakeholders. Example: Using BIM to plan the construction of a sports stadium, visualizing structures before they are built.


27. Site Supervisor

Definition: A site supervisor manages the daily operations at a construction site, ensuring everything runs smoothly. Example: A site supervisor at a residential project ensures workers are on task and safety measures are followed.


28. Contingency Plan

Definition: A contingency plan is a backup plan for handling potential risks or unforeseen issues during a project. Example: In road construction, a contingency plan may involve using alternative materials if the original supplier fails to deliver.


29. Earned Value Management (EVM)

Definition: EVM is a project management technique for measuring project performance and progress in terms of cost and schedule. Example: Using EVM to track the financial performance of a dam construction project against the original budget.


30. Punch-Out Work

Definition: Punch-out work refers to minor fixes and final touches that need to be completed before final project handover. Example: In a newly constructed office building, punch-out work might include fixing door handles or adjusting lighting fixtures.


31. Change Control

Definition: Change control is the process of managing changes to the project’s scope, schedule, or budget. Example: Adjusting the project plan to accommodate changes requested by the client, such as adding a new wing to a hospital.


32. Job Safety Analysis (JSA)

Definition: JSA is a process that identifies potential hazards in each step of a job to reduce risks. Example: Conducting a JSA before starting excavation to identify risks like underground cables.


33. Cost-Benefit Analysis

Definition: A cost-benefit analysis evaluates the financial benefits of a project relative to its costs. Example: Deciding to construct a multi-story parking lot after a cost-benefit analysis shows potential long-term revenue.


34. Value Engineering

Definition: Value engineering involves analyzing a project to improve function, reduce costs, and ensure high-quality results. Example: Replacing expensive marble with durable, less costly granite in a hotel to save costs without compromising quality.


35. Site Logistics Plan

Definition: A site logistics plan organizes the movement of people, equipment, and materials on a construction site. Example: Planning where to store construction materials on a busy city-center site to ensure efficient workflow.


36. Labor Productivity

Definition: Labor productivity measures the output of workers over a period of time. Example: Tracking the number of bricks laid by a mason per day to gauge labor productivity in a housing project.


37. Material Takeoff (MTO)

Definition: An MTO is a detailed list of all the materials required to complete a construction project. Example: Creating an MTO for a shopping mall project to determine the exact quantity of concrete, steel, and other materials needed.


38. Permitting

Definition: Permitting refers to the process of obtaining legal approvals from local authorities before starting construction. Example: Securing a building permit for a high-rise apartment in an urban area to comply with zoning laws.


39. As-Built Drawings

Definition: As-built drawings reflect the final version of the project as it was actually built, accounting for any changes made during construction. Example: Creating as-built drawings for a residential tower that show all the electrical and plumbing systems installed.


40. Site Inspection

Definition: Site inspections involve checking the construction site to ensure that the project is progressing according to plan and regulations. Example: A site inspection at a bridge project might check if the foundations have been laid correctly.


41. Lead Time

Definition: Lead time is the time required between placing an order for materials and when they arrive on-site. Example: If ordering steel beams for a skyscraper takes 4 weeks, that's the lead time.


42. Commissioning

Definition: Commissioning is the process of testing and validating building systems to ensure they are functioning correctly before handover. Example: Testing the HVAC system in a newly constructed hospital to ensure it meets design specifications.


43. Fast Tracking

Definition: Fast-tracking is a project management technique where tasks are performed in parallel to save time. Example: Starting electrical wiring before the walls are fully erected in an office building to speed up the project.


44. Liquidated Damages

Definition: Liquidated damages are pre-determined penalties for delays in project completion. Example: If a contractor fails to complete a highway on time, they may face liquidated damages of $5,000 per day.


45. Pre-construction Phase

Definition: The pre-construction phase involves planning and preparation activities before physical construction begins. Example: Conducting a site survey and finalizing designs before starting the construction of a school.


46. Snagging

Definition: Snagging refers to identifying and fixing minor defects or unfinished work towards the end of a project. Example: Noticing that some doors in a new office building need adjustment before the final handover.


47. Project Closeout

Definition: Project closeout is the final phase of the project, involving the completion of paperwork, handover, and post-construction activities. Example: Completing the final inspections, delivering as-built drawings, and handing over a completed commercial complex to the client.


48. Bill of Quantities (BOQ)

Definition: The BOQ is a document that lists the quantities and costs of materials and labor required for a project. Example: Creating a BOQ for a housing development project to determine the cost of materials and labor for 100 homes.


49. Project Charter

Definition: A project charter is a formal document that authorizes the project, outlining its objectives, stakeholders, and scope. Example: Drafting a project charter for the construction of a government office complex, including the goals and timeline.


50. Contractor

Definition: A contractor is an individual or company hired to perform specific tasks in a construction project, typically overseeing labor, materials, and equipment. Example: A contractor might be hired to complete the entire construction of a residential building, from foundation to finishing.



51. Punch List

Definition: A punch list is a document that outlines items that need to be completed or fixed before the project can be considered complete. Example: A punch list for a hotel project might include repainting a wall or fixing a leaking tap before the final handover.


52. Retainage

Definition: Retainage refers to a portion of the payment withheld from a contractor until the project is completed satisfactorily. Example: A construction contract may withhold 5% of the payment until the contractor finishes the remaining work in a school project.


53. Handover

Definition: Handover is the process of transferring responsibility for the project from the contractor to the client after completion. Example: In a commercial building project, the contractor officially hands over the keys to the client after a final inspection.


54. Time and Materials Contract

Definition: This type of contract involves billing the client for the actual time worked and the materials used. Example: A contractor building a custom house might use a time and materials contract where the client is billed based on hours worked and materials purchased.


55. Prime Contractor

Definition: A prime contractor is the main contractor responsible for the overall project, overseeing all other subcontractors. Example: A prime contractor managing the construction of a shopping mall would coordinate the plumbing, electrical, and structural subcontractors.


56. Shop Drawings

Definition: Shop drawings are detailed drawings or diagrams that show how certain elements of a construction project will be fabricated and installed. Example: A shop drawing for the steel beams in a high-rise building would show the exact measurements and placement details for installation.


57. Contract Administration

Definition: Contract administration involves managing and overseeing all aspects of a contract throughout the construction project. Example: A project manager might oversee the contract administration for a highway project, ensuring that all terms are followed and documented.


58. Cost Control

Definition: Cost control refers to the process of monitoring project expenses to ensure that the project stays within the approved budget. Example: Implementing cost control measures during the construction of a hospital to prevent exceeding the initial budget of $5 million.


59. Safety Officer

Definition: A safety officer is responsible for ensuring that the construction site complies with all safety regulations to prevent accidents. Example: A safety officer at a construction site might conduct regular inspections to ensure workers are wearing helmets and safety gear.


60. Soft Costs

Definition: Soft costs are indirect expenses that are not directly related to physical construction, such as legal fees, design fees, or permits. Example: Hiring an architect and obtaining building permits for a residential project are examples of soft costs.


61. Hard Costs

Definition: Hard costs refer to the tangible, direct costs associated with physical construction, such as materials, labor, and equipment. Example: Purchasing cement, bricks, and hiring workers for a building project are hard costs.


62. Defect Liability Period

Definition: The defect liability period is the time during which the contractor is responsible for fixing any defects in the project after completion. Example: A contractor building a hotel might be responsible for fixing plumbing issues discovered during the defect liability period.


63. Schedule of Values

Definition: A schedule of values is a document that breaks down the total project cost into individual components, showing how the budget is allocated. Example: A schedule of values for a school construction project might show that $100,000 is allocated for roofing and $50,000 for electrical work.


64. Liquidation

Definition: Liquidation refers to the process of winding up a construction project’s financial obligations, settling any debts, and closing accounts. Example: After completing the construction of a bridge, the contractor settles final payments and closes the project’s accounts through liquidation.


65. Mobilization

Definition: Mobilization is the process of setting up the resources, equipment, and labor required to begin construction on-site. Example: Mobilizing for a road project would include setting up temporary offices, bringing in machinery, and getting workers on-site.


66. Procurement Strategy

Definition: A procurement strategy outlines the plan for acquiring materials, equipment, and services needed for a project. Example: A construction manager for a railway station might create a procurement strategy to purchase steel from local suppliers to reduce costs.


67. Submittals

Definition: Submittals are documents, materials, or samples submitted by the contractor for approval before starting construction. Example: A contractor submits samples of tiles to the client for approval before installing them in a shopping mall.


68. Tender

Definition: A tender is a formal offer to perform work or supply materials for a specific price, often submitted during the bidding process. Example: Contractors submit tenders to build a new government office complex, detailing costs and timelines for the project.


69. Bid

Definition: A bid is a proposal submitted by a contractor to complete a project, usually outlining costs, timelines, and resources. Example: A contractor submits a bid of $2 million to build a bridge across a river, outlining the work plan and materials required.


70. Cost Baseline

Definition: The cost baseline is the original budget approved for the project, used as a reference point for tracking expenditures. Example: In building a housing complex, the cost baseline might be $10 million, and any deviations from this baseline are monitored closely.


71. Schedule Baseline

Definition: The schedule baseline is the original timeline for the project, used to track the project’s progress. Example: If a road construction project has a schedule baseline of 6 months, this serves as the benchmark for tracking time-related delays or accelerations.


72. Earned Value

Definition: Earned value is a measure used to assess the value of work actually completed compared to the planned budget and schedule. Example: If 50% of a bridge is built at 40% of the budget, the earned value shows the project is financially ahead of schedule.


73. Direct Costs

Definition: Direct costs are expenses that can be directly attributed to a specific task or component of the project. Example: The cost of cement and labor for pouring the foundation of a building are direct costs.


74. Indirect Costs

Definition: Indirect costs are expenses that cannot be directly attributed to a specific task but are necessary for the project’s overall completion. Example: Office rent, utility bills, and administrative costs for managing a construction project are indirect costs.


75. Scope Creep

Definition: Scope creep refers to the uncontrolled expansion of the project’s scope due to additional features or changes, often without adjusting timelines or budgets. Example: If a client requests additional amenities for an office building, like extra floors or parking spaces, that weren't part of the original scope, it could lead to scope creep.


76. Clerk of Works

Definition: The clerk of works is responsible for inspecting the quality of work on-site, ensuring that the project meets the specified standards. Example: A clerk of works might inspect the brickwork in a residential project to ensure it adheres to the construction specifications.


77. Punch-Out List

Definition: A punch-out list is similar to a punch list but focuses specifically on minor items that need fixing toward the end of the project. Example: The punch-out list for a hotel construction might include tasks like fixing chipped paint or re-aligning doors.


78. Permit

Definition: A permit is a legal document issued by the local authority, allowing the project to proceed according to regulations. Example: Before starting a high-rise building in a city, a contractor must obtain a construction permit from the local municipal office.


79. Drawings

Definition: Drawings are technical plans or blueprints that detail the dimensions, layouts, and design elements of the project. Example: Architectural drawings for a hospital project show the layout of patient rooms, hallways, and emergency exits.


80. Owner’s Representative

Definition: An owner’s representative is hired by the project owner to oversee the project and ensure that the contractor follows the owner’s interests. Example: The owner of a commercial complex might hire a representative to ensure the contractor adheres to budget and quality requirements.


81. Building Envelope

Definition: The building envelope refers to the exterior elements of a building, such as walls, windows, roof, and foundation, that protect the interior from outside elements. Example: In a residential tower, the building envelope would include the outer walls, roof, and windows that shield the inside from rain and wind.


82. Takeoff

Definition: Takeoff refers to the process of measuring the quantities of materials required from the project drawings. Example: A contractor performs a takeoff to determine the amount of concrete needed to lay the foundation of a multi-story building.


83. Section

Definition: A section is a drawing that shows a vertical cut through a building, illustrating the internal structure. Example: A section drawing for a school might show how each floor aligns, including classrooms, stairways, and structural components.


84. Request for Information (RFI)

Definition: An RFI is a formal request made by a contractor to the client or designer for clarification or additional information about the project. Example: A contractor may submit an RFI asking for clarification on the type of flooring to be used in a mall project.


85. Deviation

Definition: A deviation occurs when a project task or element is carried out differently from what was specified in the original plan or contract. Example: Using a different grade of steel in a building project without prior approval would be considered a deviation.


86. Project Life Cycle

Definition: The project life cycle refers to the phases a project goes through from initiation to completion. Example: The life cycle of a dam construction project might include phases like planning, design, construction, and post-construction activities.


87. Contract

Definition: A contract is a legally binding agreement between two or more parties outlining the terms of the work to be completed. Example: A construction contract between a developer and a contractor for building an apartment complex would specify scope, cost, and timeline.


88. Schedule Variance (SV)

Definition: Schedule variance is the difference between the planned progress and actual progress of a project. Example: If the construction of a bridge is supposed to be 50% complete but is only 40% complete, the project has a schedule variance.


89. Cost Variance (CV)

Definition: Cost variance is the difference between the budgeted cost and the actual cost of the work completed. Example: If the actual cost of a road construction project exceeds the budget by $100,000, that represents a cost variance.


90. Demobilization

Definition: Demobilization refers to the process of removing personnel, equipment, and materials from a construction site after the project is complete. Example: Once the school building is finished, the contractor demobilizes by clearing the site and removing all construction equipment.


91. Certificate of Completion

Definition: A certificate of completion is an official document issued when the project has been completed as per the contract. Example: After a commercial building project is finished, the contractor receives a certificate of completion, allowing the client to take possession.


92. Retrofitting

Definition: Retrofitting involves making updates or improvements to an existing building or structure to meet current standards or improve functionality. Example: Retrofitting an old office building to make it earthquake-resistant.


93. Quality Control Plan

Definition: A quality control plan outlines the processes and standards that will be followed to ensure the project meets quality requirements. Example: A contractor might create a quality control plan for a hospital project, detailing how materials will be inspected before installation.


94. Construction Claim

Definition: A construction claim is a formal request for compensation due to delays, additional work, or unforeseen issues during the project. Example: A contractor might file a claim for extra costs incurred due to weather delays in a highway construction project.


95. Work Stoppage

Definition: Work stoppage occurs when work on a construction site is halted due to various reasons such as safety concerns, lack of materials, or legal issues. Example: A work stoppage might occur on a residential construction project if there is a dispute over land ownership.


96. Key Performance Indicator (KPI)

Definition: KPIs are measurable values that demonstrate how effectively a project is achieving its key objectives. Example: KPIs for a high-rise building project might include tracking labor productivity, schedule adherence, and cost savings.


97. Cost Overrun

Definition: A cost overrun occurs when the actual cost of the project exceeds the planned budget. Example: If a residential complex was budgeted at $10 million but ends up costing $12 million, it faces a cost overrun.


98. Owner’s Risk

Definition: Owner’s risk refers to risks that are the responsibility of the project owner, such as changes in design or scope. Example: If the client requests additional features during the construction of a shopping mall, any additional costs or delays may fall under owner’s risk.


99. Contingency Budget

Definition: A contingency budget is a reserved fund to cover unexpected costs or changes in the project. Example: A contractor might set aside 10% of the project budget as a contingency for unforeseen issues, such as material price increases.


100. Joint Venture

Definition: A joint venture is a business arrangement where two or more companies collaborate on a single project, sharing resources, risks, and rewards. Example: Two construction firms might enter a joint venture to build a large-scale infrastructure project like an airport.



101. Force Majeure

Definition: Force majeure refers to unexpected events beyond anyone's control that prevent the project from being completed on time, such as natural disasters, war, or strikes. Example: A construction project might be delayed due to a hurricane, which is considered a force majeure event.


102. Commissioning Plan

Definition: A commissioning plan is a document outlining the process of testing and verifying the functionality of building systems before final handover. Example: Before handing over a hospital, the HVAC, plumbing, and electrical systems must be tested according to the commissioning plan.


103. Project Milestone

Definition: A project milestone is a key achievement or point in the project timeline that signifies the completion of a major phase or deliverable. Example: Completing the foundation of a skyscraper is an important project milestone.


104. Lean Construction

Definition: Lean construction is a methodology focused on minimizing waste and maximizing value in the construction process. Example: Using just-in-time delivery of materials in a high-rise building project to avoid storing excess supplies on-site and reducing waste.


105. Building Code

Definition: A building code is a set of regulations governing the design, construction, and maintenance of buildings to ensure safety and quality. Example: In an apartment construction project, the design must adhere to local building codes regarding fire exits and structural safety.


106. Resource Leveling

Definition: Resource leveling is a technique used to optimize the allocation of resources over the duration of a project, balancing labor and equipment needs. Example: In a bridge construction project, resource leveling might involve delaying certain activities until enough labor and machinery are available.


107. Dispute Resolution

Definition: Dispute resolution refers to the methods used to resolve conflicts or disagreements between parties involved in a project, such as arbitration or mediation. Example: If a contractor and client disagree over the quality of work on a shopping complex, they may use arbitration to resolve the dispute.


108. Acceleration

Definition: Acceleration refers to actions taken to speed up the progress of a project, usually to meet tight deadlines or compensate for delays. Example: Working additional shifts or increasing labor on-site to finish a hotel project in time for a grand opening.


109. Change Management

Definition: Change management is the process of managing any modifications to the project's scope, budget, or timeline to ensure smooth implementation. Example: In a residential project, change management might involve tracking changes requested by the client, such as adding more bedrooms or upgrading finishes.


110. Environmental Impact Assessment (EIA)

Definition: An EIA is a formal evaluation of the potential environmental effects of a construction project before it begins. Example: Conducting an EIA for a dam construction project to assess its impact on local wildlife and water resources.


111. Substantial Completion

Definition: Substantial completion refers to the point at which the project is sufficiently complete and can be used for its intended purpose, even if minor work remains. Example: A hotel might be deemed substantially complete when guests can start checking in, even though landscaping work is still ongoing.


112. Liquidated Damages Clause

Definition: A liquidated damages clause is a contract term that imposes a financial penalty on the contractor for delays in project completion. Example: In a road construction project, if the contractor fails to finish on time, they might owe the client $1,000 for every day of delay.


113. Workfront

Definition: A workfront is the specific area of the construction site where work is actively being performed. Example: In the construction of a housing complex, one workfront could be the basement excavation while another is installing steel reinforcement.


114. Line of Balance (LOB)

Definition: The Line of Balance is a scheduling technique used to manage repetitive tasks in projects with multiple similar units, such as housing developments. Example: In a residential project, the LOB might help coordinate activities like bricklaying and plastering across multiple buildings.


115. Rebar

Definition: Rebar, short for reinforcing bar, is steel reinforcement used in concrete structures to increase their strength and durability. Example: Rebar is placed within the concrete foundation of a skyscraper to provide additional tensile strength.


116. Takeoff Sheet

Definition: A takeoff sheet lists the quantities of materials needed for a project, based on the drawings and specifications. Example: A contractor uses a takeoff sheet to calculate how many bricks are needed for a commercial building.


117. Builder’s Risk Insurance

Definition: Builder’s risk insurance is a type of insurance that protects a construction project from damage during construction, such as fire, theft, or vandalism. Example: A contractor may take out builder’s risk insurance to cover potential losses while constructing a shopping mall.


118. Material Handling

Definition: Material handling refers to the movement, protection, storage, and control of materials throughout the construction site. Example: On a high-rise construction site, material handling might include the use of cranes to move steel beams to the upper floors.


119. Warranties

Definition: Warranties are guarantees provided by contractors or manufacturers that the work or materials will meet certain quality standards. Example: A contractor provides a warranty for the roofing materials used in a school building, ensuring they are leak-proof for 10 years.


120. Back Charge

Definition: A back charge is a deduction from the contractor’s payment to cover the costs of work that was completed incorrectly or missed. Example: If the electrical work in a residential building project was not up to code, the client might issue a back charge for the costs of fixing it.


121. Latent Defect

Definition: A latent defect is a hidden flaw in construction work that may not be visible until after the project is completed. Example: A crack in the foundation of a commercial building that appears months after completion is considered a latent defect.


122. Escalation Clause

Definition: An escalation clause allows for adjustments in the contract price if there are significant changes in the cost of materials or labor. Example: If the cost of steel increases during the construction of a bridge, the escalation clause would adjust the contract price accordingly.


123. Depreciation

Definition: Depreciation refers to the gradual reduction in the value of an asset over time due to wear and tear. Example: Heavy machinery used on a construction site, like cranes or bulldozers, depreciates in value over time.


124. Allowances

Definition: Allowances are budgeted amounts set aside for items that are not fully specified at the time of the contract. Example: In a home construction project, an allowance might be included for kitchen fixtures, giving the client flexibility in choosing the materials.


125. Payment Application

Definition: A payment application is a formal request submitted by the contractor to the client for payment for work completed. Example: A contractor submits a payment application after completing 50% of the work on a residential project.


126. Scope Statement

Definition: A scope statement is a document that defines the project's goals, deliverables, tasks, and the work required to complete it. Example: The scope statement for a hospital project might include building the structure, installing medical equipment, and completing the landscaping.


127. S-Curve

Definition: An S-curve is a graphical representation of the cumulative progress of a project over time, showing how work accelerates and then levels off. Example: In a high-rise building project, the S-curve shows slow progress during the foundation stage, faster progress during the framing, and a slowdown again during the finishing phase.


128. Contractor’s All-Risk Insurance (CAR)

Definition: CAR insurance is a comprehensive policy that covers physical loss or damage to the works, materials, and plant on a construction site. Example: A contractor building a factory takes out CAR insurance to protect against damage from theft, fire, or accidents.


129. Stakeholder Analysis

Definition: Stakeholder analysis identifies and assesses the influence and expectations of key stakeholders involved in a construction project. Example: In a bridge construction project, a stakeholder analysis might involve understanding the concerns of the local community, government officials, and environmental groups.


130. Contractor Prequalification

Definition: Contractor prequalification is the process of evaluating a contractor's experience, financial stability, and capabilities before they are allowed to bid on a project. Example: A developer prequalifies several contractors before accepting bids for a commercial building project, ensuring that only experienced firms participate.


131. Job Hazard Analysis (JHA)

Definition: JHA is a process that identifies potential safety hazards for each task in a construction project to minimize the risk of accidents. Example: Before beginning excavation work, a JHA might identify the risk of underground cables being hit and ensure safety measures are in place.


132. Retention Release

Definition: Retention release refers to the payment of the portion of the contract price that was withheld (retained) until the project is completed satisfactorily. Example: Once all punch list items are completed in a commercial office project, the retention money is released to the contractor.


133. Surety Bond

Definition: A surety bond is a contract between a contractor, a client, and a bonding company to ensure the contractor completes the project as per the terms. Example: A surety bond might be required for a government building project to guarantee that the contractor fulfills their obligations.


134. Direct Labor

Definition: Direct labor refers to the workers directly involved in the construction of a project, such as carpenters, masons, and electricians. Example: The wages of workers laying bricks in the construction of a school building are considered direct labor costs.


135. Indirect Labor

Definition: Indirect labor refers to workers who are not directly involved in construction but support the project, such as supervisors, cleaners, and security guards. Example: The wages of security guards at a construction site for a shopping mall are considered indirect labor costs.


136. Unit Price Contract

Definition: A unit price contract bases the contractor’s payment on the quantity of work completed, multiplied by a set unit price for each component. Example: In a road construction project, the contractor might be paid $100 per cubic meter of asphalt laid.


137. Guaranteed Maximum Price (GMP)

Definition: A GMP contract sets a maximum price that the client will pay, with the contractor covering any costs above this price unless changes are made to the scope. Example: In a stadium project, the contractor agrees to complete the work for no more than $50 million, with any cost overruns being absorbed by the contractor.


138. Certificate of Occupancy (CO)

Definition: A CO is a legal document issued by the local government certifying that a building complies with building codes and is safe for occupancy. Example: Before tenants can move into a new office building, the contractor must obtain a certificate of occupancy from the city.


139. Cost Estimate

Definition: A cost estimate is an approximation of the total expenses required to complete a construction project, based on the design and scope. Example: A contractor provides a cost estimate of $5 million for building a luxury apartment complex, including labor, materials, and equipment.


140. Value Analysis

Definition: Value analysis is the process of reviewing the project’s components to ensure that they provide the best possible value without sacrificing quality. Example: Replacing expensive imported marble with a high-quality local alternative during a hotel project to reduce costs without compromising aesthetics.


141. Functional Requirements

Definition: Functional requirements define what the construction project must accomplish, focusing on the client’s needs and goals. Example: For a hospital construction project, the functional requirements might include ensuring that all operating rooms have proper ventilation and electrical systems.


142. Prequalification

Definition: Prequalification is the process of screening potential contractors, suppliers, or subcontractors before allowing them to bid on a project. Example: A real estate developer prequalifies contractors for an upcoming condominium project by assessing their experience and financial stability.


143. Performance Specification

Definition: Performance specifications define the results and standards the finished project must meet, without specifying the methods or materials to be used. Example: In a power plant construction project, the performance specification might require that the cooling system maintains a certain temperature, but it leaves the choice of system to the contractor.


144. Invitation to Bid (ITB)

Definition: An ITB is a formal invitation sent to contractors or suppliers, requesting bids for a project or a specific portion of the work. Example: A municipality issues an ITB for the construction of a public park, outlining the scope of work and deadlines for submitting bids.


145. Cost Benefit Ratio (CBR)

Definition: The cost-benefit ratio is a measure that compares the benefits of a project to its costs, helping to evaluate its financial viability. Example: If a highway project has a cost-benefit ratio of 1.5, it means that for every dollar spent, the project is expected to return $1.50 in economic benefits.


146. Warranty Period

Definition: The warranty period is the time frame after project completion during which the contractor is responsible for correcting any defects. Example: A contractor might offer a 2-year warranty period on the structural integrity of a commercial building.


147. Final Account

Definition: The final account is a statement that details the actual costs incurred during a project, compared to the original budget. Example: After completing a hotel, the contractor submits the final account to the client, showing the actual costs for materials, labor, and other expenses.


148. Mobilization Payment

Definition: A mobilization payment is an upfront payment made to the contractor to cover the initial costs of setting up the construction site and getting the project started. Example: The contractor receives a mobilization payment to set up temporary facilities and bring equipment to the site for a bridge construction project.


149. Program Evaluation and Review Technique (PERT)

Definition: PERT is a project management tool used to estimate the time required to complete tasks and identify the critical path. Example: Using PERT in a residential project helps identify that building the foundation, framing, and roofing are critical tasks that determine the overall timeline.


150. Cash Flow Projection

Definition: A cash flow projection is an estimate of the inflows and outflows of money during the course of the construction project, helping to ensure financial stability. Example: A contractor creates a cash flow projection to predict when payments from the client will be received and when expenses for labor and materials will need to be paid.



151. Rough Order of Magnitude (ROM) Estimate

Definition: An ROM estimate is a preliminary estimate that gives a rough idea of the project's cost, typically with an accuracy range of -25% to +75%. Example: A contractor provides an ROM estimate of $1 million for building a school, understanding that this figure could change significantly as details are finalized.


152. Schedule Compression

Definition: Schedule compression refers to shortening the project timeline without reducing the project scope, often through fast-tracking or crashing. Example: If a mall project needs to be completed two months earlier, the contractor might compress the schedule by adding more shifts or overlapping tasks.


153. Scope Management

Definition: Scope management involves defining and controlling what is included in the project and ensuring that only necessary changes are made to the scope. Example: In a housing project, scope management ensures that changes like adding extra rooms or upgrading finishes are carefully reviewed and approved.


154. Project Handover

Definition: Project handover refers to the formal transfer of responsibility for the completed project from the contractor to the client. Example: After finishing a highway construction project, the contractor officially hands over the project to the government authority for public use.


155. Bonding Capacity

Definition: Bonding capacity is the maximum amount of work a contractor is qualified to undertake, as determined by a bonding company. Example: A contractor may have a bonding capacity of $5 million, meaning they can bid on projects up to that value.


156. As-Built Survey

Definition: An as-built survey documents the actual locations and dimensions of structures after construction, often comparing them to the original design. Example: After a residential building is completed, an as-built survey is conducted to ensure all walls, plumbing, and electrical systems match the final plans.


157. Risk Assessment

Definition: Risk assessment is the process of identifying potential risks in the project and analyzing their potential impact on cost, schedule, and quality. Example: In a dam construction project, a risk assessment might identify flooding during the rainy season as a potential risk that could delay progress.


158. Risk Mitigation

Definition: Risk mitigation involves taking steps to reduce the likelihood or impact of risks identified in a project. Example: To mitigate the risk of materials being delayed due to bad weather, a contractor might order supplies ahead of time for a bridge project.


159. Earned Value Analysis

Definition: Earned value analysis is a method for measuring project performance by comparing the budgeted cost of work performed to the actual cost. Example: If a commercial building is halfway done but has used only 40% of the budget, the earned value analysis would indicate the project is financially ahead of schedule.


160. Certificate of Practical Completion

Definition: A certificate of practical completion is issued when a project is sufficiently complete for the client to use it, although minor work may still be required. Example: A certificate of practical completion is issued for a shopping mall when tenants can start moving in, even though some painting and landscaping remain.


161. Precast Concrete

Definition: Precast concrete refers to concrete elements that are cast in a controlled environment and then transported to the construction site for installation. Example: Precast concrete panels are commonly used in high-rise buildings to speed up the construction process and ensure consistency.


162. Design-Build Contract

Definition: In a design-build contract, the contractor is responsible for both designing and constructing the project, offering a single point of responsibility. Example: A contractor hired to design and construct a hospital under a design-build contract manages both the architectural design and construction.


163. Specifications (Specs)

Definition: Specifications are detailed documents that outline the materials, standards, and procedures required for the project. Example: In building a library, the specifications might detail the type of brick, mortar, and finishing to be used, ensuring the building meets design standards.


164. Subcontractor Agreement

Definition: A subcontractor agreement is a contract between the general contractor and subcontractor, detailing the scope of work, payment terms, and timelines. Example: In a hotel construction project, the general contractor might have a subcontractor agreement with an electrician to install all electrical wiring and systems.


165. General Conditions

Definition: General conditions refer to the indirect costs required to complete a project, such as site utilities, supervision, and temporary facilities. Example: The general conditions for a residential project might include the cost of site offices, water supply, and construction management fees.


166. Finishing Work

Definition: Finishing work refers to the final touches on a construction project, including painting, flooring, and installation of fixtures. Example: In a commercial building project, finishing work might include installing lighting fixtures, carpeting, and painting the walls.


167. Escalation

Definition: Escalation refers to increases in the costs of materials, labor, or equipment over the course of a project. Example: The cost of steel might escalate during a bridge project, causing the overall project cost to increase beyond the original budget.


168. Retrospective Delay Analysis

Definition: Retrospective delay analysis is the process of examining past events to determine the causes of delays in a project. Example: If a road project was delayed by 6 months, a retrospective delay analysis might show that poor weather and material shortages were key factors.


169. Progress Billing

Definition: Progress billing is a method where the contractor invoices the client for completed work at regular intervals, based on the percentage of work completed. Example: In constructing a skyscraper, the contractor may submit progress bills monthly, reflecting the completed floors or stages.


170. Lien Waiver

Definition: A lien waiver is a legal document that waives the contractor's right to file a lien against the property in exchange for payment. Example: After receiving payment for installing windows in a residential building, the contractor signs a lien waiver, confirming they have been paid.


171. Schedule of Works

Definition: A schedule of works is a detailed list of tasks that need to be completed, often used in renovation or repair projects. Example: In a home renovation project, the schedule of works might include tasks like replacing the roof, upgrading the kitchen, and repainting walls.


172. Front-Loading

Definition: Front-loading refers to the practice of allocating more resources or expenses early in the project to complete critical tasks faster. Example: In a hospital project, front-loading could involve bringing in extra labor and equipment early on to complete the foundation more quickly.


173. Turnkey Contract

Definition: A turnkey contract involves the contractor delivering a fully completed project, ready for the client to use immediately. Example: A developer may enter into a turnkey contract with a contractor to build an entire office complex, handing over the keys once it's ready for occupancy.


174. Baseline Schedule

Definition: A baseline schedule is the original, approved timeline for completing the project, used as a reference point for tracking progress. Example: In constructing a residential tower, the baseline schedule might show that the first 10 floors should be completed within 3 months.


175. Occupational Safety and Health Administration (OSHA)

Definition: OSHA is a government agency that sets and enforces safety standards to protect workers on construction sites. Example: On a high-rise construction project, OSHA regulations require workers to wear fall protection gear while working at heights.


176. Cash Flow Statement

Definition: A cash flow statement outlines the flow of money in and out of the project, helping to manage expenses and ensure financial stability. Example: A contractor prepares a cash flow statement for a stadium project to ensure that payments for labor and materials are made on time.


177. Crashing

Definition: Crashing is a schedule compression technique that involves adding more resources to critical tasks to speed up project completion. Example: A construction manager may use crashing on a road project by bringing in additional workers and equipment to finish the paving faster.


178. BOQ (Bill of Quantities)

Definition: The Bill of Quantities is a detailed document listing all materials, labor, and tasks required to complete a construction project. Example: The BOQ for a hotel project includes the quantities of bricks, cement, steel, and labor needed to construct the building.


179. Modular Construction

Definition: Modular construction involves building sections or modules of a project off-site and then assembling them on-site. Example: A modular construction method is used to build a school by creating classroom units off-site and assembling them on-site within weeks.


180. Clash Detection

Definition: Clash detection is the process of identifying and resolving conflicts in design plans, such as overlapping pipes or electrical conduits. Example: In a hospital project, clash detection software helps identify where electrical lines intersect with water pipes, resolving the issue before construction.


181. Feasibility Report

Definition: A feasibility report assesses whether a proposed construction project is practical and viable in terms of cost, schedule, and technical requirements. Example: Before starting a dam construction project, a feasibility report evaluates whether the site is suitable and the costs are justified.


182. Completion Bond

Definition: A completion bond is a type of financial guarantee that ensures a project will be completed according to the contract, even if the contractor defaults. Example: A contractor working on a major highway project may be required to provide a completion bond to reassure the client that the work will be finished on time.


183. Liquidated Damages

Definition: Liquidated damages are financial penalties imposed on the contractor for failing to complete the project on time or to the required standard. Example: A contractor may be required to pay $10,000 per day for delays in completing a bridge project.


184. Horizontal Construction

Definition: Horizontal construction refers to infrastructure projects such as roads, bridges, and pipelines, rather than vertical buildings. Example: A civil engineering firm specializing in horizontal construction may be responsible for building highways and water treatment plants.


185. Vertical Construction

Definition: Vertical construction refers to building structures that rise above the ground, such as residential towers, office buildings, and hospitals. Example: A developer specializing in vertical construction may be involved in the construction of a new 30-story apartment building.


186. Lien

Definition: A lien is a legal claim placed on a property by a contractor or supplier to ensure payment for services rendered. Example: If a contractor is not paid for their work on a commercial building, they may file a lien to claim payment from the property owner.


187. Construction Closeout

Definition: Construction closeout is the final phase of a project, involving inspections, final payments, and the handover of project documentation. Example: The construction closeout for a shopping mall includes delivering as-built drawings, settling final payments, and completing all punch list items.


188. Green Building Certification

Definition: Green building certification is a formal recognition that a building meets environmental and sustainability standards, such as LEED or BREEAM. Example: A new office tower receives LEED Gold certification for its energy-efficient design and use of sustainable materials.


189. Performance Bond

Definition: A performance bond is a type of insurance that guarantees the contractor will complete the project according to the contract terms. Example: A contractor building a stadium may be required to provide a performance bond to reassure the client that the work will meet quality and timeline expectations.


190. Bid Bond

Definition: A bid bond is a financial guarantee that the contractor will enter into the contract if selected and will provide the required performance bond. Example: A contractor bidding on a government office project submits a bid bond to ensure they will follow through with the contract if awarded the job.


191. Constructability Review

Definition: A constructability review is an evaluation of the project design to ensure it can be built efficiently and cost-effectively. Example: Before starting a high-rise project, the construction team conducts a constructability review to identify any potential challenges in the design.


192. Interim Payment Certificate

Definition: An interim payment certificate is a document issued during the project that authorizes partial payment for work completed up to that point. Example: The contractor on a highway project receives an interim payment certificate after completing 50% of the road paving.


193. Surety

Definition: A surety is a financial entity that provides bonds guaranteeing that the contractor will fulfill their contractual obligations. Example: A surety provides a performance bond to guarantee that a contractor will complete the construction of a public park.


194. Bar Chart

Definition: A bar chart is a type of visual schedule used to track the progress of project tasks over time, also known as a Gantt chart. Example: A bar chart for a hotel construction project shows the timeline for each phase, such as foundation, framing, and finishing.


195. Project Contingency

Definition: A project contingency is a reserved amount of the budget set aside to cover unforeseen costs or changes in scope. Example: A contractor working on a residential complex sets aside 10% of the project budget as a contingency for unexpected costs, like weather delays.


196. Construction Phasing

Definition: Construction phasing involves dividing a project into distinct phases, such as site preparation, foundation, and structural work, to ensure smooth progress. Example: A multi-story building project is divided into phases, with each phase focusing on different elements of construction, like the foundation and walls.


197. Site Survey

Definition: A site survey is a detailed examination and measurement of the construction site to determine boundaries, topography, and utility locations. Example: Before constructing a bridge, the engineering team conducts a site survey to map out the riverbanks and ensure the bridge aligns with existing roads.


198. Infrastructure Development

Definition: Infrastructure development refers to the construction of essential public services, such as roads, bridges, water systems, and power supplies. Example: A city invests in infrastructure development by building a new water treatment plant to meet the growing population's needs.


199. Commissioning Report

Definition: A commissioning report documents the tests, inspections, and verifications performed to ensure that all building systems meet the required specifications. Example: After constructing an office tower, the commissioning report details that the HVAC, electrical, and fire protection systems were tested and are functioning correctly.


200. Overhead Costs

Definition: Overhead costs refer to indirect expenses that are not directly tied to the construction work but are necessary for the project's completion, such as office administration and equipment maintenance. Example: The contractor's office rent and project management salaries for a mall construction are considered overhead costs.



201. Long Lead Items

Definition: Long lead items are materials or equipment that require significant time to manufacture and deliver, so they must be ordered well in advance. Example: In a power plant project, large turbines are considered long lead items and must be ordered early to ensure they arrive on time for installation.


202. Building Envelope Commissioning

Definition: Building envelope commissioning is the process of testing and verifying the performance of the exterior shell of a building, including insulation, windows, and roofs, to ensure energy efficiency. Example: For a high-rise office building, the building envelope commissioning ensures that the windows and walls are airtight, reducing energy loss.


203. Direct Costs

Definition: Direct costs are expenses that can be directly attributed to a specific construction task, such as labor, materials, and equipment. Example: The cost of purchasing steel beams and hiring workers to install them in a bridge project are considered direct costs.


204. Indirect Costs

Definition: Indirect costs are expenses that are not directly tied to construction tasks but are necessary for overall project completion, like administration, supervision, or safety equipment. Example: The cost of renting an on-site office for project management in a large residential project is considered an indirect cost.


205. Progress Payment

Definition: Progress payment is a partial payment made to a contractor based on the amount of work completed at certain milestones during the project. Example: In the construction of a commercial building, the contractor may receive progress payments after completing the foundation, framing, and roofing phases.


206. Submittal Register

Definition: A submittal register is a document used to track all submittals (like shop drawings, product data, and samples) that need to be reviewed and approved by the design team. Example: In a hospital project, the contractor uses a submittal register to ensure that materials such as plumbing fixtures and electrical systems are approved before installation.


207. Wet Trade

Definition: Wet trades refer to construction activities that involve the use of materials mixed with water, such as concrete, plastering, or bricklaying. Example: In a residential construction project, tasks like pouring the concrete foundation and bricklaying are part of the wet trades.


208. Clerk of Works

Definition: A clerk of works is a site-based professional responsible for ensuring that the construction work meets the specifications and quality standards. Example: In the construction of a public library, the clerk of works inspects materials and workmanship to ensure compliance with the project's design and regulations.


209. Scope Creep

Definition: Scope creep occurs when additional tasks or requirements are introduced to a project without formal approval, often leading to budget overruns and delays. Example: In a school construction project, the client may request extra classrooms or upgraded facilities mid-project, causing scope creep.


210. Quantity Surveyor

Definition: A quantity surveyor is a professional responsible for estimating and managing project costs to ensure the project stays within budget. Example: The quantity surveyor for a hospital project calculates the cost of materials, labor, and equipment to provide an accurate estimate of the project's total budget.


211. Pre-Tender Estimate

Definition: A pre-tender estimate is a detailed cost estimate prepared before the tendering process to determine the expected cost of the project. Example: Before bidding on a new highway project, the client prepares a pre-tender estimate to forecast the likely construction costs based on material and labor rates.


212. Occupational Health and Safety (OHS)

Definition: OHS refers to the standards and regulations designed to protect the health and safety of workers on construction sites. Example: In the construction of a skyscraper, OHS regulations mandate that workers wear hard hats, safety harnesses, and steel-toed boots to prevent accidents.


213. Construction Phase Plan (CPP)

Definition: A construction phase plan is a detailed document outlining how health and safety will be managed during the construction phase of the project. Example: For a large housing development, the construction phase plan includes safety measures, hazard identification, and emergency response procedures.


214. Variation Order

Definition: A variation order is a formal change to the contract that alters the scope of work, timeline, or cost of the project. Example: In a hotel project, a variation order might be issued to upgrade all the rooms from standard finishes to luxury materials, adjusting the cost and timeline.


215. Material On Site (MOS)

Definition: Material on site refers to construction materials that have been delivered to the project location but have not yet been used in the building process. Example: In a warehouse construction project, stacks of steel beams delivered to the site but not yet installed would be considered MOS.


216. Performance Specifications

Definition: Performance specifications outline the functional requirements a project or system must meet, without specifying how to achieve them. Example: A performance specification for an HVAC system in an office building might require that it maintain indoor temperatures of 22°C without dictating the brand or type of system to be used.


217. Value Management

Definition: Value management is a systematic approach to improving the value of a project by optimizing costs and resources without compromising quality. Example: In a hospital construction project, value management might involve replacing expensive imported tiles with local alternatives that meet the same quality standards at a lower cost.


218. Defects Liability Period

Definition: The defects liability period is the time after project completion during which the contractor is responsible for fixing any defects that arise. Example: In a shopping mall project, the contractor must repair any leaks or cracks discovered within the defects liability period, typically lasting 12 months after handover.


219. Hold Point

Definition: A hold point is a mandatory checkpoint in the construction process where work must stop until specific inspections or approvals are obtained. Example: In a bridge construction project, a hold point might occur before pouring concrete, requiring inspection of the reinforcement by an engineer.


220. Backlog

Definition: A backlog refers to the amount of work or projects that a construction company has under contract but has not yet started or completed. Example: A construction firm may have a backlog of three high-rise building projects that need to be completed over the next two years.


221. Activity-on-Node (AON)

Definition: AON is a project scheduling technique where activities are represented by nodes, and the dependencies between them are shown by arrows. Example: In the construction of a stadium, the AON diagram might show that installing seats can only happen after the roofing is completed.


222. Provisional Sum

Definition: A provisional sum is an estimated amount included in the contract for work that is uncertain or cannot be fully defined at the outset. Example: In a road project, a provisional sum may be allocated for potential soil stabilization work, which will be confirmed after further site investigation.


223. Progress Report

Definition: A progress report is a document detailing the current status of the project, including completed work, upcoming tasks, and any delays or issues. Example: In the construction of a residential complex, the contractor submits weekly progress reports to the client, outlining tasks completed and any challenges encountered.


224. Rebar Detailing

Definition: Rebar detailing refers to the design and placement of steel reinforcement bars (rebar) in concrete structures, ensuring proper strength and support. Example: In a parking garage construction project, rebar detailing ensures that the reinforcement bars are correctly positioned within the concrete slabs to support vehicle loads.


225. Snagging List

Definition: A snagging list is a document that identifies minor defects or unfinished work that must be completed before the project can be considered finished. Example: In a hotel construction project, the snagging list might include tasks like fixing chipped paint or aligning misfitted doors.


226. Prime Cost (PC)

Definition: Prime cost refers to the direct costs of materials and labor required to complete a project, excluding indirect costs like overhead. Example: The prime cost of building a house includes the cost of cement, bricks, and the wages of the workers who construct it.


227. Takeoff

Definition: A takeoff is the process of measuring and quantifying materials needed for a construction project, based on drawings and specifications. Example: Before starting a shopping mall project, the contractor performs a takeoff to calculate the amount of concrete, steel, and tiles required.


228. Client Brief

Definition: A client brief is a document provided by the client that outlines the objectives, requirements, and constraints of the project. Example: For a new school construction, the client brief might specify the number of classrooms, laboratories, and playground facilities required.


229. Leveling

Definition: Leveling refers to ensuring that a surface, such as a floor or foundation, is flat and even, often done using specialized equipment like lasers. Example: In a warehouse construction project, the contractor levels the concrete floor to ensure it is perfectly flat for machinery and storage.


230. Construction Management at Risk (CMAR)

Definition: CMAR is a project delivery method where the construction manager acts as a consultant during the design phase and as the general contractor during construction, taking on the risk for completing the project within a guaranteed maximum price. Example: In a hospital construction project, the CMAR method allows the construction manager to collaborate with the designers to control costs and ensure the project stays on budget.


231. Design and Build (D&B)

Definition: Design and build is a project delivery method where one entity is responsible for both the design and construction of the project. Example: In a new office building project, a contractor is hired to design the building and construct it, streamlining communication and ensuring quicker project delivery.


232. FIDIC Contracts

Definition: FIDIC contracts are a set of standardized international construction contracts commonly used in large infrastructure and engineering projects. Example: A contractor working on a highway in the Middle East might use a FIDIC contract to manage the legal and financial terms of the project.


233. Lean Construction

Definition: Lean construction is a methodology focused on minimizing waste and maximizing efficiency in the construction process. Example: In a high-rise residential project, lean construction practices might involve reducing material waste by using just-in-time delivery of resources.


234. No Objection Certificate (NOC)

Definition: An NOC is a legal document issued by authorities indicating that they have no objection to the project proceeding. Example: A contractor may need to obtain an NOC from the local fire department before starting the construction of a commercial building.


235. Method Statement

Definition: A method statement is a document outlining how specific tasks or processes will be carried out during the construction project, including safety and quality measures. Example: In a bridge construction project, the method statement for pouring concrete might include step-by-step instructions, safety protocols, and quality checks.


236. Mediation

Definition: Mediation is a form of alternative dispute resolution where a neutral third party helps resolve conflicts between the parties involved in a construction project. Example: If a dispute arises between the contractor and client over delays in a shopping mall project, they might use mediation to reach an agreement without going to court.


237. Curing

Definition: Curing is the process of maintaining moisture, temperature, and time conditions for concrete to harden and gain strength after it has been poured. Example: In a residential construction project, the contractor covers freshly poured concrete with wet burlap and plastic sheets to cure it properly.


238. Health and Safety Plan

Definition: A health and safety plan outlines the procedures, responsibilities, and protocols for ensuring worker safety on a construction site. Example: In a factory construction project, the health and safety plan includes guidelines for wearing protective gear, conducting site inspections, and managing emergencies.


239. Cost Engineering

Definition: Cost engineering involves the application of engineering principles to control and manage project costs, ensuring that the project stays within budget. Example: A cost engineer in a highway construction project analyzes labor, materials, and equipment expenses to ensure cost efficiency and avoid overruns.


240. Notice to Proceed (NTP)

Definition: An NTP is a formal document issued by the client authorizing the contractor to begin work on the project. Example: After signing the contract, the contractor receives a Notice to Proceed from the client, allowing them to mobilize workers and start construction on a new hospital.



241. Contingency Fund

Definition: A contingency fund is an amount of money set aside to cover unforeseen costs or emergencies during the construction project. Example: In a commercial building project, the contingency fund may be used if the price of materials rises unexpectedly or if additional excavation is needed.


242. Top-Out

Definition: Topping-out is a construction milestone where the structure of a building reaches its maximum height, often celebrated with a small ceremony. Example: When the last beam is placed on a 30-story office tower, the team celebrates the top-out as a major project milestone.


243. Partnering Agreement

Definition: A partnering agreement is a collaborative arrangement between the client, contractor, and other stakeholders, aimed at promoting teamwork and shared objectives. Example: In a large infrastructure project, the client and contractor sign a partnering agreement to ensure that all parties work together to meet deadlines and budgets.


244. Cost Plus Contract

Definition: A cost-plus contract reimburses the contractor for actual costs incurred during construction, plus an additional fee or percentage for profit. Example: In a custom home project, the contractor is paid for all expenses, such as materials and labor, plus a 15% fee for overhead and profit.


245. Bill of Materials (BOM)

Definition: A Bill of Materials is a comprehensive list of all the materials required for the construction project, including quantities and specifications. Example: The BOM for a bridge project might include quantities of steel, concrete, bolts, and other components needed to complete the structure.


246. Decentralized Construction

Definition: Decentralized construction refers to the practice of carrying out construction activities at various locations rather than at a centralized site. Example: In a large infrastructure project like road construction across multiple regions, work is carried out simultaneously at different locations.


247. Variance Report

Definition: A variance report tracks differences between the planned and actual performance of a project, often related to schedule or budget. Example: In a shopping mall construction project, a variance report might show that the electrical work is two weeks behind schedule, prompting corrective actions.


248. Stakeholder Management

Definition: Stakeholder management involves identifying project stakeholders and ensuring their needs and concerns are addressed throughout the project. Example: In a school construction project, stakeholder management includes keeping parents, teachers, and local authorities informed about the project's progress.


249. Closeout Documentation

Definition: Closeout documentation refers to all the records, certifications, and manuals provided at the completion of the project to ensure proper operation and maintenance. Example: For an office building project, the contractor provides closeout documentation, including warranties, as-built drawings, and equipment manuals, to the client.


250. Request for Proposal (RFP)

Definition: An RFP is a formal request issued by a client inviting contractors to submit proposals for a specific project or service. Example: A government agency issues an RFP for the construction of a new hospital, detailing the scope of work, timelines, and budget requirements.


251. Procurement Management

Definition: Procurement management involves acquiring goods and services necessary for the construction project, from selecting suppliers to managing contracts. Example: In a bridge construction project, procurement management includes sourcing steel beams from approved suppliers and negotiating favorable terms for delivery.


252. Batch Plant

Definition: A batch plant is a facility used to produce concrete or asphalt by mixing raw materials, which are then transported to the construction site. Example: For a highway project, the contractor sets up a batch plant near the site to ensure a steady supply of fresh concrete.


253. Construction Lien

Definition: A construction lien is a legal claim filed by a contractor or supplier to secure payment for work performed on a property. Example: A subcontractor who hasn’t been paid for roofing work on a commercial building files a construction lien to protect their right to payment.


254. Certificate of Substantial Completion

Definition: A certificate of substantial completion indicates that the project is sufficiently complete for the client to occupy or use it, even if some minor work remains. Example: A certificate of substantial completion is issued for a university dormitory once the rooms are ready for students to move in, although landscaping work is still ongoing.


255. Safety Audit

Definition: A safety audit is a thorough examination of a construction site to ensure compliance with safety regulations and identify potential hazards. Example: On a large commercial site, the contractor conducts regular safety audits to verify that workers are using the correct protective gear and that equipment is properly maintained.


256. Interim Completion

Definition: Interim completion refers to the partial completion of a project where certain sections are finished and handed over to the client, while the remaining work continues. Example: In a hospital construction project, the emergency department may achieve interim completion and be handed over for use while other parts of the building are still under construction.


257. Job Costing

Definition: Job costing involves tracking all costs associated with a specific task or phase of a construction project to monitor expenses and profitability. Example: In a residential development, job costing is used to calculate the total cost of laying the foundation, including labor, materials, and equipment.


258. Critical Chain Project Management (CCPM)

Definition: CCPM is a method of project scheduling that focuses on managing resources and ensuring that critical tasks are completed on time by reducing multitasking and interruptions. Example: In a skyscraper project, CCPM helps prioritize resource allocation to critical tasks, such as steel reinforcement installation, to prevent delays.


259. Design-Bid-Build (DBB)

Definition: DBB is a traditional project delivery method where the design and construction phases are contracted separately, with the client first hiring a designer and then selecting a builder through a competitive bidding process. Example: In a public school construction project, the client hires an architect to design the building, and once the design is complete, contractors submit bids to build it.


260. Project Program

Definition: A project program is a detailed plan outlining the objectives, timeline, and steps required to complete the construction project. Example: In a housing development project, the program details all phases, from site preparation to final inspection and handover.


261. Retention Money

Definition: Retention money is a portion of the payment withheld by the client until the contractor completes all the work and addresses any defects. Example: In a hotel project, the client holds back 5% of the total contract value as retention money, which will only be paid after the defects liability period ends.


262. Quality Plan

Definition: A quality plan outlines the standards, procedures, and inspections required to ensure the project meets quality expectations. Example: In a hospital project, the quality plan includes regular checks of concrete strength, plumbing installation, and electrical wiring to ensure they meet design specifications.


263. Notice of Delay

Definition: A notice of delay is a formal communication from the contractor to the client, informing them that the project is delayed due to unforeseen circumstances. Example: In a road construction project, the contractor issues a notice of delay due to unexpected weather conditions that halted work for several days.


264. Fast-Track Construction

Definition: Fast-track construction is a project delivery strategy where design and construction phases overlap to accelerate the project timeline. Example: In a high-rise construction project, the contractor begins foundation work before the final designs for the upper floors are complete, using fast-track construction to meet tight deadlines.


265. Retention Bond

Definition: A retention bond is a financial instrument that allows the client to release retention money to the contractor in exchange for a guarantee from a bonding company. Example: Instead of withholding retention money, the contractor provides a retention bond on a commercial project, ensuring the client is protected if defects arise after completion.


266. Shop Drawing Review

Definition: Shop drawing review is the process of reviewing detailed drawings submitted by subcontractors or fabricators to ensure they align with the design intent. Example: In a hotel construction project, the structural engineer reviews shop drawings for steel beams to ensure they match the specifications in the approved design.


267. Permitting

Definition: Permitting refers to the process of obtaining legal permissions from local authorities before construction can begin, ensuring compliance with zoning laws and regulations. Example: Before starting construction on a new shopping mall, the contractor must obtain permits for building, electrical, and plumbing work from the city government.


268. Latent Conditions

Definition: Latent conditions are hidden or unforeseen site conditions that were not identified during the planning stage, often leading to delays or additional costs. Example: In a bridge construction project, the contractor discovers hidden rock formations during excavation, leading to extra costs and changes to the foundation design.


269. Adjudication

Definition: Adjudication is a dispute resolution process where an independent third party reviews the case and makes a binding decision. Example: In a contractual dispute between a contractor and client over a delay in a high-rise construction project, both parties agree to adjudication to resolve the matter quickly.


270. Building Lifecycle

Definition: The building lifecycle refers to the entire process a building goes through, from design and construction to operation, maintenance, and eventual demolition. Example: A green building project incorporates lifecycle planning to ensure that energy efficiency and sustainability are maintained throughout the building's operational life.


271. Design for Manufacture and Assembly (DfMA)

Definition: DfMA is a construction approach that emphasizes designing buildings in a way that makes them easier to manufacture and assemble, reducing time and cost. Example: In a prefabricated building project, DfMA techniques are used to design components that can be easily manufactured off-site and assembled quickly on-site.


272. Latent Defects Insurance

Definition: Latent defects insurance provides coverage for hidden defects in a building's structure that may only become apparent years after construction is completed. Example: A developer may take out latent defects insurance for a new apartment complex to cover any structural issues that arise after the tenants have moved in.


273. Commissioning Agent

Definition: A commissioning agent is responsible for verifying that all building systems are installed and operating as intended, and that the project meets the owner's requirements. Example: In a data center project, the commissioning agent ensures that the HVAC, electrical, and backup power systems are fully operational and meet the client's performance standards.


274. Remediation

Definition: Remediation refers to the process of correcting or removing environmental hazards, such as soil contamination or asbestos, from a construction site. Example: Before building a residential development on a former industrial site, the contractor undertakes remediation to remove contaminated soil and ensure the land is safe for construction.


275. Mobilization Plan

Definition: A mobilization plan outlines the steps required to prepare the construction site and bring in necessary equipment, materials, and labor before work begins. Example: In a highway construction project, the mobilization plan details the setup of site offices, fencing, and the delivery of heavy machinery like bulldozers and excavators.


276. Critical Task

Definition: A critical task is any activity that must be completed on time to ensure the project stays on schedule; delays in critical tasks can delay the entire project. Example: In a high-rise construction project, the installation of structural steel is a critical task that must be completed before other activities like roofing and facade installation can proceed.


277. Risk Register

Definition: A risk register is a document that lists all identified risks in a project, along with their likelihood, impact, and mitigation strategies. Example: In the construction of a sports arena, the risk register includes potential risks such as delays due to weather, material shortages, and labor strikes, along with plans to manage them.


278. As-Built Documentation

Definition: As-built documentation consists of the final set of drawings and specifications that reflect all the changes made during construction, showing exactly how the project was completed. Example: After completing a new office building, the contractor submits as-built documentation showing the actual locations of plumbing, electrical, and structural components, which may differ slightly from the original plans.


279. Client Representative

Definition: The client representative is a person or team appointed by the client to oversee the project on their behalf, ensuring that it meets their requirements and expectations. Example: In a government-funded infrastructure project, the client appoints a representative to monitor construction progress, review costs, and ensure compliance with the contract.


280. Dayworks

Definition: Dayworks refer to additional tasks performed on a construction project that are not part of the original contract, typically paid for on a time and materials basis. Example: A contractor may be asked to perform dayworks to repair unexpected damage to a water pipe during a road construction project, with costs billed based on the hours worked and materials used.


281. Risk Appetite

Definition: Risk appetite refers to the level of risk a project owner or organization is willing to accept to achieve project objectives. Example: In a high-rise construction project, the owner’s risk appetite may be low, requiring the contractor to take extra precautions to avoid safety issues and delays.


282. Preliminary Cost Estimate

Definition: A preliminary cost estimate provides an early approximation of the overall project cost based on limited design information. Example: Before finalizing designs for a commercial complex, the contractor gives the client a preliminary cost estimate to help in budget planning.


283. Sequence of Operations

Definition: The sequence of operations outlines the order in which tasks will be performed during construction to ensure efficiency and avoid delays. Example: In a hotel construction project, the sequence of operations might dictate that foundation work is completed before the walls and roof are built.


284. Design Life

Definition: Design life refers to the number of years a structure is expected to perform its intended function without major repairs or replacements. Example: A bridge may be designed with a 50-year design life, meaning it should be structurally sound and functional for half a century under normal conditions.


285. Cost Performance Index (CPI)

Definition: The Cost Performance Index is a measure of cost efficiency in a project, calculated by dividing the budgeted cost of work performed by the actual cost. Example: In a residential tower project, a CPI greater than 1.0 indicates the project is under budget, while a CPI less than 1.0 shows cost overruns.


286. Project Dashboard

Definition: A project dashboard is a visual tool that presents key project performance metrics such as schedule, cost, and progress in a clear, concise format. Example: A contractor uses a project dashboard to provide weekly updates on the progress of a hospital construction project, showing whether it’s on track in terms of time and budget.


287. Work Package

Definition: A work package is a portion of a project that is defined in detail, including scope, time, and resources, allowing it to be managed and completed as a standalone unit. Example: In a housing development, the installation of plumbing systems for each building is treated as a separate work package, with its own timeline and budget.


288. Cost Breakdown Structure (CBS)

Definition: The Cost Breakdown Structure is a hierarchical representation of the costs associated with the components of a project, categorized by activities or tasks. Example: In a factory construction project, the CBS may include costs for foundation work, framing, roofing, and finishing, broken down into labor, materials, and equipment.


289. Resource Histogram

Definition: A resource histogram is a graphical representation of resource allocation over time, showing the number of workers or equipment needed during different phases of a project. Example: A resource histogram for a highway project might show that the peak demand for labor occurs during paving, with fewer workers required for landscaping.


290. Owner’s Liability

Definition: Owner’s liability refers to the legal responsibility of the project owner for any risks or issues that arise during construction. Example: In a shopping mall project, the owner may be held liable for delays caused by changes in the design that affect the contractor’s ability to complete the work on time.


291. Claim Management

Definition: Claim management involves identifying, documenting, and resolving claims for additional payment or time due to unforeseen changes or delays in a construction project. Example: A contractor files a claim for additional costs due to unexpected soil conditions encountered during the excavation phase of a road construction project.


292. As-Built Schedule

Definition: The as-built schedule documents the actual timeline followed during construction, noting any deviations from the original plan. Example: For a hospital project, the as-built schedule shows that electrical work was completed two weeks later than planned due to material shortages.


293. Design Freeze

Definition: A design freeze is a point in the project where no further changes to the design are allowed, ensuring that construction can proceed without delays. Example: In a residential project, the design is frozen once the foundation work begins to avoid any delays caused by late design modifications.


294. Quality Control Inspection

Definition: A quality control inspection involves checking materials, workmanship, and equipment to ensure they meet the project's quality standards. Example: In a commercial building project, the contractor conducts a quality control inspection of the concrete foundation to ensure it meets strength and durability specifications.


295. Tender Package

Definition: A tender package contains all the documents, drawings, and specifications required for contractors to submit bids for a project. Example: The tender package for a new airport construction project includes the design drawings, specifications for materials, and instructions for submitting bids.


296. Key Date

Definition: A key date is a critical deadline within the project schedule that signifies the completion of an important milestone or deliverable. Example: In a hotel construction project, a key date might be the completion of the foundation, which must be finished before the structure can begin.


297. Snagging

Definition: Snagging is the process of identifying and fixing minor defects or unfinished work before the project is officially handed over to the client. Example: In an office building, snagging might involve correcting small issues like adjusting door alignment or fixing minor paint defects.


298. Outturn Cost

Definition: Outturn cost refers to the final cost of a project, including any additional expenses or savings incurred during construction. Example: The outturn cost for a bridge project may exceed the original estimate due to unexpected material price increases and additional labor requirements.


299. Project Risk Register

Definition: A project risk register is a document that tracks potential risks, including their likelihood, impact, and strategies for mitigation. Example: In a high-rise construction project, the risk register might include risks such as labor shortages, material delays, and extreme weather events.


300. Rework

Definition: Rework refers to tasks that need to be redone due to errors, defects, or changes in design after initial completion. Example: In a school construction project, rework may involve fixing incorrectly installed electrical outlets that were not in line with the approved design.


301. Plant and Equipment

Definition: Plant and equipment refer to the heavy machinery, tools, and vehicles used in the construction process. Example: In a road construction project, plant and equipment include bulldozers, excavators, cranes, and concrete mixers.


302. Baseline Budget

Definition: The baseline budget is the original, approved budget for the project, used as a reference to measure financial performance and control costs. Example: In a residential development project, the baseline budget includes estimates for materials, labor, and equipment, with any deviations monitored closely.


303. Performance Guarantee

Definition: A performance guarantee is a contract clause that ensures the contractor will complete the project as specified or face financial penalties. Example: A contractor building a factory provides a performance guarantee, ensuring the project will be completed to the client's standards, or else a portion of the payment will be forfeited.


304. Contract Closeout

Definition: Contract closeout is the final phase of a project, involving the completion of outstanding work, final payments, and the resolution of claims. Example: In a commercial office project, the contract closeout includes ensuring that all punch list items are addressed, all payments are made, and any remaining disputes are resolved.


305. Cost Code

Definition: A cost code is a numerical code used to track specific costs associated with various activities or tasks within a project. Example: In a hospital project, a cost code is assigned to each task, such as plumbing, electrical work, and interior finishing, to monitor expenses accurately.


306. Warranties

Definition: Warranties are guarantees provided by contractors or suppliers that specific work or materials will meet certain standards for a defined period. Example: In a shopping mall project, the contractor provides a warranty that the roofing materials will last at least 10 years without significant issues.


307. Completion Certificate

Definition: A completion certificate is a legal document issued to confirm that the construction project has been completed according to the contract and is ready for use. Example: In a housing development, the contractor receives a completion certificate after finishing all the required work and passing the final inspection.


308. Trade Contractor

Definition: A trade contractor is a specialized subcontractor hired to perform specific tasks such as electrical, plumbing, or carpentry work. Example: In a hotel construction project, a trade contractor is hired to install all the plumbing systems, including water supply and drainage.


309. Certificate of Payment

Definition: A certificate of payment is issued by the project manager or architect to authorize the client to release funds to the contractor for work completed. Example: After completing the framing of a commercial building, the contractor receives a certificate of payment, allowing them to request partial payment from the client.


310. Daily Construction Report (DCR)

Definition: A daily construction report is a log that records the day-to-day activities, progress, and issues encountered on the construction site. Example: In a residential construction project, the site manager completes a DCR documenting the number of workers on-site, tasks completed, and any safety incidents.


311. Construction Mock-Up

Definition: A construction mock-up is a full-scale model of a part of the project, used to test and evaluate materials, finishes, and techniques. Example: In a high-rise building project, the contractor creates a mock-up of a typical apartment unit to demonstrate the finishes, plumbing, and electrical systems to the client.


312. Material Escalation Clause

Definition: A material escalation clause allows for adjustments in the contract price if the cost of materials increases significantly during the project. Example: In a highway construction project, the contractor includes a material escalation clause to protect against unexpected increases in the cost of steel and asphalt.


313. Construction Sequencing

Definition: Construction sequencing refers to the planned order in which tasks will be completed, ensuring an efficient flow of work without interruptions. Example: In a residential tower project, construction sequencing dictates that plumbing work starts after the walls are built but before electrical installations.


314. Mobilization Advance

Definition: Mobilization advance is an upfront payment made to the contractor to help cover initial expenses like setting up the site and ordering materials. Example: In a bridge construction project, the contractor receives a mobilization advance to cover the costs of bringing in heavy machinery and setting up the construction camp.


315. Cost Report

Definition: A cost report is a document that tracks the expenses of a project over time, comparing actual costs to the budget and highlighting variances. Example: In a commercial development, the contractor provides a monthly cost report showing that material expenses are slightly under budget, but labor costs have exceeded estimates.


316. Final Account

Definition: The final account is a comprehensive statement detailing the total cost of the project, including all variations, payments, and outstanding amounts. Example: After completing a high-rise office tower, the contractor submits the final account to the client, documenting all costs and settling any remaining balances.


317. Building Information Modeling (BIM)

Definition: BIM is a digital representation of the physical and functional characteristics of a building, used to facilitate planning, design, and construction processes. Example: In the construction of a stadium, BIM is used to create 3D models of the structure, helping the team visualize how different systems interact and identify potential conflicts before construction begins.


318. Unit Rate

Definition: The unit rate is the cost per unit of a specific task or material, often used to calculate the total cost based on quantities. Example: In a road construction project, the unit rate for asphalt is calculated per ton, allowing the contractor to estimate the total cost of paving based on the required quantity.


319. Non-Conformance Report (NCR)

Definition: An NCR is issued when a part of the project does not meet the required standards or specifications, identifying what corrective actions are needed. Example: In a shopping mall project, an NCR is issued for a section of flooring that was installed with the wrong tiles, requiring the contractor to replace it.


320. Critical Path Method (CPM)

Definition: CPM is a project management technique that identifies the longest sequence of tasks in a project, helping to determine the minimum project duration. Example: In a hospital construction project, CPM is used to identify that the critical path includes tasks like structural framing, roofing, and electrical installations, which must be completed on time to avoid delays.



321. Safety Plan

Definition: A safety plan outlines the procedures and protocols to protect workers from injury and ensure a safe construction site. Example: In a high-rise building project, the safety plan includes wearing hard hats, fall protection systems, and regular safety drills.


322. Budget Overrun

Definition: A budget overrun occurs when the actual costs of a project exceed the initial budget estimates. Example: A contractor faces a budget overrun in a hospital project due to unexpected material price increases and delays caused by adverse weather.


323. Float

Definition: Float, also known as slack, is the amount of time a task can be delayed without affecting the overall project timeline. Example: In a road construction project, a task like landscaping may have a float of two weeks, meaning it can be delayed without impacting the completion date.


324. Stakeholder Engagement

Definition: Stakeholder engagement involves actively involving all stakeholders, such as the client, community, and regulatory bodies, in the project process. Example: In the construction of a new community center, the contractor holds stakeholder meetings to gather input from local residents on the design and amenities.


325. Lean Construction

Definition: Lean construction is a methodology that focuses on minimizing waste and improving efficiency in the construction process. Example: In a shopping mall project, lean construction is used to streamline the supply chain, reducing material waste by ensuring that only the necessary amount of materials is delivered to the site.


326. Cost Plus Incentive Fee (CPIF) Contract

Definition: A CPIF contract reimburses the contractor for actual costs and provides an additional incentive fee if the project is completed under budget or ahead of schedule. Example: A contractor working on a school project may receive a bonus for completing the project ahead of schedule and under budget, in addition to the reimbursement of all costs.


327. Safety Audit

Definition: A safety audit is an official inspection of a construction site to ensure compliance with safety regulations and identify potential hazards. Example: In a bridge project, the contractor conducts regular safety audits to check that all workers are following safety protocols and that equipment is in proper working condition.


328. Cost Plus Fixed Fee (CPFF) Contract

Definition: A CPFF contract reimburses the contractor for actual costs and provides a fixed fee for profit, regardless of the project's final cost. Example: In a large infrastructure project, the contractor receives a fixed fee of $500,000 in addition to the reimbursement of costs for labor and materials.


329. Claims Avoidance

Definition: Claims avoidance refers to the strategies used to prevent disputes or claims for additional time or payment in a construction project. Example: A contractor working on a residential tower uses clear communication and thorough documentation to avoid disputes over scope changes, helping to avoid claims from the client.


330. Jobsite Layout Plan

Definition: A jobsite layout plan shows the arrangement of all temporary facilities, storage areas, and equipment on a construction site. Example: In a high-rise construction project, the jobsite layout plan includes the locations of cranes, material storage, worker facilities, and access points for vehicles.


331. Work Breakdown Structure (WBS)

Definition: The WBS is a hierarchical breakdown of the project into smaller, manageable tasks and deliverables. Example: In a hospital construction project, the WBS breaks the project into major components like foundation work, structural framing, electrical systems, and finishing.


332. Easement

Definition: An easement is a legal right to use another person's land for a specific purpose, such as installing utility lines or accessing a construction site. Example: A contractor building a new road may need an easement to access a neighboring property to install drainage pipes.


333. Joint Venture Agreement

Definition: A joint venture agreement is a contract between two or more parties to collaborate on a specific project, sharing resources, risks, and profits. Example: Two construction firms enter into a joint venture to build an international airport, with each company providing specialized skills and equipment.


334. Progress Claim

Definition: A progress claim is a request for payment submitted by the contractor to the client, based on the percentage of work completed. Example: In a residential complex project, the contractor submits monthly progress claims to receive payment for work completed on each building phase.


335. Risk Transfer

Definition: Risk transfer involves shifting the responsibility for certain risks to another party, usually through insurance or contractual clauses. Example: In a commercial building project, the contractor transfers the risk of equipment damage to an insurance company by purchasing builder's risk insurance.


336. Pre-Construction Services

Definition: Pre-construction services include planning, budgeting, and design consultation provided by the contractor before the actual construction begins. Example: In a hospital project, pre-construction services might include value engineering, where the contractor works with the client to optimize design elements and reduce costs before construction starts.


337. Project Punch List

Definition: A project punch list is a document listing incomplete or defective work that must be addressed before final payment is made. Example: In a retail store construction project, the punch list includes tasks like repainting walls and adjusting the alignment of light fixtures before the project is considered complete.


338. Certificate of Completion

Definition: A certificate of completion is issued to confirm that all construction work has been finished and that the building is ready for use. Example: After completing a shopping mall, the contractor receives a certificate of completion, allowing tenants to start moving into their spaces.


339. Allowance

Definition: An allowance is a specified amount set aside in the project budget for items that are not fully defined at the time of contracting. Example: In a home construction project, an allowance might be set aside for kitchen appliances, with the final selection and pricing to be determined later.


340. Schedule of Rates

Definition: A schedule of rates is a list of unit prices for materials, labor, and equipment, used to calculate the cost of work in a construction contract. Example: In a road project, the contractor uses the schedule of rates to determine the cost of paving each kilometer of the highway based on the specified materials and labor.


341. Insurance Certificate

Definition: An insurance certificate is a document that provides proof of insurance coverage, often required before work on a construction project can begin. Example: Before starting work on a large office building, the contractor submits an insurance certificate showing that they have liability and builder's risk coverage.


342. Subrogation

Definition: Subrogation refers to the legal right of an insurance company to pursue a third party responsible for damages after compensating the insured party. Example: If a construction accident is caused by faulty equipment, the insurance company may subrogate the manufacturer after covering the contractor's losses.


343. Project Management Office (PMO)

Definition: A PMO is a centralized unit within an organization that provides support and oversight for managing projects, ensuring consistency and best practices. Example: In a large construction company, the PMO oversees multiple projects, providing guidance on scheduling, risk management, and quality control.


344. Construction Cost Index (CCI)

Definition: The CCI is a metric used to track changes in construction costs over time, factoring in labor, material, and equipment prices. Example: A developer monitors the CCI to estimate the budget for a new residential tower, adjusting for inflation and material price fluctuations.


345. Interim Payment

Definition: An interim payment is a partial payment made to the contractor for work completed during a specific period, usually made at regular intervals. Example: In a high-rise construction project, the contractor receives interim payments every month based on the percentage of work completed, such as the foundation, framing, and roofing stages.


346. Project Acceleration

Definition: Project acceleration involves speeding up the completion of tasks to meet a tighter deadline, often by increasing resources or working overtime. Example: In a hotel project, the contractor accelerates construction by adding night shifts to ensure that the building is completed in time for the grand opening.


347. Cost Overrun

Definition: A cost overrun occurs when the actual costs of a project exceed the initial budget, often due to changes in scope, delays, or unforeseen issues. Example: A residential development experiences a cost overrun due to delays caused by adverse weather, requiring additional labor and materials to complete the project.


348. Performance Specification

Definition: A performance specification defines the desired outcome or function of a system or component, without specifying how it should be achieved. Example: In a data center project, the performance specification might require the HVAC system to maintain a specific temperature and humidity range, leaving the choice of system to the contractor.


349. Retained Risk

Definition: Retained risk refers to the risks that remain with the project owner or contractor after risk mitigation strategies have been implemented. Example: In a commercial building project, retained risk might include unforeseen changes in material prices, which the contractor must absorb without passing costs to the client.


350. Procurement Plan

Definition: A procurement plan outlines the process for acquiring the goods and services needed for a construction project, detailing timelines, suppliers, and contracts. Example: In a highway project, the procurement plan specifies when and where to source asphalt, reinforcing steel, and heavy machinery, ensuring timely delivery to the site.


351. Value Engineering

Definition: Value engineering is a systematic approach to improving project efficiency by optimizing costs without compromising quality or functionality. Example: In a university construction project, value engineering might suggest using cost-effective building materials that still meet the required durability and aesthetic standards.


352. Bid Evaluation

Definition: Bid evaluation is the process of reviewing and comparing contractor bids to select the most qualified and cost-effective option. Example: In a bridge construction project, the client evaluates multiple bids, considering factors like price, experience, and timeline, before awarding the contract.


353. Critical Task

Definition: A critical task is a project activity that must be completed on time to prevent delays in the overall schedule. Example: In a skyscraper construction project, pouring the concrete foundation is a critical task that must be finished before any further work can continue.


354. Project Commissioning

Definition: Project commissioning is the process of verifying that all systems and components of a building or infrastructure are properly installed and functioning as intended. Example: In a new airport terminal, the commissioning process involves testing the HVAC, electrical, and fire safety systems to ensure they meet operational standards before opening.


355. Turnover Package

Definition: A turnover package contains all documentation, manuals, and warranties required to operate and maintain the completed building, delivered to the client at the end of the project. Example: After completing a hospital, the contractor provides the turnover package, which includes as-built drawings, equipment warranties, and user manuals for the building systems.


356. Surety Bond

Definition: A surety bond is a contract between the client, contractor, and bonding company that guarantees the contractor will fulfill their obligations, or the bonding company will cover the losses. Example: In a large-scale government project, the contractor provides a surety bond to reassure the client that the work will be completed according to the contract terms.


357. Procurement Strategy

Definition: A procurement strategy is a plan that outlines how the goods and services required for the project will be sourced, focusing on cost, quality, and delivery timelines. Example: In a road project, the procurement strategy might involve bulk purchasing materials like asphalt and steel to get discounts and ensure timely supply.


358. Precast Concrete

Definition: Precast concrete refers to concrete elements that are manufactured off-site and then transported to the construction site for installation. Example: In a parking structure project, precast concrete panels are fabricated in a factory and then transported to the site for quick assembly, speeding up construction.


359. Change Control

Definition: Change control is the process of managing and documenting any changes to the project scope, budget, or schedule to ensure proper oversight and approval. Example: In a high-rise apartment project, the client requests changes to the interior layout, which are managed through the change control process to update the design, cost, and schedule.


360. Demobilization Plan

Definition: A demobilization plan outlines the steps required to safely remove all equipment, personnel, and materials from the construction site once the project is completed. Example: After finishing a stadium, the contractor follows a demobilization plan to dismantle temporary site offices, remove machinery, and clean up the site.



361. Risk Allocation

Definition: Risk allocation refers to assigning responsibility for potential risks to specific parties in the contract, such as the client, contractor, or suppliers. Example: In a power plant construction project, the risk of material price increases might be allocated to the contractor, while design risks could be the client's responsibility.


362. Resource Smoothing

Definition: Resource smoothing involves adjusting the allocation of resources to avoid periods of high demand while keeping the project on schedule. Example: In a highway construction project, the contractor may delay non-critical tasks to ensure that the necessary labor and equipment are available for critical tasks.


363. Notice to Proceed

Definition: A notice to proceed is a formal letter from the client to the contractor authorizing the start of construction work. Example: After signing the contract for a commercial office building, the contractor receives a notice to proceed, allowing them to begin mobilization and site setup.


364. Baseline Cost Estimate

Definition: A baseline cost estimate is the original project cost estimate, used as a reference point for measuring actual costs and managing the budget. Example: In a residential tower project, the baseline cost estimate includes initial projections for labor, materials, and equipment, serving as a benchmark throughout the project.


365. Final Payment Certificate

Definition: The final payment certificate is a document issued by the project manager or architect authorizing the release of the remaining payment to the contractor once all work is completed. Example: After finishing a shopping mall project and addressing all defects, the contractor receives the final payment certificate from the client.


366. Backlog Management

Definition: Backlog management refers to overseeing a collection of uncompleted tasks or pending projects that need to be prioritized and scheduled. Example: A contractor with several housing developments in progress uses backlog management to organize and schedule each project's pending work.


367. Construction Manager at Risk (CMAR)

Definition: CMAR is a project delivery method where the construction manager assumes the risk for delivering the project on time and within budget. Example: In a university campus expansion project, the construction manager uses CMAR to ensure that the new academic buildings are completed within the guaranteed maximum price.


368. Cost Forecasting

Definition: Cost forecasting involves predicting future project expenses based on current spending trends and potential risks, allowing adjustments to be made to stay within budget. Example: In a large hospital project, cost forecasting is used to anticipate and plan for potential increases in material prices or labor costs.


369. Constructability

Definition: Constructability refers to how easily and efficiently a design can be built, considering factors like material availability, site conditions, and labor skills. Example: In a high-rise construction project, constructability reviews are conducted to ensure that the design allows for safe, efficient construction with available materials.


370. Safety Risk Assessment

Definition: A safety risk assessment is an evaluation of potential hazards on a construction site, identifying risks and implementing measures to prevent accidents. Example: In a skyscraper construction project, the safety risk assessment includes identifying risks like falls from height, heavy equipment accidents, and exposure to hazardous materials.


371. Provisional Acceptance

Definition: Provisional acceptance is the client's acknowledgment that the project is substantially complete, allowing the facility to be used while minor works are finalized. Example: In a shopping center project, the client grants provisional acceptance, allowing retailers to begin setting up their stores while landscaping work continues.


372. Time and Materials Contract

Definition: A time and materials contract reimburses the contractor for labor and materials based on actual costs, with an additional fee for overhead and profit. Example: In a renovation project, the client agrees to a time and materials contract, paying the contractor for the actual hours worked and materials used, plus a fixed markup.


373. Kickoff Meeting

Definition: A kickoff meeting is the first formal meeting held at the beginning of a construction project to align all parties on the project's goals, timeline, and responsibilities. Example: Before starting work on a new office complex, the client, contractor, and design team hold a kickoff meeting to review the project schedule and assign roles.


374. Fast-Tracking

Definition: Fast-tracking is a scheduling technique where project activities are overlapped to reduce the overall duration, even if this increases risk or costs. Example: In a hotel construction project, fast-tracking might involve beginning interior work while the exterior structure is still being completed to meet a tight deadline.


375. Mitigation Plan

Definition: A mitigation plan outlines the strategies and actions to reduce the likelihood or impact of identified risks in a construction project. Example: In a residential building project, a mitigation plan for potential delays due to weather might include ordering materials in advance and planning indoor work during rainy seasons.


376. Subcontractor

Definition: A subcontractor is a specialized contractor hired by the main contractor to perform specific tasks, such as electrical work or plumbing, on a construction project. Example: In a school construction project, the main contractor hires an HVAC subcontractor to install the heating, ventilation, and air conditioning systems.


377. BOQ (Bill of Quantities)

Definition: The Bill of Quantities is a document that lists all materials, labor, and services required for a project, with estimated quantities and costs for each. Example: In a road project, the BOQ includes detailed estimates of asphalt, concrete, gravel, and labor needed to complete the highway.


378. Lead Time

Definition: Lead time is the amount of time required between ordering materials or equipment and their delivery to the construction site. Example: In a commercial building project, the lead time for ordering custom windows is six weeks, so the contractor plans accordingly to avoid delays.


379. Retention Fund

Definition: A retention fund is a portion of the payment withheld by the client until the project is fully completed and all defects are rectified. Example: In a warehouse construction project, 5% of the total contract value is retained by the client until all punch list items are addressed and the project is signed off.


380. Design-Build-Finance-Operate (DBFO)

Definition: DBFO is a project delivery model where a single entity is responsible for the design, construction, financing, and operation of a facility over a defined period. Example: In a highway construction project, the contractor designs, builds, finances, and operates the road for 20 years, receiving payments from toll revenues.


381. Critical Incident Reporting

Definition: Critical incident reporting involves documenting any significant safety or operational issues that occur on the construction site and require immediate attention. Example: In a high-rise construction project, the collapse of scaffolding is reported as a critical incident, triggering an investigation and corrective actions.


382. Material Takeoff (MTO)

Definition: Material takeoff refers to the process of measuring quantities of materials required for a construction project based on the design drawings and specifications. Example: In a residential project, the contractor performs a material takeoff to calculate the exact amount of bricks, cement, and steel needed for the structure.


383. Interim Certificate

Definition: An interim certificate is issued by the project manager or architect during the project to certify that part of the work has been completed and payment is due. Example: In a commercial building project, an interim certificate is issued after the completion of the foundation, allowing the contractor to request partial payment.


384. Supply Chain Management

Definition: Supply chain management in construction involves overseeing the sourcing, production, and delivery of materials to ensure they arrive on-site when needed and in the right quantities. Example: In a large infrastructure project, the contractor implements supply chain management to coordinate the timely delivery of steel beams and concrete while minimizing storage costs on-site.


385. Completion Bond

Definition: A completion bond is a guarantee provided by a bonding company ensuring that the contractor will complete the project according to the contract, or the bonding company will cover the costs. Example: A contractor working on a government-funded school project provides a completion bond to assure the client that the work will be finished on time and within budget.


386. Outsourcing

Definition: Outsourcing involves contracting out specific tasks or services to external companies or specialists to reduce costs or access expertise. Example: In a hospital construction project, the contractor outsources the installation of specialized medical equipment to a company with experience in hospital systems.


387. Cost Plus Contract

Definition: A cost-plus contract reimburses the contractor for actual costs incurred, plus an additional fee for overhead and profit, which is typically a percentage of the total costs. Example: In a custom home construction project, the contractor is reimbursed for materials and labor costs, with a 10% fee added for profit.


388. Bidding Process

Definition: The bidding process is the formal procedure by which contractors submit proposals or bids to compete for a construction project contract. Example: For a new highway project, multiple contractors participate in the bidding process, submitting proposals outlining their costs, timelines, and qualifications.


389. Force Majeure

Definition: Force majeure refers to unforeseen events, such as natural disasters, that prevent the contractor from fulfilling their obligations under the contract. Example: In a coastal construction project, a hurricane causes significant delays, and the contractor invokes the force majeure clause to avoid penalties for the missed deadlines.


390. Insurance Coverage

Definition: Insurance coverage protects the contractor, client, and workers against risks such as property damage, accidents, and liability claims during the construction project. Example: In a high-rise office project, the contractor secures builder's risk insurance to cover potential damage to the building during construction.


391. Jobsite Safety

Definition: Jobsite safety refers to the measures and protocols implemented to protect workers from accidents and hazards while on the construction site. Example: In a road construction project, the contractor enforces jobsite safety by requiring all workers to wear high-visibility vests and hard hats, as well as conducting regular safety drills.


392. Retainage

Definition: Retainage is the portion of the payment withheld by the client until the project is completed and all obligations are met, typically released after the final inspection. Example: In a hotel construction project, the client withholds 10% of the payment as retainage, which is released once all defects have been corrected after project completion.


393. Cost Estimate

Definition: A cost estimate is a detailed approximation of the total expenses required to complete a construction project, including labor, materials, and equipment. Example: A contractor provides a cost estimate of $10 million for constructing a new office building, covering all phases from excavation to finishing work.


394. Prequalification

Definition: Prequalification is the process of assessing the qualifications, experience, and financial stability of contractors or suppliers before inviting them to bid on a project. Example: A developer prequalifies contractors for a commercial office building project, ensuring they have the necessary experience and financial capacity to complete the work.


395. Cost-to-Complete

Definition: Cost-to-complete refers to the estimated amount of money required to finish a construction project, based on the remaining work and resources needed. Example: In a school construction project, the contractor calculates the cost-to-complete after the foundation and structural framing are finished, providing an updated budget for the client.


396. Performance Review

Definition: A performance review is an evaluation of a contractor's progress, efficiency, and quality of work during the construction project. Example: In a high-rise building project, the client conducts monthly performance reviews to assess whether the contractor is meeting deadlines, staying within budget, and delivering high-quality work.


397. Latent Defects

Definition: Latent defects are hidden flaws in a construction project that may not become apparent until after completion, often leading to claims or disputes. Example: Several months after completing a shopping mall, latent defects in the building's plumbing system cause leaks, requiring the contractor to return and make repairs.


398. Resource Allocation

Definition: Resource allocation refers to the process of assigning labor, equipment, and materials to specific tasks in a construction project to optimize efficiency. Example: In a residential construction project, the project manager allocates carpenters to frame the building while electricians are scheduled to install wiring afterward.


399. Hard Costs

Definition: Hard costs are the tangible, direct expenses related to the physical construction of a project, such as labor, materials, and equipment. Example: The hard costs for building a new hospital include the cost of concrete, steel, windows, and the wages paid to construction workers.


400. Submittals

Definition: Submittals are documents, drawings, and samples provided by the contractor to the client or design team for approval before the construction work begins. Example: In a university project, the contractor submits samples of flooring materials and wall finishes to the architect for approval before proceeding with installation.


401. Substantial Completion

Definition: Substantial completion is the stage in a construction project where the work is sufficiently complete, allowing the client to use or occupy the building, even if minor items remain unfinished. Example: In a hotel project, substantial completion is achieved once the guest rooms, lobby, and essential services are operational, even though some painting and landscaping tasks are still pending.


402. As-Built Drawings

Definition: As-built drawings are updated project plans that reflect any changes made during construction, showing how the project was actually built. Example: After completing an office tower, the contractor provides the client with as-built drawings, showing the actual locations of electrical wiring and plumbing, which may differ from the original plans.


403. Design-Build Contract

Definition: A design-build contract combines both design and construction responsibilities into a single contract, providing the client with a single point of responsibility. Example: A school project is completed under a design-build contract, with the contractor responsible for both designing the school and constructing it to the agreed specifications.


404. Contingency Plan

Definition: A contingency plan outlines steps to be taken in the event of unexpected disruptions, such as weather delays or material shortages, to minimize the impact on the project timeline and budget. Example: In a high-rise construction project, the contractor has a contingency plan that includes renting additional equipment if critical machinery breaks down unexpectedly.


405. Site Survey

Definition: A site survey is a detailed examination and measurement of a construction site to assess its topography, utilities, and boundaries before construction begins. Example: In a highway project, the engineering team conducts a site survey to map the terrain, identify existing utilities, and plan the road's alignment.


406. Cost Plus Percentage Contract

Definition: A cost-plus percentage contract reimburses the contractor for actual costs incurred and adds a percentage of those costs as profit. Example: In a custom home construction project, the contractor is reimbursed for all labor and material expenses, with an additional 10% fee added as profit.


407. Bonding Capacity

Definition: Bonding capacity refers to the maximum amount of work a contractor can undertake, as determined by a bonding company, based on the contractor’s financial stability and past performance. Example: A contractor with a bonding capacity of $5 million is eligible to bid on government projects of that value or less.


408. Cost Plan

Definition: A cost plan outlines the estimated budget for a construction project, broken down into categories such as materials, labor, and equipment. Example: In a commercial office project, the cost plan includes projections for concrete, steel, HVAC systems, and labor costs.


409. Project Milestone

Definition: A project milestone is a significant event or achievement in the project timeline that marks the completion of a key phase or task. Example: In a residential development, the completion of the foundation is considered a major milestone, allowing the contractor to proceed with structural framing.


410. Construction Schedule

Definition: The construction schedule is a detailed plan that outlines the sequence of activities and tasks required to complete a construction project within a specified timeframe. Example: In a retail complex project, the construction schedule breaks down tasks such as excavation, foundation work, framing, and interior finishing, with deadlines for each phase.


411. General Contractor

Definition: A general contractor is the main contractor responsible for overseeing the entire construction project, including hiring subcontractors, managing the site, and ensuring the project meets the client’s requirements. Example: In a shopping mall project, the general contractor is responsible for coordinating all aspects of construction, from the foundation to the final interior finishes.


412. Turnkey Project

Definition: A turnkey project is a construction contract in which the contractor is responsible for the entire project, delivering a fully completed, ready-to-use facility to the client. Example: A developer hires a contractor to complete a turnkey apartment complex, where the contractor handles everything from design and construction to installing fixtures and final cleaning.


413. Design Review

Definition: A design review is a formal evaluation of the construction design by the project team and client, ensuring it meets the project's objectives and specifications. Example: In a bridge construction project, the design review includes an analysis of the structural plans to confirm they meet safety and performance standards before construction begins.


414. Bid Bond

Definition: A bid bond is a financial guarantee provided by a contractor to ensure that they will enter into a contract if selected as the winning bidder. Example: In a government infrastructure project, the contractor submits a bid bond to assure the client that they will sign the contract and begin work if their bid is accepted.


415. Mobilization

Definition: Mobilization refers to the process of preparing the construction site, moving in equipment, and setting up facilities before work begins. Example: In a large office building project, mobilization includes setting up temporary site offices, bringing in construction machinery, and installing fencing around the perimeter.


416. Baseline Schedule

Definition: The baseline schedule is the original project schedule approved by the client, used as a reference point for measuring progress and performance. Example: In a stadium construction project, the baseline schedule includes detailed timelines for excavation, foundation work, and structural framing, with all tasks monitored against this baseline.


417. Change Order

Definition: A change order is a formal document issued to modify the scope, cost, or timeline of a construction project, requiring approval from both the client and contractor. Example: In a residential project, a change order is issued to add an additional room, increasing the project's scope and budget.


418. Retrospective Schedule

Definition: A retrospective schedule is a review of the actual progress of a project compared to the original baseline schedule, often used to identify delays or inefficiencies. Example: In a university construction project, a retrospective schedule is created to assess the impact of weather delays on the completion of the roof and exterior work.


419. Handover

Definition: Handover refers to the formal transfer of the completed project from the contractor to the client, often marked by the issuance of the final completion certificate. Example: In a corporate office project, the contractor hands over the building to the client once all construction work is complete and any defects have been rectified.


420. Cost Analysis

Definition: Cost analysis is the process of breaking down project expenses to understand where the money is being spent and identify potential cost-saving opportunities. Example: In a shopping mall project, the contractor performs a cost analysis to determine whether using alternative materials could reduce overall construction costs.


421. Construction Drawings

Definition: Construction drawings are detailed plans that show the layout, dimensions, and specifications of a building or structure, used to guide construction work. Example: In a hospital project, the construction drawings include floor plans, elevations, and sections, detailing the exact dimensions and placement of walls, windows, and doors.


422. Prime Contractor

Definition: A prime contractor is the main contractor who has direct responsibility for the construction project, often hiring subcontractors to complete specialized tasks. Example: In a bridge construction project, the prime contractor oversees all aspects of the project, including hiring subcontractors for concrete work and steel reinforcement.


423. Boilerplate

Definition: Boilerplate refers to standard contract clauses that are commonly used in construction agreements to address legal and procedural issues, such as dispute resolution and termination. Example: In a construction contract for a school, the boilerplate clauses include provisions for handling delays, payment terms, and changes in scope.


424. Progress Payment

Definition: A progress payment is a partial payment made to the contractor based on the percentage of work completed during a specific period. Example: In a hotel construction project, the contractor submits progress payment requests monthly, based on the completion of each phase, such as foundation, framing, and finishing.


425. Letter of Intent (LOI)

Definition: A letter of intent is a document issued by the client indicating their intention to award a construction contract, allowing the contractor to begin preliminary work while the final contract is being finalized. Example: In a commercial development, the client issues a letter of intent to the contractor, allowing them to start mobilizing equipment and setting up the site before the formal contract is signed.


426. Joint Check Agreement

Definition: A joint check agreement is an arrangement between the client, contractor, and subcontractor to ensure that subcontractors are paid directly by the client for their work. Example: In a road construction project, the client and contractor enter into a joint check agreement with the asphalt supplier to guarantee timely payment for materials.


427. Material Escalation Clause

Definition: A material escalation clause allows for adjustments to the contract price if the cost of materials increases significantly during the course of the project. Example: In a commercial building project, the contractor includes a material escalation clause to account for potential increases in the price of steel and concrete.


428. Workforce Management

Definition: Workforce management involves overseeing the allocation and scheduling of labor to ensure that construction tasks are completed efficiently and on time. Example: In a residential project, workforce management ensures that carpenters, electricians, and plumbers are scheduled appropriately to avoid delays and maximize productivity.


429. Performance Review

Definition: A performance review is an evaluation of the contractor’s or subcontractor’s progress, quality of work, and adherence to schedule and budget. Example: In a large office project, the client conducts regular performance reviews to assess whether the contractor is meeting the agreed-upon milestones and quality standards.


430. Scope Definition

Definition: Scope definition outlines the specific tasks, deliverables, and goals of a construction project, ensuring that all parties understand their responsibilities and expectations. Example: In a bridge construction project, the scope definition includes detailed descriptions of the materials, labor, and timelines required to complete each phase of work.


431. Master Schedule

Definition: A master schedule is the overall project schedule that outlines all tasks, deadlines, and milestones, serving as the primary timeline for the entire project. Example: In a shopping mall construction project, the master schedule includes timelines for excavation, foundation, structural work, interior finishing, and landscaping.


432. Holdback

Definition: A holdback is a percentage of the payment withheld by the client until the contractor fulfills all obligations, such as completing outstanding tasks or rectifying defects. Example: In a commercial office project, the client retains 5% of the total payment as a holdback, which is released once the final inspection confirms that all work has been completed satisfactorily.


433. Work Sequence

Definition: Work sequence refers to the order in which construction tasks are performed, ensuring that each task is completed in the most efficient manner to avoid delays. Example: In a residential construction project, the work sequence dictates that the foundation must be poured before framing can begin.


434. Cost-Plus Contract

Definition: A cost-plus contract reimburses the contractor for all costs incurred during construction, plus an agreed-upon fee or percentage for profit. Example: In a custom home construction project, the contractor is reimbursed for labor and material costs, with an additional 15% fee added for overhead and profit.


435. Construction Warranty

Definition: A construction warranty is a guarantee provided by the contractor that certain aspects of the project, such as materials and workmanship, will meet specified standards for a set period. Example: In a new apartment complex, the contractor provides a one-year construction warranty, covering defects in materials and workmanship during that time.


436. Scope of Work (SOW)

Definition: The scope of work is a detailed description of the tasks, responsibilities, and deliverables required to complete a construction project. Example: In a bridge construction project, the SOW includes tasks such as site preparation, foundation work, and concrete pouring, along with deadlines for each phase.


437. Construction Claim

Definition: A construction claim is a formal request made by the contractor or client for additional compensation or time due to unforeseen circumstances or changes in scope. Example: In a road construction project, the contractor files a claim for extra costs incurred due to unexpected soil conditions that required additional excavation.


438. Liquidated Damages Clause

Definition: A liquidated damages clause specifies a financial penalty that the contractor must pay if the project is not completed by the agreed-upon deadline. Example: In a hotel construction project, the contract includes a liquidated damages clause requiring the contractor to pay $5,000 per day for delays beyond the completion date.


439. Project Cost Management

Definition: Project cost management involves planning, estimating, budgeting, and controlling costs to ensure that the project is completed within the approved budget. Example: In a commercial building project, the contractor uses cost management to track expenses for labor, materials, and equipment, ensuring that the project stays within budget.


440. Final Handover

Definition: Final handover is the stage where the contractor officially transfers the completed project to the client, signifying the end of construction and the start of occupancy or operation. Example: In a shopping mall project, the final handover occurs after all work is completed, inspections are passed, and the client accepts the building.


441. Budget Estimate

Definition: A budget estimate is an approximation of the total cost of a construction project, used for initial planning and decision-making. Example: A contractor provides a budget estimate for building a new residential complex, including the costs of labor, materials, and equipment.


442. Project Deliverable

Definition: A project deliverable is a tangible or intangible output produced during the project, such as a completed building, a report, or a set of drawings. Example: In a hospital construction project, the completed building, including all medical facilities and equipment, is considered the final project deliverable.


443. Field Work

Definition: Fieldwork refers to the tasks and activities performed on the construction site, such as excavation, concrete pouring, or electrical installation. Example: In a road construction project, fieldwork includes activities like clearing the site, laying the foundation, and paving the roadway.


444. Site Manager

Definition: A site manager oversees daily construction activities on-site, ensuring that work is completed on time, within budget, and according to specifications. Example: In a residential project, the site manager is responsible for coordinating workers, managing materials, and addressing any issues that arise on the construction site.


445. General Conditions

Definition: General conditions are the administrative, logistical, and operational requirements of a construction project, often including project management, temporary utilities, and safety measures. Example: In a high-rise construction project, general conditions cover costs such as site office setup, safety equipment, and worker transportation.


446. Cost Report

Definition: A cost report is a document that tracks project expenses over time, comparing actual costs with the budget and highlighting any variances. Example: In a university construction project, the contractor provides monthly cost reports to the client, detailing expenses for materials, labor, and equipment.


447. Payment Bond

Definition: A payment bond is a guarantee provided by the contractor to ensure that subcontractors and suppliers are paid for their work and materials. Example: In a bridge construction project, the contractor provides a payment bond to assure the client that all subcontractors and material suppliers will be compensated.


448. Substantial Completion Certificate

Definition: A substantial completion certificate is issued when the project is sufficiently completed for the client to occupy or use the building, even if minor work remains. Example: In a shopping mall project, the contractor receives a substantial completion certificate once the interior spaces are finished, allowing tenants to begin moving in.


449. Direct Labor

Definition: Direct labor refers to the workforce directly involved in performing construction tasks, such as carpenters, electricians, and plumbers. Example: In a commercial office project, direct labor costs include wages paid to the carpenters building the framework and the electricians installing wiring.


450. As-Built Survey

Definition: An as-built survey is a survey conducted after construction is completed to verify that the building or infrastructure matches the design plans. Example: In a highway construction project, an as-built survey is conducted to ensure that the road alignment, elevation, and dimensions conform to the approved design.


451. Project Kickoff

Definition: Project kickoff is the initial meeting held to align all stakeholders on the project objectives, roles, and responsibilities, officially marking the start of the project. Example: In a hospital construction project, the project kickoff meeting involves the client, contractor, and design team discussing the timeline, budget, and scope of work.


452. Field Engineer

Definition: A field engineer works on-site, overseeing technical aspects of the construction process and ensuring that the work adheres to the design and specifications. Example: In a tunnel construction project, the field engineer is responsible for checking the alignment and placement of the tunnel boring machine.


453. Site Layout

Definition: The site layout is the arrangement of temporary facilities, equipment, storage areas, and workspaces on the construction site, designed to optimize efficiency and safety. Example: In a high-rise building project, the site layout includes the positioning of cranes, material storage, and worker facilities to ensure smooth operations.


454. Retrospective Review

Definition: A retrospective review is an evaluation of the project’s progress, identifying lessons learned, successes, and areas for improvement based on past performance. Example: After completing a shopping mall project, the contractor conducts a retrospective review to assess the causes of delays and suggest ways to improve future project scheduling.


455. Construction Overrun

Definition: A construction overrun occurs when the project exceeds the estimated time or budget due to unforeseen circumstances, changes in scope, or delays. Example: In a bridge project, an overrun occurs when unexpected weather conditions cause delays, leading to increased labor and equipment costs.


456. Job Costing

Definition: Job costing involves tracking and analyzing the costs of individual tasks or phases within a construction project to monitor financial performance. Example: In a residential construction project, job costing tracks the expenses associated with framing, plumbing, and electrical work, helping the contractor stay within budget.


457. Green Building

Definition: Green building refers to construction practices that prioritize sustainability, energy efficiency, and minimal environmental impact. Example: In an office tower project, green building techniques include using energy-efficient windows, solar panels, and environmentally friendly materials to reduce the building's carbon footprint.


458. Project Closeout

Definition: Project closeout is the final phase of a construction project, involving the completion of all outstanding tasks, final inspections, and the handover of documentation to the client. Example: In a university construction project, the closeout phase includes finishing landscaping, resolving any defects, and providing the client with as-built drawings and warranties.


459. Subcontractor Agreement

Definition: A subcontractor agreement is a contract between the general contractor and a specialized contractor, outlining the scope of work, payment terms, and responsibilities. Example: In a high-rise construction project, the general contractor signs a subcontractor agreement with a plumbing contractor to install the water and sewage systems.


460. Quantity Surveying

Definition: Quantity surveying involves estimating and managing construction costs to ensure the project stays within budget and meets financial objectives. Example: In a shopping mall project, the quantity surveyor estimates the cost of materials, labor, and equipment, tracking expenses throughout the project to prevent cost overruns.


461. Unit Price Contract

Definition: A unit price contract is a construction agreement where the client pays the contractor a set amount for each unit of work completed, based on predetermined rates. Example: In a road construction project, the contractor is paid per kilometer of road completed, with unit prices set for labor, materials, and equipment.


462. Job Hazard Analysis (JHA)

Definition: Job hazard analysis is the process of identifying and assessing potential safety hazards associated with specific construction tasks and implementing measures to mitigate risks. Example: In a high-rise project, the contractor conducts a JHA before installing scaffolding to ensure that workers are protected from fall risks.


463. Project Contingency

Definition: Project contingency is a reserve of time, money, or resources set aside to cover unexpected risks or changes in the construction project. Example: In a hospital construction project, the contractor includes a 10% contingency in the budget to account for unforeseen expenses like material shortages or weather delays.


464. Safety Net

Definition: A safety net is a physical barrier installed on a construction site to catch falling workers or debris, helping to prevent accidents and injuries. Example: In a bridge construction project, safety nets are installed underneath the work area to catch any tools, materials, or workers that might fall from height.


465. Demobilization

Definition: Demobilization refers to the process of removing equipment, personnel, and temporary facilities from the construction site after the project is completed. Example: After finishing a highway project, the contractor begins demobilization by dismantling temporary offices, moving heavy machinery off-site, and cleaning up the area.


466. Procurement Officer

Definition: A procurement officer is responsible for sourcing and purchasing materials, equipment, and services for the construction project, ensuring timely delivery and cost efficiency. Example: In a commercial building project, the procurement officer negotiates contracts with suppliers for concrete, steel, and glass, ensuring that materials are delivered on schedule.


467. Contractor’s All Risk Insurance (CAR)

Definition: CAR insurance is a comprehensive policy that covers damage to the construction site, materials, and equipment, as well as third-party liability for accidents. Example: In a residential tower project, the contractor takes out CAR insurance to protect against damages caused by fire, theft, or accidents during construction.


468. Work Order

Definition: A work order is an official document authorizing a contractor or subcontractor to begin work on a specific task or phase of a construction project. Example: In a retail store project, the contractor issues a work order to the electrical subcontractor, authorizing them to start installing the lighting and power systems.


469. Critical Path Analysis

Definition: Critical path analysis is a project management technique that identifies the longest sequence of dependent tasks, determining the minimum project duration. Example: In a bridge construction project, critical path analysis shows that excavation, foundation work, and steel reinforcement are the critical tasks that must be completed on time to avoid delays.


470. Non-Compliance Report (NCR)

Definition: An NCR is issued when work performed on the construction site does not meet the project specifications, requiring corrective action to resolve the issue. Example: In a commercial office project, an NCR is issued for the incorrect installation of windows, requiring the contractor to replace them to meet the design specifications.


471. Cost Allocation

Definition: Cost allocation involves distributing project expenses among different tasks, phases, or departments to accurately track spending and ensure budget control. Example: In a hospital project, cost allocation ensures that labor, materials, and equipment costs are properly assigned to each department, such as radiology, surgery, and patient rooms.


472. Permit to Work (PTW)

Definition: A permit to work is an official document issued to authorize specific tasks on a construction site, ensuring that safety protocols and conditions are met before work begins. Example: In a refinery construction project, a PTW is required for any work involving welding, to ensure that fire safety measures are in place and approved by the safety officer.


473. Budget Control

Definition: Budget control involves monitoring and managing the project’s expenses to ensure that costs remain within the approved budget, taking corrective actions as needed. Example: In a shopping mall project, the contractor uses budget control techniques to track actual expenses against the budget, making adjustments to avoid overruns.


474. Project Brief

Definition: A project brief is a detailed document that outlines the project’s objectives, scope, budget, and timelines, serving as a guide for the project team. Example: In a university construction project, the project brief includes the overall goals, design requirements, and estimated costs, ensuring that all stakeholders are aligned.


475. Sublet Agreement

Definition: A sublet agreement is a contract between the contractor and a third party to perform specific tasks or services, such as plumbing or electrical work, on the construction site. Example: In a hospital project, the contractor enters into a sublet agreement with a specialist contractor to install advanced medical gas systems throughout the building.


476. Project Integration Management

Definition: Project integration management ensures that all aspects of the construction project, such as scope, schedule, cost, quality, and risks, are coordinated and aligned with the project’s goals. Example: In a highway construction project, the project manager oversees integration management to ensure that the various teams, from site preparation to asphalt paving, work together seamlessly.


477. RFI (Request for Information)

Definition: An RFI is a formal request made by the contractor or subcontractor to clarify any ambiguities or uncertainties in the project’s drawings or specifications. Example: In a school construction project, the contractor submits an RFI to the architect to clarify the specifications for the roofing materials before placing the order.


478. Certificate of Practical Completion

Definition: A certificate of practical completion is issued when the construction work is complete enough for the client to use the building, although minor work may still be pending. Example: In a corporate office project, the certificate of practical completion is issued once the building is ready for occupancy, even though some landscaping work remains unfinished.


479. Geotechnical Survey

Definition: A geotechnical survey involves analyzing the soil, rock, and groundwater conditions at a construction site to assess its suitability for the project. Example: In a bridge project, the geotechnical survey determines the type of foundation required by analyzing the soil composition and load-bearing capacity at the site.


480. Schedule Variance (SV)

Definition: Schedule variance is the difference between the planned progress and the actual progress of a construction project, used to assess whether the project is on track. Example: In a commercial building project, a negative schedule variance indicates that excavation is behind schedule due to unexpected delays, requiring corrective action.


481. Design Intent

Definition: Design intent refers to the overall vision and goals of the project's design, guiding decisions about aesthetics, functionality, and performance. Example: In a museum construction project, the design intent focuses on creating open, well-lit gallery spaces that enhance the visitor experience, with modern architectural features.


482. Contract Administration

Definition: Contract administration involves managing the day-to-day responsibilities of a construction contract, including tracking compliance, processing payments, and resolving disputes. Example: In a stadium construction project, the contract administrator ensures that the contractor follows the contract terms, processes change orders, and manages claims.


483. Feasibility Study

Definition: A feasibility study is an analysis of the viability of a construction project, considering factors such as cost, site conditions, legal requirements, and potential risks. Example: Before approving the construction of a new airport terminal, the client conducts a feasibility study to assess the project's economic and logistical feasibility.


484. Force Account

Definition: Force account refers to work performed by the client or owner using their own labor, materials, and equipment, rather than hiring a contractor. Example: In a small municipal road project, the city government uses a force account to carry out minor repairs using its own workers and equipment.


485. Detailed Estimate

Definition: A detailed estimate is a comprehensive breakdown of the project costs, including quantities of materials, labor, equipment, and overhead. Example: In a commercial office project, the contractor provides a detailed estimate showing the costs for each building component, such as flooring, walls, and electrical systems.


486. Payment Schedule

Definition: A payment schedule outlines when and how much the client will pay the contractor at various stages of the project, typically based on progress or milestones. Example: In a residential project, the payment schedule is tied to the completion of specific milestones, such as the foundation, framing, and finishing work.


487. Commissioning

Definition: Commissioning is the process of testing and verifying that all systems and components of a building are installed and functioning according to the design specifications. Example: In a hospital project, commissioning includes testing HVAC systems, electrical wiring, and medical equipment to ensure they meet performance standards.


488. Cash Flow Forecast

Definition: A cash flow forecast estimates the flow of cash into and out of the project over time, helping to ensure that funds are available when needed for expenses. Example: In a hotel construction project, the contractor prepares a cash flow forecast to anticipate when payments will be received and when major expenses, such as materials and labor, will be incurred.


489. Material Procurement

Definition: Material procurement involves sourcing and purchasing the materials needed for the construction project, ensuring that they are delivered on time and within budget. Example: In a residential construction project, the contractor procures materials such as cement, steel, and windows, coordinating with suppliers to meet the project timeline.


490. Rebar

Definition: Rebar, short for reinforcing bar, is a steel bar used to reinforce concrete in construction, increasing the material’s tensile strength. Example: In a bridge project, rebar is used in the concrete foundation and columns to provide additional strength and support for the structure.


491. Cost Overrun Report

Definition: A cost overrun report documents any instances where actual project costs exceed the estimated budget, explaining the reasons for the overrun and proposing corrective actions. Example: In a commercial office project, the contractor submits a cost overrun report detailing additional expenses due to unforeseen site conditions that required extra excavation.


492. Architectural Review Board (ARB)

Definition: An ARB is a committee responsible for reviewing and approving building designs, ensuring that they meet aesthetic and zoning requirements. Example: In a historic district project, the ARB reviews the design for a new office building to ensure it aligns with the architectural character of the surrounding area.


493. Piling

Definition: Piling involves driving long, sturdy columns, typically made of steel or concrete, into the ground to provide foundation support for a building or structure. Example: In a coastal construction project, the contractor uses piling to support a high-rise building, ensuring it remains stable despite the soft soil conditions.


494. Warranty Period

Definition: The warranty period is the time during which the contractor guarantees that the work is free from defects, typically covering any repairs or replacements needed. Example: In a commercial building project, the contractor provides a two-year warranty period, ensuring that any structural defects discovered within that time will be repaired at no additional cost to the client.


495. Punch List

Definition: A punch list is a document that lists all incomplete or defective work that needs to be addressed before the project can be considered finished. Example: In a hotel construction project, the punch list includes tasks such as fixing light fixtures, repainting walls, and installing missing hardware before the client takes occupancy.


496. Retainage Release

Definition: Retainage release refers to the process of paying out the final portion of the contractor’s fee that was withheld until all work is completed and approved. Example: In a retail center project, the client releases the retainage after the contractor completes the final inspection and addresses all items on the punch list.


497. Feasibility Analysis

Definition: A feasibility analysis evaluates whether a proposed construction project is practical and achievable, considering factors like cost, regulations, and site conditions. Example: Before starting a large infrastructure project, the contractor conducts a feasibility analysis to determine if the site conditions and budget allow for the proposed design.


498. Design Development (DD)

Definition: Design development is the phase in which the initial project concept is further refined, with detailed drawings and specifications that guide construction. Example: In a museum construction project, the design development phase includes creating detailed plans for the structural system, HVAC, and interior finishes, preparing the project for construction.


499. Bid Tabulation

Definition: Bid tabulation is the process of comparing all bids received from contractors, analyzing them based on price, experience, and qualifications to determine the best option. Example: In a public road project, the client performs bid tabulation to compare contractors' prices and determine which company offers the best value and experience for the job.


500. Final Payment

Definition: Final payment is the last payment made to the contractor once all work has been completed, including any retainage, and the project has been signed off as complete. Example: In a corporate office project, the contractor receives final payment after completing all punch list items, resolving defects, and passing the final inspection.

Fri Sep 6, 2024

Pop-Up Message
Call Us Call Us Guidance